# Chalk Point Power

PJM Natural Gas Fired Combustion Turbine, Natural Gas Steam Turbine, Petroleum Liquids · https://askthegrid.com/assets/facilities/chalk-point-power

Chalk Point Power is a natural gas-fired power facility with 1,825 MW of EIA-reported nameplate capacity in Prince Georges County, Maryland, registered as EIA Plant ID 1571. In the first quarter of 2024, those units received approximately $20 million of PJM uplift credits, representing 26% of total PJM uplift. Terrapin Power, LLC, a Rockland Capital subsidiary acquired a 100% interest in the plant from Osprey Energy Holdings, LLC in 2024.

## Key facts

- Technology: Natural Gas Fired Combustion Turbine, Natural Gas Steam Turbine, Petroleum Liquids
- Power capacity: 1825 MW
- Commercial operation: 1967
- Operating status: operating

## Grid and market context

- ISO/RTO: PJM
- Balancing authority: PJM
- Substation: Chalk Point substation
- Point of interconnection: Chalk Point substation
- Transmission owner: Pepco
- Interconnection voltage: 230 kV

## Source-backed facts

- Identifiers: [{"value":"1571","system":"EIA plant ID"},{"value":"PJM Interconnection","system":"ISO/RTO"},{"value":"SWMACC","system":"PJM subregion"},{"value":"EL24-36-000","system":"FERC docket"},{"value":"EL24-39-000","system":"FERC docket"},{"value":"ER21-573-003","system":"FERC docket"}] — Chalk Point Generating Station · confidence: medium
- Identifiers: [{"value":"1571","system":"EIA plant ID"},{"value":"PJM Interconnection","system":"ISO/RTO"},{"value":"SWMACC","system":"PJM subregion"},{"value":"EL24-36-000","system":"FERC docket"},{"value":"EL24-39-000","system":"FERC docket"},{"value":"ER21-573-003","system":"FERC docket"}] — Chalk Point Plant | OLYMPUS Power, LLC · confidence: medium
- Identifiers: [{"value":"1571","system":"EIA plant ID"},{"value":"PJM Interconnection","system":"ISO/RTO"},{"value":"SWMACC","system":"PJM subregion"},{"value":"EL24-36-000","system":"FERC docket"},{"value":"EL24-39-000","system":"FERC docket"},{"value":"ER21-573-003","system":"FERC docket"}] — Federal Register :: Chalk Point Power, LLC, Dickerson Power, LLC; Notice of Institution of Section 206 Proceedings and Refund Effective Date · confidence: medium
- Identifiers: [{"value":"1571","system":"EIA plant ID"},{"value":"PJM Interconnection","system":"ISO/RTO"},{"value":"SWMACC","system":"PJM subregion"},{"value":"EL24-36-000","system":"FERC docket"},{"value":"EL24-39-000","system":"FERC docket"},{"value":"ER21-573-003","system":"FERC docket"}] — eLibrary | Docket Search Results · confidence: medium
- Description: Chalk Point Power is an 1,825 MW gas- and oil-fired power plant with eight generating units in Prince Georges County, Maryland. It is located in Aquasco, has dual-fuel capability, and serves the SWMACC region of PJM. Its units came online between 1967 and 1991. — Chalk Point Plant | OLYMPUS Power, LLC · confidence: medium
- Identifiers.0: {"value":"1571","system":"EIA plant ID"} — Chalk Point Generating Station · confidence: medium
- Identifiers.1: {"value":"PJM Interconnection","system":"ISO/RTO"} — Chalk Point Plant | OLYMPUS Power, LLC · confidence: high
- Identifiers.2: {"value":"SWMACC","system":"PJM subregion"} — Chalk Point Plant | OLYMPUS Power, LLC · confidence: high
- Identifiers.3: {"value":"EL24-36-000","system":"FERC docket"} — Federal Register :: Chalk Point Power, LLC, Dickerson Power, LLC; Notice of Institution of Section 206 Proceedings and Refund Effective Date · confidence: high
- Identifiers.4: {"value":"EL24-39-000","system":"FERC docket"} — eLibrary | Docket Search Results · confidence: high
- Parties.1: {"relationship":"Registered plant company / FERC market-based-rate applicant","name":"Chalk Point Power, LLC","official_url":null} — eLibrary | Docket Search Results · confidence: high
- Parties.3: {"relationship":"Asset manager and operations-and-maintenance provider","name":"Consolidated Asset Management Services","official_url":null} — Chalk Point Plant | OLYMPUS Power, LLC · confidence: high
- Site acres: 1160 — Maryland Department of Environment · confidence: high
- Unit configuration: Eight gas- and oil-fired generating units: 6 combustion gas turbines and 2 steam turbines; dual-fuel natural gas and diesel fuel oil capability. — Chalk Point Plant | OLYMPUS Power, LLC · confidence: medium
- Product url: https://www.gevernova.com/gas-power/products/gas-turbines/7e — 7E Gas Turbine (7E.03) | GE Vernova · confidence: medium
- Product url: https://www.gevernova.com/gas-power/products/gas-turbines/7e — Steam Turbine Power Plant Solutions · confidence: medium
- Product family: Pratt & Whitney FT4A; General Electric Frame-7EA and GE-7EA; Kraftwork Union V84.2; GE G7 tandem-compound steam turbines — 7E Gas Turbine (7E.03) | GE Vernova · confidence: medium
- Equipment models.1: {"manufacturer_domain":"gevernova.com","product_url":"https://www.gevernova.com/gas-power/products/gas-turbines/7e","count":2,"unit_mw":99,"name":"General Electric Frame-7EA combustion turbine"} — AIR AND RADIATION ADMINISTRATION DRAFT PART 70 OPERATING PERMIT DOCKET # 24-033-2920 Chalk Point Power, LLC- Chalk : PANY COM · confidence: medium
- Equipment models.1: {"manufacturer_domain":"gevernova.com","product_url":"https://www.gevernova.com/gas-power/products/gas-turbines/7e","count":2,"unit_mw":99,"name":"General Electric Frame-7EA combustion turbine"} — 7E Gas Turbine (7E.03) | GE Vernova · confidence: medium
- Equipment models.3: {"manufacturer_domain":"gevernova.com","product_url":"https://www.gevernova.com/gas-power/products/gas-turbines/7e","count":1,"unit_mw":93,"name":"General Electric GE-7EA combustion turbine"} — AIR AND RADIATION ADMINISTRATION DRAFT PART 70 OPERATING PERMIT DOCKET # 24-033-2920 Chalk Point Power, LLC- Chalk : PANY COM · confidence: medium
- Equipment models.3: {"manufacturer_domain":"gevernova.com","product_url":"https://www.gevernova.com/gas-power/products/gas-turbines/7e","count":1,"unit_mw":93,"name":"General Electric GE-7EA combustion turbine"} — 7E Gas Turbine (7E.03) | GE Vernova · confidence: medium
- Description: Chalk Point Power is an approximately 1,825 MW gas- and oil-fired facility with eight generating units in Aquasco, Prince George’s County, Maryland, serving the SWMACC region of PJM. The configuration comprises six combustion turbines and two steam turbines with natural-gas and diesel-fuel-oil capability. Rockland Capital acquired the facility in November 2024 from an affiliate of Olympus Power through a transaction involving Terrapin Power and Osprey Energy Holdings. The coal-fired Units 1 and 2 entered service in 1964 and 1965 and were retired on June 1, 2021, while the remaining gas- and oil-fired units continued operating. — Chalk Point Plant | OLYMPUS Power, LLC · confidence: medium
- Description: Chalk Point Power is an approximately 1,825 MW gas- and oil-fired facility with eight generating units in Aquasco, Prince George’s County, Maryland, serving the SWMACC region of PJM. The configuration comprises six combustion turbines and two steam turbines with natural-gas and diesel-fuel-oil capability. Rockland Capital acquired the facility in November 2024 from an affiliate of Olympus Power through a transaction involving Terrapin Power and Osprey Energy Holdings. The coal-fired Units 1 and 2 entered service in 1964 and 1965 and were retired on June 1, 2021, while the remaining gas- and oil-fired units continued operating. — Bracewell Represents Rockland Capital in Acquisition From Affiliate of Olympus Power | Bracewell LLP News Releases · confidence: medium
- Quality notes: ["Capacity figures reflect different scopes and reporting dates: the EIA-derived plant record reports 1,825 MW, Olympus reported 1,612 MW, Bracewell described the acquired facility as 1,613 MW, and the FERC market-power filing focused on the 1,200 MW steam Units 3 and 4.","The December 2023 Olympus transaction and November 2024 Rockland transaction were separate ownership events. The clearly documented generation change is the retirement of coal Units 1 and 2 while the natural-gas and oil-fired capacity continued operating."] — Natural Gas Combined Cycle – Rockland Capital · confidence: medium
- Financing summary: No project-financing debt, loan amount, or Chalk Point-specific purchase consideration is disclosed in the cited materials. In December 2023, Olympus acquired the relevant applicants through an arrangement among Lanyard Power and its lenders intended to avoid foreclosure; in November 2024, Terrapin Power, a Rockland Capital subsidiary, acquired 100% of Osprey Power from Osprey Energy Holdings. The transaction sources identify the parties and assets but do not state a purchase price or acquisition-debt package. — Bracewell Represents Rockland Capital in Acquisition From Affiliate of Olympus Power | Bracewell LLP News Releases · confidence: medium
- Financing summary: No project-financing debt, loan amount, or Chalk Point-specific purchase consideration is disclosed in the cited materials. In December 2023, Olympus acquired the relevant applicants through an arrangement among Lanyard Power and its lenders intended to avoid foreclosure; in November 2024, Terrapin Power, a Rockland Capital subsidiary, acquired 100% of Osprey Power from Osprey Energy Holdings. The transaction sources identify the parties and assets but do not state a purchase price or acquisition-debt package. — Natural Gas Combined Cycle – Rockland Capital · confidence: medium
- Quality notes.0: Capacity figures reflect different scopes and reporting dates: the EIA-derived plant record reports 1,825 MW, Olympus reported 1,612 MW, Bracewell described the acquired facility as 1,613 MW, and the FERC market-power filing focused on the 1,200 MW steam Units 3 and 4. — Comments of the Independent Market Monitor for PJM · confidence: high
- Quality notes.1: The December 2023 Olympus transaction and November 2024 Rockland transaction were separate ownership events. No project-financing debt amount or Chalk Point-specific sale consideration is identified in the cited transaction materials. — Natural Gas Combined Cycle – Rockland Capital · confidence: medium
- Timeline.1: {"event":"Gas- and oil-fired unit buildout","date":"1967-1991","detail":"The facility’s gas- and oil-fired units came online at various times between 1967 and 1991; the plant configuration is reported as six combustion turbines and two steam turbines."} — Chalk Point Plant | OLYMPUS Power, LLC · confidence: high
- Timeline.8: {"event":"Coal-unit retirement","date":"2021-06-01","detail":"Coal Units 1 and 2 were shut down on schedule; the approximately 1,600 MW of natural-gas and oil-fired capacity at the site continued operating."} — Chalk Point Generating Station - Global Energy Monitor · confidence: medium
- Timeline.10: {"event":"Rockland acquisition","date":"2024-11-14","detail":"Rockland Capital acquired the Chalk Point Power Facility from an affiliate of Olympus Power. Terrapin Power, a Rockland subsidiary, acquired Osprey Power from Osprey Energy Holdings, indirectly obtaining Chalk Point Power, LLC."} — Bracewell Represents Rockland Capital in Acquisition From Affiliate of Olympus Power | Bracewell LLP News Releases · confidence: high
- Timeline.10: {"event":"Rockland acquisition","date":"2024-11-14","detail":"Rockland Capital acquired the Chalk Point Power Facility from an affiliate of Olympus Power. Terrapin Power, a Rockland subsidiary, acquired Osprey Power from Osprey Energy Holdings, indirectly obtaining Chalk Point Power, LLC."} — Natural Gas Combined Cycle – Rockland Capital · confidence: high
- Commercial parties.0: {"relationship":"Current owner / 2024 acquisition buyer","name":"Rockland Capital, LLC","detail":"Acquired the Chalk Point Power Facility in November 2024 from an affiliate of Olympus Power; Rockland Capital LP remained identified as the FERC contact for Chalk Point Power, LLC in July 2026.","official_url":"https://rocklandcapital.com"} — Bracewell Represents Rockland Capital in Acquisition From Affiliate of Olympus Power | Bracewell LLP News Releases · confidence: medium
- Commercial parties.3: {"relationship":"Predecessor owner / 2023 buyer parent","name":"Olympus Power, LLC","detail":"Parent of Osprey Power and predecessor owner that acquired the Chalk Point applicants in the December 2023 lender-driven transaction.","official_url":"https://www.olympuspower.com"} — Chalk Point Plant | OLYMPUS Power, LLC · confidence: high
- Commercial parties.9: {"relationship":"Asset manager and operations-and-maintenance provider","name":"Consolidated Asset Management Services","detail":"Listed by Olympus as asset manager and operations-and-maintenance provider for the Chalk Point facility.","official_url":"https://camstex.com"} — Chalk Point Plant | OLYMPUS Power, LLC · confidence: high
- Acquisition date: 2024-11 — Bracewell Represents Rockland Capital in Acquisition From Affiliate of Olympus Power | Bracewell LLP News Releases · confidence: medium
- Acquisition date: 2024-11 — Bracewell Represents Rockland Capital in Acquisition From Affiliate of Olympus Power | Bracewell LLP News Releases · confidence: medium
- Seller: Osprey Energy Holdings, LLC — Bracewell Represents Rockland Capital in Acquisition From Affiliate of Olympus Power | Bracewell LLP News Releases · confidence: medium
- Substation: Chalk Point substation — Source · confidence: medium
- Resource type: GEN — Generators · confidence: medium
- Status detail: The exact plant is operating as of the June 2026 EIA-860M inventory period. Chalk Point coal Units 1 and 2 were retired on June 1, 2021, while the approximately 1,600 MW of natural-gas- and oil-fired capacity continued operating; current records also identify Chalk Point 3, Chalk Point 4, and Chalk Point CT resources in PJM. — GenOn Holdings, Inc. Announces Retirement of Chalk Point Coal Units — GenOn · confidence: medium
- Status detail: The exact plant is operating as of the June 2026 EIA-860M inventory period. Chalk Point coal Units 1 and 2 were retired on June 1, 2021, while the approximately 1,600 MW of natural-gas- and oil-fired capacity continued operating; current records also identify Chalk Point 3, Chalk Point 4, and Chalk Point CT resources in PJM. — Federal Register :: Combined Notice of Filings #1 · confidence: medium
- Operating status: operating — Federal Register :: Combined Notice of Filings #1 · confidence: medium

## Timeline

- 1964-1965 — Initial coal-unit operation
  Chalk Point coal Units 1 and 2 entered service in 1964 and 1965, respectively.
  Source: GenOn Holdings, Inc. Announces Retirement of Chalk Point Coal Units — GenOn (https://www.genon.com/genon-news/genon-holdings-inc-announces-retirement-of-chalk-point-coal-units)
- 1967-1991 — Gas- and oil-fired unit buildout
  The facility’s gas- and oil-fired units came online at various times between 1967 and 1991; the plant configuration is reported as six combustion turbines and two steam turbines.
  Source: Chalk Point Plant | OLYMPUS Power, LLC (https://www.olympuspower.com/node/27)
- 2010 — Mirant merger into GenOn
  Mirant merged into GenOn Energy in 2010.
  Source: Chalk Point Generating Station - Global Energy Monitor (https://www.gem.wiki/Chalk_Point_Generating_Station)
- 2012 — GenOn merger into NRG
  GenOn merged into NRG in 2012.
  Source: Chalk Point Generating Station - Global Energy Monitor (https://www.gem.wiki/Chalk_Point_Generating_Station)
- 2020-08-10 — Coal retirement announced
  GenOn announced the retirement process for coal Units 1 and 2, citing unfavorable economics and increased environmental-compliance costs, with a proposed June 1, 2021 retirement date.
  Source: GenOn Holdings, Inc. Announces Retirement of Chalk Point Coal Units — GenOn (https://www.genon.com/genon-news/genon-holdings-inc-announces-retirement-of-chalk-point-coal-units)
- 2024-11 — Acquisition closed
  Rockland Capital, LLC through subsidiary Terrapin Power, LLC acquired the 1,613-MW Chalk Point Power Facility from Osprey Energy Holdings, LLC (parent of Osprey Power, LLC). No exact acquisition consideration disclosed.
  Source: Bracewell Represents Rockland Capital in Acquisition From Affiliate of Olympus Power | Bracewell LLP News Releases (https://www.bracewell.com/news-events/bracewell-represents-rockland-capital-in-acquisition-from-affiliate-of-olympus-power/)

## Sources

- [Chalk Point Generating Station](https://www.wikidata.org/wiki/Q5068815) — wikidata.org · tier other
- [Chalk Point Plant](https://www.olympuspower.com/node/27) — olympuspower.com · tier other
- [Federal Register :: Chalk Point Power, LLC, Dickerson Power, LLC; Notice of Institution of Section 206 Proceedings and Refund Effective Date](https://www.federalregister.gov/documents/2024/01/03/2023-28902/chalk-point-power-llc-dickerson-power-llc-notice-of-institution-of-section-206-proceedings-and) — federalregister.gov · tier regulatory
- [eLibrary | Docket Search Results](https://elibrary.ferc.gov/eLibrary/docketsheet?docket_number=ER21-573-003&sub_docket=All&dt_from=1960-01-01&dt_to=2025-12-12&chklegadata=false&pageNm=dsearch&date_range=custom&search_type=docket&date_type=filed_date&sub_docket_q=Allsub&sid=962892c7-a9d2-4b6e-949f-8317f2f20481) — elibrary.ferc.gov · tier regulatory
- [GenOn Holdings, Inc. Announces Retirement of Chalk Point Coal Units — GenOn](https://www.genon.com/genon-news/genon-holdings-inc-announces-retirement-of-chalk-point-coal-units) — genon.com · tier other
- [Source](https://www.rd.usda.gov/sites/default/files/UWP_MD04-SMECO_HollandCliffs_AES.pdf) — rd.usda.gov · tier regulatory
- [Maryland Department of Environment](https://www.marylandmatters.org/wp-content/uploads/2021/06/MDE-Inspection-Report-Eagle-Harbor-1.pdf) — marylandmatters.org · tier other
- [Chalk Pt Power - Maryland Department of the Environment](https://mde.maryland.gov/programs/permits/AirManagementPermits/Test/Chalk%20Pt%20Power%20Initial%202022%20%20T5%20and%20FS.pdf) — mde.maryland.gov · tier regulatory
- [AIR AND RADIATION ADMINISTRATION DRAFT PART 70 OPERATING PERMIT DOCKET # 24-033-2920 Chalk Point Power, LLC- Chalk : PANY COM](https://mde.maryland.gov/programs/permits/AirManagementPermits/Documents/Public-Review/new%20Title%20V%20public%20review/Chalk%20Point%20CTs%20Docket.pdf) — mde.maryland.gov · tier regulatory
- [7E Gas Turbine (7E.03) | GE Vernova](https://www.gevernova.com/gas-power/products/gas-turbines/7e) — gevernova.com · tier other
- [Steam Turbine Power Plant Solutions](https://www.gevernova.com/gas-power/products/steam-turbines) — gevernova.com · tier other
- [Comments of the Independent Market Monitor for PJM](https://www.monitoringanalytics.com/filings/2024/IMM_Comments_Docket_No_EC24-79_202406010.pdf) — monitoringanalytics.com · tier other
- [Bracewell Represents Rockland Capital in Acquisition From Affiliate of Olympus Power | Bracewell LLP News Releases](https://www.bracewell.com/news-events/bracewell-represents-rockland-capital-in-acquisition-from-affiliate-of-olympus-power/) — bracewell.com · tier other
- [Natural Gas Combined Cycle – Rockland Capital](https://rocklandcapital.com/natural-gas-combined-cycle/) — rocklandcapital.com · tier other
- [Chalk Point Generating Station - Global Energy Monitor](https://www.gem.wiki/Chalk_Point_Generating_Station) — gem.wiki · tier other
- [Source](https://www.nerc.com/globalassets/our-work/reports/event-reports/washington_dc_area_low-voltage_disturbance_event_of_april_7_2015_final.pdf) — nerc.com · tier other
- [Generators](https://mis.nyiso.com/public/pdf/generator/generator.pdf) — mis.nyiso.com · tier other
- [Federal Register :: Combined Notice of Filings #1](https://www.federalregister.gov/documents/2026/07/02/2026-13426/combined-notice-of-filings-1) — federalregister.gov · tier regulatory

## Data quality

- Capacity figures reflect different scopes and reporting dates: the EIA-derived plant record reports 1,825 MW, Olympus reported 1,612 MW, Bracewell described the acquired facility as 1,613 MW, and the FERC market-power filing focused on the 1,200 MW steam Units 3 and 4. The December 2023 Olympus transaction and November 2024 Rockland transaction were separate ownership events. No project-financing debt amount or Chalk Point-specific sale consideration is identified in the cited transaction materials. The clearly documented generation change is the retirement of coal Units 1 and 2 while the natural-gas and oil-fired capacity continued operating.

---

Canonical page: https://askthegrid.com/assets/facilities/chalk-point-power