Lancaster AI Hub West is a proposed data center campus at 1375 Harrisburg Pike in the city of Lancaster, Pennsylvania, being developed by Chirisa Technology Parks. Chirisa's own listing shows two buildings with 130 MW and 220 MW of utility power, the second targeted for the fourth quarter of 2026, and a December 2025 plan submission describes a different one-building scheme. A new PPL Electric Utilities substation is proposed on the property. Air and water-obstruction applications were pending with the state in September 2026.

## Identity and location

- Operating status: proposed
- Asset scope: campus
- Location: 1375 Harrisburg Pike, Lancaster, Lancaster County County, PA
- Developer: Chirisa Technology Parks (exact asset)
- Owner: Harrisburg Place Owner, LLC (exact asset)

## Power and grid context

- Available power: 130 MW · reported · exact asset — Developer-listed utility power for LPW-01, available immediately
- Available power: 220 MW · target · exact asset — Developer-listed utility power for LPW-02
- ISO/RTO: PJM
- Electric utility: PPL Electric Utilities
- Substation: New PPL Electric Utilities substation proposed on the property

## Compute and operations

- Facility classes: build-to-suit

## Sources

- [Second planned Lancaster city data center facing residents' appeal | Local News | lancasteronline.com](https://lancasteronline.com/news/local/second-planned-lancaster-city-data-center-facing-residents-appeal/article_9c47bec3-7771-48f9-8fb2-5a02a3df25e4.html)
- [Developer submits plans for data center near Long's Park | Local News | lancasteronline.com](https://lancasteronline.com/news/local/developer-submits-plans-for-data-center-near-longs-park/article_3b6cf262-24ea-4fa0-ad75-da7de04ae34d.html)
- [Chirisa Technology Parks |](https://chirisatechnologyparks.com/)
- [eFACTS on the Web](https://www.ahs.dep.pa.gov/eFACTSWeb/searchResults_singleAuth.aspx?AuthID=1586002)
- [eFACTS on the Web](https://www.ahs.dep.pa.gov/eFACTSWeb/searchResults_singleAuth.aspx?AuthID=1586119)
- [www.cityoflancasterpa.gov](https://www.cityoflancasterpa.gov/wp-content/uploads/2025/11/Lancaster-CBA-Draft.pdf)
- [https://geocoding.geo.census.gov/geocoder/geographies/onelineaddress?address=1375+Harrisburg+Pike%2C+Lancaster%2C+PA&benchmark=Public_AR_Current&vintage=Current_Current&format=json](https://geocoding.geo.census.gov/geocoder/geographies/onelineaddress?address=1375+Harrisburg+Pike%2C+Lancaster%2C+PA&benchmark=Public_AR_Current&vintage=Current_Current&format=json)

---

Canonical page: https://askthegrid.com/assets/facilities/chirisa-lancaster-ai-hub-west-data-center--grid-load-d04a96c04549b111
Profile generated: 2026-11-02T21:31:18.677933Z
Source: Ask the Grid — https://askthegrid.com/