# Cavalier Solar

PJM asset profile · https://askthegrid.com/assets/facilities/cavalier-solar

AES Clean Energy - Isle of Wight County - PJM

Operating 155.6 MW solar photovoltaic facility at 10045 Mill Swamp Road, Smithfield, Virginia, in Isle of Wight County. It interconnects through a 500 kV transmission connection to Dominion Energy Virginia's Septa Substation. Kiewit engineered, procured, constructed, tested, and commissioned the 500/34.5 kV collector substation and associated 16 circuit-miles of 34.5 kV overhead collector line. The facility is operated by AES Clean Energy and participates in the PJM wholesale electricity market as an independent power producer.

## Metrics

- **Nameplate capacity:** 155.6 MW — Canonical EIA plant baseline.
- **Registry anchor:** Plant 67420 — plant-67420

## Facts

- **Technology:** Solar Photovoltaic
- **Operator:** AES Clean Energy

## Related parties

- **Owner / operator / developer:** AES Clean Energy — Owner, developer, and operator ([source](https://www.aes.com))
- **Project company / developer:** Cavalier Solar A, LLC — Project developer and local-government applicant
- **EPC contractor / construction contractor:** Kiewit Corporation — EPC contractor for collector substation and interconnection facilities ([source](https://www.kiewit.com))
- **Interconnection counterparty / transmission owner:** Virginia Electric and Power Company d/b/a Dominion Energy Virginia — Transmission and interconnection facilities owner ([source](https://www.dominionenergy.com))

## Sources

- [docs.publicnow.com](https://docs.publicnow.com/viewDoc.aspx?filename=40942\EXT\A308F15BD5ACA24C961BA86FE1D67431C28C1B65_43DCFA800A3E9B1FBD22BDEBDE3AD01407140C2B.PDF) — docs.publicnow.com · public_source — Source retained for exact-record publication review.
- [surrycountyva.gov](https://surrycountyva.gov/DocumentCenter/View/805/Request-for-Public-Hearing--Cavalier-Solar-LLC---Combined-Files-3-25-2021) — surrycountyva.gov · authoritative — Source retained for exact-record publication review.
- [aes.com](https://www.aes.com/sustainability-impact/people-communities/projects/cavalier-solar-project) — aes.com · public_source — Source retained for exact-record publication review.
- [kiewit.com](https://www.kiewit.com/projects/cavalier-substation) — kiewit.com · public_source — Source retained for exact-record publication review.
- [prnewswire.com](https://www.prnewswire.com/news-releases/spower-now-part-of-aes-clean-energy-closes-landmark-debt-financing-for-a-400-mwh-standalone-battery-storage-project-in-california-301224387.html) — prnewswire.com · public_source — Source retained for exact-record publication review.

---

Canonical page: https://askthegrid.com/assets/facilities/cavalier-solar
Website: [AES Clean Energy](https://www.aes.com)

Source: Ask the Grid — https://askthegrid.com/