# Equinix NY2

PJM data center · https://askthegrid.com/assets/facilities/equinix-ny2

Equinix NY2 is a facility data center in Secaucus, Hudson, NJ. Equinix is identified as the operator, and the facility is operating. It is identified as part of Equinix Secaucus Campus. Spatial service-territory evidence associates the site with Public Service Electric & Gas Co.; the profile assigns the asset to PJM through that documented market role. Reported development, power, and commercial facts retain their source-specific facility, campus, building, or phase scope; the page does not collapse those values into a single implied load.

## Identity and location

- Operating status: operating
- Asset scope: facility
- Location: 275 Hartz Way, Secaucus, Hudson County, NJ
- Operator: Equinix (exact asset) — https://www.equinix.com
- Owner: JEMB Realty (exact asset)
- Utility: Public Service Electric & Gas Co. (exact asset)

## Power and grid context

- Utility service: 6 MW · reported · exact asset — Access to 6.0 MW of power
- Utility service: 10 MW · reported · exact asset — 10 MW of power
- ISO/RTO: PJM
- Balancing authority: PJM
- Electric utility: Public Service Electric & Gas Co.

## Development

- Site area: 20 acres
- Gross floor area: 131,040 square feet
- Buildings: 1
- Construction: NY2 was built in 1999, renovated in 2002, and currently operates as a 1‑story steel‑frame building with 131,040 ft² gross floor area, 6 MW power capacity, 7 generators, and N+1 redundancy.

## Compute and operations

- Facility classes: colocation, enterprise
- Workloads: AI, high-density workloads
- Operating context: Equinix NY2 is an operating Tier 3 colocation data center in Secaucus, NJ, offering carrier‑neutral connectivity, fiber cross‑connects, N+1 power and cooling redundancy, and supporting AI and high‑density workloads for large financial, media, and enterprise customers.

## Sources

- [http://api.eia.gov/v2/electricity/operating-generator-capacity/data?api_key=DEMO_KEY&data[]=county&data[]=latitude&data[]=longitude&data[]=nameplate-capacity-mw&data[]=net-summer-capacity-mw&data[]=net-winter-capacity-mw&data[]=operating-year-month&data[]=planned-retirement-year-month&end=2026-06&facets[plantid][]=66314&frequency=monthly&start=2026-06](http://api.eia.gov/v2/electricity/operating-generator-capacity/data?api_key=DEMO_KEY&data[]=county&data[]=latitude&data[]=longitude&data[]=nameplate-capacity-mw&data[]=net-summer-capacity-mw&data[]=net-winter-capacity-mw&data[]=operating-year-month&data[]=planned-retirement-year-month&end=2026-06&facets[plantid][]=66314&frequency=monthly&start=2026-06)
- [CoreSite Secaucus NY2 Data Center](http://baxtel.com/data-center/coresite-secaucus-ny2)
- [Equinix New York Secaucus NY2 Data Center](http://baxtel.com/data-center/equinix-new-york-secaucus-ny2)
- [http://baxtel.com/news/data-centers/equinix-secaucus-ny2-ny4-ny5-ny6?page=2](http://baxtel.com/news/data-centers/equinix-secaucus-ny2-ny4-ny5-ny6?page=2)
- [http://blog.equinix.com/blog/2024/09/19/how-data-centers-use-water-and-how-were-working-to-use-water-responsibly](http://blog.equinix.com/blog/2024/09/19/how-data-centers-use-water-and-how-were-working-to-use-water-responsibly)
- [http://blog.equinix.com/blog/2025/03/20/how-data-centers-can-use-alternative-water-sources](http://blog.equinix.com/blog/2025/03/20/how-data-centers-can-use-alternative-water-sources)
- [Equinix - New York (Secaucus) Data Center NY2 - Cloud and Colocation](http://cloudandcolocation.com/datacenters/equinix-new-york-secaucus-data-center-ny2)
- [http://datacenterhawk.com/marketplace/providers/equinix/275-hartz-way/ny2](http://datacenterhawk.com/marketplace/providers/equinix/275-hartz-way/ny2)
- [http://dchub.cloud/facilities/equinix-inc-equinix-ny2ny4ny5ny6-new-york-secaucus-b3ebf9b7](http://dchub.cloud/facilities/equinix-inc-equinix-ny2ny4ny5ny6-new-york-secaucus-b3ebf9b7)
- [NY-5 Preconstruction Permit and Certificate to Operate Permit Application/Secaucus, NJ NOTICE OF INTENT TO MODIFY AIR PERMITS Air Pollution Control](http://dep.nj.gov/wp-content/uploads/ej/bloom-equinix-notice-12052023.pdf)
- [NY2](http://equinix.com/data-centers/americas-colocation/united-states-colocation/new-york-data-centers/ny2)
- [http://equinix.com/data-centers/americas-colocation/united-states-colocation/new-york-data-centers/ny3](http://equinix.com/data-centers/americas-colocation/united-states-colocation/new-york-data-centers/ny3)
- [http://godatacenters.com/data-centers/new-jersey/secaucus/equinix-ny2-64769f32](http://godatacenters.com/data-centers/new-jersey/secaucus/equinix-ny2-64769f32)
- [http://investor.equinix.com/news-events/press-releases/detail/264/equinix-to-install-largest-deployment-of-fuel-cells-for-the](http://investor.equinix.com/news-events/press-releases/detail/264/equinix-to-install-largest-deployment-of-fuel-cells-for-the)
- [http://nj.gov/bpu/pdf/boardorders/2024/20240417/8A%20ORDER%20Equinix%20Inc%20Energy%20Efficiency%20Incentives.pdf](http://nj.gov/bpu/pdf/boardorders/2024/20240417/8A%20ORDER%20Equinix%20Inc%20Energy%20Efficiency%20Incentives.pdf)
- [http://nj.pseg.com/serviceterritory](http://nj.pseg.com/serviceterritory)
- [http://njpropertyrecords.com/property/0909_22_2_HM](http://njpropertyrecords.com/property/0909_22_2_HM)
- [http://ocolo.io/colocation/equinix/ny2-secaucus](http://ocolo.io/colocation/equinix/ny2-secaucus)
- [http://peeringdb.com/fac/36](http://peeringdb.com/fac/36)
- [http://woolpert.com/projects/ny5](http://woolpert.com/projects/ny5)
- [Equinix New York Secaucus NY2 Data Center](https://baxtel.com/data-center/equinix-new-york-secaucus-ny2)
- [Secaucus, New Jersey](https://en.wikipedia.org/wiki/Secaucus,_New_Jersey)
- [The AI data center boom is the next environmental crisis and it’s already starting &bull; Jersey Vindicator](https://jerseyvindicator.org/2026/03/15/the-ai-data-center-boom-is-the-next-environmental-crisis-and-its-already-starting/)
- [Equinix NY2 Data Center, Secaucus, NJ, USA](https://marketplace.upstack.com/data-centers/equinix-data-center-new-jersey-ny2)
- [New Jersey Data Centers — 31 Facilities | USDataMap](https://usdatamap.com/state/NJ)
- [Equinix Data Center in Secaucus, New Jersey](https://www.datacenters.com/equinix-ny2-secaucus)
- [NY2](https://www.equinix.com/data-centers/americas-colocation/united-states-colocation/new-york-data-centers/ny2)
- [275 Hartz Way, Secaucus, NJ 07094](https://www.loopnet.com/Listing/275-Hartz-Way-Secaucus-NJ/4932450/)
- [Red Rash - 15 Meadowlands Pkwy, Secaucus, NJ, 07094](https://www.mapquest.com/us/new-jersey/ntr-substation-red-rash-783050140)
- [With AI booming, NJ is a growing data center hub](https://www.northjersey.com/picture-gallery/news/business/2025/12/02/with-ai-booming-nj-is-a-growing-data-center-hub/87326574007/) — NorthJersey.com · 2025-12-02
- [Equinix New York Secaucus NY2 — Data Centre · Equinix | OverWatts](https://www.overwatts.com/asset/osm-way-193611219)

## Data quality

- Power values retain their reported, requested, contracted, energized, gross-campus, or critical-IT basis.

---

Canonical page: https://askthegrid.com/assets/facilities/equinix-ny2
Profile generated: 2026-09-04T16:40:08.516284Z
Source: Ask the Grid — https://askthegrid.com/