# Cologix Johnstown Data Center Campus

PJM data center · https://askthegrid.com/assets/facilities/cologix-johnstown-data-center-campus--grid-load-db673fd417fe950c

The Cologix Johnstown campus is a planned eight-building data center campus on about 154 acres in Johnstown, Licking County, Ohio. Cologix describes a potential 800 MW of scalable capacity at full buildout, and a state tax exemption approval reported 75 MW of electricity use at first and as much as 176 MW. Construction was reported ongoing in September 2026. AEP Ohio will supply grid power under expected service agreements, supplemented by a behind-the-meter solid oxide fuel cell system on the property that Cologix cites as a 25 MW project.

## Identity and location

- Operating status: under_construction
- Asset scope: campus
- Location: 12017 Duncan Plains Road, Johnstown, Licking County, OH
- Owner: Cologix Johnstown LLC (exact asset)
- Developer: Cologix (exact asset)
- Operator: Cologix (exact asset)

## Power and grid context

- Reported unspecified: Up to 800 MW · proposed · exact asset — Potential scalable capacity at full buildout of the campus
- Reported unspecified: 75 MW · reported · exact asset — Initial electricity use of the larger Johnstown facility, as reported at the state tax exemption approval
- Reported unspecified: Up to 176 MW · reported · exact asset — Possible growth of the larger Johnstown facility, as reported at the state tax exemption approval
- Reported unspecified: 50 MW · reported · exact asset — Site capacity advertised by the operator for the first listed building
- Reported unspecified: 21 MW · reported · exact asset — Site capacity advertised by the operator for the second listed building
- ISO/RTO: PJM
- Electric utility: AEP Ohio

## Development

- Construction: Eight AI-ready data centers planned at full buildout across 2.0 million square feet on about 154 acres

## Sources

- [Johnstown City Council approves special election to decide data center ban; Election slated for January 2027 - The Reporting Project - Covering Licking County, Ohio](https://www.thereportingproject.org/johnstown-city-council-approves-special-election-to-decide-data-center-ban-election-slated-for-january-2027/)
- [Cologix Expands Central Ohio Footprint With Land Acquisition For New AI-Ready 800MW Data Center Campus - Cologix](https://cologix.com/news/cologix-expands-central-ohio-footprint-with-land-acquisition-for-new-ai-ready-800mw-data-center-campus/)
- [2 Ohio data centers get $42M tax break before pause](https://signalohio.org/ohio-approves-last-data-center-exemption-before-moratorium/)
- [Columbus Colocation Data Center &amp; Interconnection Hub | Cologix COL7](https://cologix.com/data-centers/columbus/col7/)
- [Columbus Colocation Data Center &amp; Interconnection Hub | Cologix COL8](https://cologix.com/data-centers/columbus/col8/)
- [www.supremecourt.ohio.gov](https://www.supremecourt.ohio.gov/pdf_viewer/pdf_viewer.aspx?pdf=991349.pdf&subdirectory=2025-1241%5CDocketItems)
- [https://dam.assets.ohio.gov/image/upload/development.ohio.gov/business/stateincentives/TCA_Meeting_Minutes_6.1.2026.pdf](https://dam.assets.ohio.gov/image/upload/development.ohio.gov/business/stateincentives/TCA_Meeting_Minutes_6.1.2026.pdf)
- [https://geo.epa.ohio.gov/arcgis/rest/services/SurfaceWater/NPDES/MapServer/3/query?where=ohio_epa_no%3D%274GC10864%2AAG%27&outFields=facility_name,ohio_epa_no,facility_addr1,facility_city,facility_state,facility_zip,facility_county,facility_latitude,facility_longitude,total_acres,permit_status&returnGeometry=false&f=pjson](https://geo.epa.ohio.gov/arcgis/rest/services/SurfaceWater/NPDES/MapServer/3/query?where=ohio_epa_no%3D%274GC10864%2AAG%27&outFields=facility_name,ohio_epa_no,facility_addr1,facility_city,facility_state,facility_zip,facility_county,facility_latitude,facility_longitude,total_acres,permit_status&returnGeometry=false&f=pjson)
- [https://gis.lickingcounty.gov/server/rest/services/Auditor/Parcels/FeatureServer/0/query?where=OwnerName%20like%20%27%25COLOGIX%25%27&outFields=Parcel,OwnerName,SiteAddress,LegalDescription&returnGeometry=false&f=pjson](https://gis.lickingcounty.gov/server/rest/services/Auditor/Parcels/FeatureServer/0/query?where=OwnerName%20like%20%27%25COLOGIX%25%27&outFields=Parcel,OwnerName,SiteAddress,LegalDescription&returnGeometry=false&f=pjson)

---

Canonical page: https://askthegrid.com/assets/facilities/cologix-johnstown-data-center-campus--grid-load-db673fd417fe950c
Profile generated: 2026-11-02T18:54:43.827803Z
Source: Ask the Grid — https://askthegrid.com/