# Amazon Lake Anna Technology Campus

PJM data center · https://askthegrid.com/assets/facilities/amazon-lake-anna-technology-campus--grid-load-bfba6d2c04fca08b

The Amazon Lake Anna Technology Campus is an Amazon Web Services data center campus under construction near Mineral in Louisa County, Virginia. The permit application describes seven standard data center buildings and two smaller specialty buildings with a minimum need of 420 MW. Two on-site substations are planned, each with Dominion Energy and Rappahannock Electric Cooperative sections, providing about 300 MW each. Construction has passed the halfway mark and one building has been turned over for operations. Diesel generator sets at the site are permitted by Virginia DEQ.

## Identity and location

- Operating status: under_construction
- Asset scope: campus
- Location: 230 Haley Dr, Mineral, Louisa County, VA
- Operator: Amazon Data Services, Inc. (exact asset)

## Power and grid context

- Reported unspecified: 420+ MW · proposed · exact asset — Minimum data-center capacity need stated in the permit application; not identified as IT load
- Utility service: About 600 MW · proposed · exact asset — Combined capacity of the two proposed substations, which also cover ancillary buildings, redundancy and adjacent development
- Utility service: About 300 MW · proposed · exact asset — Per substation, for two proposed substations
- ISO/RTO: PJM
- Electric utility: Rappahannock Electric Cooperative
- Substation: Two proposed substations, each split into Dominion Energy and Rappahannock Electric Cooperative sections

## Development

- Construction: Seven (7) standard data center buildings and two (2) smaller specialty data center buildings

## Sources

- [Lake Anna Technology Campus](https://www.lakeannatechcampus.com/)
- [https://webapps.mrc.virginia.gov/public/habitat/getADD.php?id=183314](https://webapps.mrc.virginia.gov/public/habitat/getADD.php?id=183314)
- [Amazon Provides Details For Lake Anna Tech Campus | Lake Anna Life](https://lakeannalife.com/amazon-provides-details-for-lake-anna-tech-campus/)
- [Lake Anna Development Continues: Data Centers, Dominion Updates, Roundabout Plaza, New Golf Course &amp; Phosphorus and Hydrilla Management Reports at the 2026 Lake Anna Summit - Lake Anna Online™](https://lakeanna.online/lake-anna-development-continues-data-centers-dominion-updates-roundabout-plaza-new-golf-course-phosphorus-and-hydrilla-management-reports-at-the-2026-lake-anna-summit/)
- [https://townhall.virginia.gov/L/GetFile.cfm?File=Meeting%5C53%5C43391%5CAgenda_DEQ_new_v1.pdf](https://townhall.virginia.gov/L/GetFile.cfm?File=Meeting%5C53%5C43391%5CAgenda_DEQ_new_v1.pdf)
- [Access Denied](https://www.deq.virginia.gov/home/showpublisheddocument/35464/639105417611870000)
- [Access Denied](https://www.nao.usace.army.mil/Media/Public-Notices/Article/3804862/nao-2023-01759-lake-anna-tech-campus-amazon-louisa-county-virginia/)
- [www.louisacounty.gov](https://www.louisacounty.gov/DocumentCenter/View/11955/Data-Centers-in-Louisa-County)

---

Canonical page: https://askthegrid.com/assets/facilities/amazon-lake-anna-technology-campus--grid-load-bfba6d2c04fca08b
Profile generated: 2026-11-02T18:55:04.776252Z
Source: Ask the Grid — https://askthegrid.com/