## Current generation inventory

EIA plant 68915 · Inventory reporting month: 2026-08.

- batteries: 200 MW operating nameplate
- Capacity basis: operating_generator_nameplate_mw
- Source inventory: [EIA-860M workbook (preliminary)](https://www.eia.gov/electricity/data/eia860m/xls/august_generator2026.xlsx)
- Inventory retrieved: 2026-10-10T02:12:40.665346+00:00
- Filed coordinate (longitude, latitude): -98.57653, 29.34836
- OSM extract: 2026-10-08T20:21:06Z
- OSM mapped edit: 2026-09-18 17:44:07+00:00
- Map prepared: 2026-10-10T02:28:19.273985+00:00

Battery power (MW) and stored energy (MWh) are separate measures. Shared physical-site membership does not establish electrical connectivity, settlement or a common export limit.

## Reviewed overview

Ferdinand Energy Center is a 200 MW batteries plant in Bexar County. Ferdinand is a 200 MW, four-hour battery storage project in south Bexar County, Texas, developed by Eolian L.P. CPS Energy contracted its capacity under a storage capacity agreement announced in August 2024, alongside the 150 MW Padua 2 project. Both were expected online in the first half of 2026 as part of CPS Energy's Vision 2027 generation plan.

## Reviewed metrics

- **Nameplate capacity:** 200 MW — Canonical EIA plant baseline.
- **Registry anchor:** Plant 68915 — plant-68915

## Facts

- **Technology:** Batteries
- **Operator:** Ferdinand Grid, LLC

## Related parties

- **Offtaker:** CPS Energy — offtaker ([source](https://www.cpsenergy.com))

## Sources

- [publicpower.org](https://www.publicpower.org/periodical/article/cps-energy-secures-350-mw-future-battery-energy-storage) — publicpower.org · public_source — Source retained for exact-record publication review.

---

Canonical page: https://askthegrid.com/assets/facilities/ferdinand-energy-center