# Cyber Integration Center Data Center, Harrisonburg (Anthem CDC 3)

PJM data center · https://askthegrid.com/assets/facilities/cyber-integration-center-data-center-harrisonburg-anthem-cdc-3--grid-load-5848a01afb6c6e6b

The Cyber Integration Center is a data center at 1175 N. Main Street, also addressed 139 Tyco Street, in Harrisonburg, Virginia. Criticon began the redevelopment and DBT-DATA built out and later repurchased the facility, and AC 139 Tyco Street, LLC is the listed owner. Anthem Health has leased the full property since 2015. The Harrisonburg Electric Commission arranged up to 40 MW of power at the 2008 acquisition and built a substation on the property.

## Identity and location

- Operating status: operating
- Asset scope: building
- Location: 139 Tyco Street, Harrisonburg, Harrisonburg city County, VA
- Owner: AC 139 Tyco Street, LLC (exact asset)
- Tenant: Anthem Health (exact asset)
- Developer: Criticon (exact asset)
- Developer: DBT-DATA (exact asset)

## Power and grid context

- Utility service: Up to 40 MW · reported · exact asset — Utility power arranged with the Harrisonburg Electric Commission at the acquisition
- Utility service: 20 MW · reported · exact asset — Each of two on-site electrical substations reported by the earlier operator
- Backup generation: 2.5 MW · reported · exact asset — Rating of each Caterpillar generator
- ISO/RTO: PJM
- Electric utility: Harrisonburg Electric Commission
- Substation: Harrisonburg Electric Commission was building a substation at the property to accommodate the arranged capacity

## Compute and operations

- Facility classes: disaster recovery
- Announced tenants: Anthem Health, fully leased since 2015
- Operating context: Reported 7,500 kW of IT load conditioned power, with 6,000 kW for immediate use

## Sources

- [Harrisonburg City Council updates zoning ordinance to allow bargaining with developers for cash 'proffers' | Council Or Board | dnronline.com](https://www.dnronline.com/news/politics_and_government/levels_of_government/municipal/council_or_board/harrisonburg-city-council-updates-zoning-ordinance-to-allow-bargaining-with-developers-for-cash-proffers/article_396647d2-eaca-5b68-b162-273256d5e822.html)
- [www.dbtholdingsllc.com](https://www.dbtholdingsllc.com/dbt-portfolio/cyber-integration-center)
- [DBT-Data Acquires Criticon's Virginia Project](https://www.datacenterknowledge.com/business/dbt-data-acquires-criticon-s-virginia-project)
- [Just a moment...](https://www.datacenterdynamics.com/en/news/carpathia-hosting-announces-new-virginia-datacenter/)
- [Access Denied](https://www.deq.virginia.gov/home/showpublisheddocument/26022/638633962837530000)
- [DBT-Data Repurchases Virginia Site From Harris](https://www.datacenterknowledge.com/business/dbt-data-repurchases-virginia-site-from-harris)
- [Valley National Bank Lends $44M on Virginia Data Center &#8211; Commercial Observer](https://commercialobserver.com/2023/02/valley-national-bank-lends-44m-virginia-data-center/)
- [2011: The Year Data Centers Turned Green | WIRED](https://www.wired.com/2011/12/green-data-centers-of-2011/)
- [Access Denied](https://www.deq.virginia.gov/news-info/shortcuts/permits/air/issued-air-permits-for-data-centers)
- [www.harrisonburghousingtoday.com](https://www.harrisonburghousingtoday.com/files_content/documents/64/20140918104828__data-center.pdf)
- [Enterprise Data Center - Carter Funds](https://carterfunds.com/enterprise-data-center/)
- [https://echodata.epa.gov/echo/dfr_rest_services.get_dfr?output=JSON&p_id=110040513209](https://echodata.epa.gov/echo/dfr_rest_services.get_dfr?output=JSON&p_id=110040513209)
- [ENERGY STAR Certified Data Centers | ENERGY STAR](https://www.energystar.gov/buildings/certified-data-centers)
- [www.dbtholdingsllc.com](https://www.dbtholdingsllc.com/dbt-portfolio/blue-ridge-data-center)

---

Canonical page: https://askthegrid.com/assets/facilities/cyber-integration-center-data-center-harrisonburg-anthem-cdc-3--grid-load-5848a01afb6c6e6b
Profile generated: 2026-11-02T18:59:10.067657Z
Source: Ask the Grid — https://askthegrid.com/