# Aligned DFW-03 Data Center

ERCOT data center · https://askthegrid.com/assets/facilities/aligned-dfw-03-data-center

Aligned Data Centers operates DFW-03, a newly completed two-story 429,603-square-foot hyperscale facility at 3801 Britton Road in Mansfield, Texas, on 27 acres. Construction began June 24, 2024, with a permit completion target of January 27, 2026 and initial capacity anticipated in Q4 2025; the facility reports 3 MW backup generation capacity and supports AI, cloud, and enterprise applications.

## Identity and location

- Operating status: operating
- Asset scope: facility
- Location: 3801 Britton Road, Mansfield, Tarrant County, TX
- Owner: Aligned Data Centers (Mansfield) PROPCO, LLC (exact asset) — https://aligneddc.com/
- Operator: Aligned Data Centers (exact asset) — https://aligneddc.com/
- Developer: Aligned Data Centers (campus) — https://aligneddc.com/

## Power and grid context

- Backup generation: 3 MW · reported · exact asset · as of 2026-07-27 — Operator materials report 3 MW back-up generators in the DFW-03 data-center context.
- ISO/RTO: ERCOT
- Electric utility: Oncor Electric Delivery Company, likely serving the site; exact service confirmation for DFW-03 was not located.
- Substation: On-site electrical substation; the substation's name and electrical rating were not disclosed.

## Development

- Site status: Operating; the regulatory record shows the project as review complete, with construction scheduled to complete January 27, 2026. No separate explicit commercial-operation date was found.
- Site area: 27 acres
- Gross floor area: 429,603 square feet
- Buildings: 1
- Construction: New construction of a two-story data-center facility with an exterior generator yard at 3801 Britton Road in Mansfield, Texas. The Texas regulatory filing identifies the project as privately funded on private land for private use; the scheduled permit construction period was June 24, 2024 through January 27, 2026.

## Compute and operations

- Facility classes: hyperscale, cloud, ai_hpc, enterprise
- Workloads: AI, cloud, enterprise applications
- Operating context: Aligned DFW-03 is a 27-acre, two-story data-center facility at 3801 Britton Road in Mansfield, Texas, with an on-site substation. It uses Aligned’s adaptive modular infrastructure and is designed for scalable, high-density AI, cloud, and enterprise deployments, including air, liquid, or hybrid cooling.

## Sources

- [http://aligneddc.com/dallas-data-centers](http://aligneddc.com/dallas-data-centers)
- [http://aligneddc.com/press-release/aligned-data-centers-expands-dfw-footprint-with-new-data-center-in-mansfield-tx](http://aligneddc.com/press-release/aligned-data-centers-expands-dfw-footprint-with-new-data-center-in-mansfield-tx)
- [http://aligneddc.com/video-resources/inside-dfw-03-building-for-today-and-tomorrow](http://aligneddc.com/video-resources/inside-dfw-03-building-for-today-and-tomorrow)
- [http://datacenterdynamics.com/en/news/aligned-plans-second-data-center-campus-in-dallas-fort-worth-texas](http://datacenterdynamics.com/en/news/aligned-plans-second-data-center-campus-in-dallas-fort-worth-texas)
- [http://tdlr.texas.gov/TABS/Search/Project/TABS2024018570](http://tdlr.texas.gov/TABS/Search/Project/TABS2024018570)
- [Sustainable, AI-Ready Data Centers in Dallas Fort Worth | Aligned](https://aligneddc.com/dallas-data-centers/)
- [Global Data Center Locations](https://aligneddc.com/locations/)
- [Aligned Data Centers Expands DFW Footprint with New Data Center in Mansfield, TX - Aligned Data Centers](https://aligneddc.com/press-release/aligned-data-centers-expands-dfw-footprint-with-new-data-center-in-mansfield-tx/) — Aligned Data Centers · 2025-02-19
- [Sustainability as a Priority | Aligned Data Centers](https://aligneddc.com/sustainability/)
- [Inside DFW-03: Building for Today and Tomorrow - Aligned Data Centers](https://aligneddc.com/video-resources/inside-dfw-03-building-for-today-and-tomorrow/)
- [Aligned: DFW-03 Data Center](https://baxtel.com/data-center/aligned-dfw-03)
- [Aligned Data Centers Expands DFW Footprint as It Races to Serve AI/Cloud Workloads » Dallas Innovates](https://dallasinnovates.com/aligned-data-centers-expands-dfw-footprint-as-it-races-to-serve-ai-cloud-workloads/) — Dallas Innovates · 2025-02-25
- [Another Day, Another Data Center. This One Will Be in Mansfield - Fort Worth Inc.](https://fortworthinc.com/real-estate/another-day-another-data-center-this-one-will-be-in-mansfiel/) — Fort Worth Inc. · 2024-05-16
- [Fetched web page](https://interchange.puc.texas.gov/Documents/56002_8_1379147.PDF)
- [CITY OF MANSFIELD - File #: 23-5798](https://mansfield.legistar.com/LegislationDetail.aspx?ID=6458071&GUID=9CBB1E94-0041-4F92-8EF9-26F55516E2B9&Options=&Search=)
- [CITY OF MANSFIELD - Meeting of Planning and Zoning Commission on 12/4/2023 at 6:00 PM](https://mansfield.legistar.com/MeetingDetail.aspx?ID=1140173&GUID=DE75996A-953D-40A6-A072-CDC7D43A5F2C&Options=&Search=)
- [Fetched web page](https://mansfield.legistar.com/View.ashx?M=F&ID=12552230&GUID=5A6BC717-C03E-487A-B75D-BF77576DA4BF)
- [Fetched web page](https://mansfield.legistar.com/View.ashx?M=F&ID=12552348&GUID=3D47E05F-DAC2-418B-9E1B-E1616D6F8416)
- [Fetched web page](https://mansfield.legistar.com/ViewReport.ashx?M=R&N=Text&GID=206&ID=5616972&GUID=FBC107A5-2125-4B40-B498-91812E784D4C&Title=Legislation+Text)
- [Aligned Mansfield Campus (DFW-03) Data Center, Texas | PoweredByWho](https://poweredbywho.com/projects/aligned-mansfield-campus-dfw-03-1be071a3)
- [Aligned Data Centers to Develop 27-Acre Campus in Mansfield, Texas - REBusinessOnline](https://rebusinessonline.com/aligned-data-centers-to-develop-27-acre-campus-in-mansfield-texas/)
- [Aligned plans second data center campus in Dallas Fort Worth, Texas - DCD](https://www.datacenterdynamics.com/en/news/aligned-plans-second-data-center-campus-in-dallas-fort-worth-texas/) — Data Center Dynamics · 2025-02-20
- [Aligned Data Centers: DFW-03 Data Center](https://www.datacenters.com/aligned-dfw-03)
- [Electric Reliability Council of Texas (ERCOT)](https://www.ercot.com/)
- [Property Tax Information | Mansfield, TX](https://www.mansfieldtexas.gov/281/Property-Tax-Information)
- [Planning | Mansfield, TX](https://www.mansfieldtexas.gov/331/Planning)
- [Start New Water Service | Mansfield, TX](https://www.mansfieldtexas.gov/469/Start-New-Water-Service)
- [Fetched web page](https://www.mansfieldtexas.gov/Archive.aspx?ADID=465)
- [Oncor](https://www.oncor.com/content/oncorwww/us/en/home.html)
- [NSR Application Postings](https://www.tceq.texas.gov/assets/public/permitting/air/reports/applications/nsr-pending-permits.html)
- [TDLR TABS - Project Details](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2024018570)
- [WMFD.com - Mansfield and North Central Ohio's News, Sports and Weather](https://www.wmfd.com/article/mansfield-residents%27-data-center-opposition-group-circulates-petition/22172)

## Data quality

- The exact asset is Aligned DFW-03 at 3801 Britton Road, Mansfield, Texas; reporting that concerns other Aligned campuses, other operators, or Mansfield, Ohio was excluded.
- The identified public hearing concerned zoning at the exact 3801 Britton Road property and was approved on December 4, 2023. The available record does not establish that the hearing was specifically for a data-center use.
- No tenant, utility, MW capacity, water use, PUE/WUE, generator count, or commercial terms were assigned because the reviewed community and local-news sources did not provide supported exact-site evidence for those fields.
- The research corpus contained no verified exact-site petition, named community opposition organization, or litigation record concerning Aligned DFW-03. This is a finding about the reviewed evidence, not proof that no such activity exists.
- Power values retain their reported, requested, contracted, energized, gross-campus, or critical-IT basis.

---