# Data Center Building TX11

ERCOT data center · https://askthegrid.com/assets/facilities/data-center-building-tx11

Vantage Data Centers owns and operates TX11, a two-story building under construction at 14720 Omicron Drive in San Antonio, with 242,667 gross square feet and four 8 MW data halls totaling 32 MW capacity. Construction began December 15, 2023 with a scheduled completion date of September 1, 2026; TDLR status shows inspection complete.

## Identity and location

- Operating status: under_construction
- Asset scope: building
- Location: 14720 Omicron Drive, San Antonio, Bexar County, TX
- Owner: VANTAGE DATA CENTERS TX1 LLC (exact asset)
- Operator: Vantage Data Centers (exact asset) — https://vantage-dc.com/
- Developer: Vantage Data Centers (exact asset) — https://vantage-dc.com/

## Power and grid context

- Utility service: 32 MW · reported · building · as of 2026-07-27 — Reported total capacity for the exact TX11 two-story building, consisting of four 8 MW data halls. The source does not identify this figure as contracted, approved, energized, utility-service, or critical-IT capacity.
- ISO/RTO: ERCOT
- Electric utility: CPS Energy

## Development

- Site status: Under construction; TDLR current status is Inspection Complete.
- Gross floor area: 242,667 square feet
- Buildings: 1
- Construction: TX11 is a permitted, two-story data-center building at 14720 Omicron Drive, San Antonio. Construction began December 15, 2023. The building is designed for 32 MW across four 8 MW data halls and has 242,667 square feet of gross building area. The TDLR filing lists an estimated completion date of September 1, 2026 and current status as Inspection Complete; no separate commercial-operation date is documented.

## Compute and operations

- Facility classes: mixed
- Workloads: wholesale data-center workloads, colocation, hybrid cloud, hyperscale cloud and AI/ML, AI/HPC and analytics, enterprise and SaaS, telecom, content delivery, and edge infrastructure, regulated-industry hosting
- Critical IT load: 32 MW
- Operating context: Vantage Data Centers is developing and operating TX11 as a wholesale, scalable data-center building at 14720 Omicron Drive. The two-story building comprises four 8 MW data halls and has a stated total capacity of 32 MW.

## Sources

- [http://datacenterdynamics.com/en/news/vantage-files-plans-for-san-antonio-data-center](http://datacenterdynamics.com/en/news/vantage-files-plans-for-san-antonio-data-center)
- [http://datacentermap.com/usa/texas/san-antonio/vantage-tx11-san-antonio](http://datacentermap.com/usa/texas/san-antonio/vantage-tx11-san-antonio)
- [http://datacenters.com/vantage-tx11-san-antonio](http://datacenters.com/vantage-tx11-san-antonio)
- [http://tdlr.texas.gov/TABS/Search/Project/TABS2024007561](http://tdlr.texas.gov/TABS/Search/Project/TABS2024007561)
- [Greater Edwards Aquifer Alliance](https://aquiferalliance.org/)
- [Data Centers in Texas](https://comptroller.texas.gov/taxes/data-centers/data-center-lists.php)
- [Data Centers Are Building Power Plants Near Neighborhoods—That May Play Into Some South San Antonio Ambitions](https://deceleration.news/data-centers-are-building-power-plants-near-neighborhoods-south-san-antonio/)
- [Environmental Integrity Project](https://environmentalintegrity.org/)
- [Vantage TX11 - San Antonio | GoDataCenters](https://godatacenters.com/data-centers/texas/san-antonio/67746c9c-977c-4b73-acaf-975c0407bb28)
- [Sustainability](https://vantage-dc.com/features/sustainability/)
- [Tax Abatements | Bexar County, TX - Official Website](https://www.bexar.org/2808/Tax-Abatements)
- [Fetched web page](https://www.cpsenergy.com/content/dam/corporate/en/Documents/Finance/TXSanAntonio06a-FIN%20%28secured%29.pdf)
- [Vantage buys two land plots in San Antonio, Texas - DCD](https://www.datacenterdynamics.com/en/news/vantage-buys-two-land-plots-in-san-antonio-texas/)
- [Vantage files plans for San Antonio data center - DCD](https://www.datacenterdynamics.com/en/news/vantage-files-plans-for-san-antonio-data-center/) — Data Center Dynamics · 2023-12-19
- [Vantage, VoltaGrid face lawsuit concerning natural gas powered off-grid data centers in San Antonio, Texas - DCD](https://www.datacenterdynamics.com/en/news/vantage-voltagrid-face-lawsuit-concerning-natural-gas-powered-off-grid-data-centers-in-san-antonio-texas/)
- [San Antonio Data Centers - 72 Facilities from 7 Operators](https://www.datacentermap.com/usa/texas/san-antonio/)
- [Vantage TX11 - San Antonio Data Center | 14720 Omicron Dr](https://www.datacentermap.com/usa/texas/san-antonio/vantage-tx11-san-antonio/)
- [Vantage Data Centers: TX11 - San Antonio Data Center](https://www.datacenters.com/vantage-tx11-san-antonio)
- ['A Special Place in Hell': San Antonio residents push back against far West Side data center - San Antonio Current](https://www.sacurrent.com/news/san-antonio-news/a-special-place-in-hell-san-antonio-residents-push-back-against-far-west-side-data-center/)
- [Denver data center company buys 89 acres on far West Side](https://www.sanantonioreport.org/san-antonio-vantage-data-centers-microsoft-west-side/)
- [Lone Star Chapter](https://www.sierraclub.org/texas)
- [Calendar of Public Meetings and Hearings on Permitting Cases](https://www.tceq.texas.gov/agency/decisions/hearings)
- [Fetched web page](https://www.tceq.texas.gov/assets/public/permitting/air/publicnotice/38602sob.pdf)
- [Fetched web page](https://www.tceq.texas.gov/assets/public/permitting/air/reports/applications/38602-tc.pdf)
- [Title V Applications](https://www.tceq.texas.gov/assets/public/permitting/air/reports/applications/titlev-pending-permits.html)
- [Fetched web page](https://www.tceq.texas.gov/downloads/agency/decisions/hearings/notices/2026/2026-05-28-vantage-data-centers-tx21-llc-o4790-nch.pdf/%40%40download/file/2026-05-28-vantage-data-centers-tx21-llc-o4790-nch.pdf)
- [TDLR TABS - Project Details](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2024007561)
- [Environmental groups threaten Clean Air Act lawsuit over San Antonio data centers | TPR](https://www.tpr.org/podcast/the-source/2026-07-27/environmental-groups-threaten-clean-air-act-lawsuit-over-san-antonio-data-centers?_amp=true)

## Data quality

- No site-specific community benefit, jobs, tax contribution, infrastructure investment, or community-benefit agreement was identified for TX11 in the reviewed evidence.
- The exact asset is Data Center Building TX11 at 14720 Omicron Drive, with TCEQ permit O4791. The May 28, 2026 hearing and O4790 permit concerned Vantage TX21 at 5207 Rogers Road, not TX11.
- Several reports discuss the Omicron site while focusing primarily on the Rogers Road project or broader Vantage developments. The TPR report contains an apparent address typo ('14270 Omicron Drive'); the official TX11 address is 14720 Omicron Drive.
- Claims about generators, air emissions, cooling, and water concerns are reported allegations or statements about related permitting and operations; they should not be treated as independently verified engineering specifications for TX11.
- Power values retain their reported, requested, contracted, energized, gross-campus, or critical-IT basis.

---

Canonical page: https://askthegrid.com/assets/facilities/data-center-building-tx11
Profile generated: 2026-07-27T23:45:45.999739Z
Source: Ask the Grid — https://askthegrid.com/