The Genesis Solar Energy Project is a 250 MW, two-unit concentrated solar thermal power facility in eastern Riverside County, California, approximately 25 miles west of Blythe. The facility uses parabolic-trough solar collectors (1,840 SENERtrough assemblies in 460 loops), heated thermal oil (Therminol VP-1), solar steam generators, steam turbine generators, and air-cooled dry cooling. Each unit is nominally 125 MW. The project occupies approximately 1,800 acres on Bureau of Land Management land and interconnects via an approximately 7-mile, 230-kV transmission line to Southern California Edison's Colorado River Substation. The facility is operated by Genesis Solar LLC, a subsidiary of NextEra Energy Resources LLC, and sells electricity to PG&E under a 25-year power purchase agreement.

## Metrics

- **Nameplate capacity:** 250 MW — Canonical EIA plant baseline.
- **Registry anchor:** Plant 57394 — plant-57394

## Facts

- **Technology:** Solar Thermal without Energy Storage
- **Operator:** Genesis Solar LLC

## Related parties

- **Owner / developer:** NextEra Energy Resources LLC — Project Owner ([source](https://www.nexteraenergyresources.com))
- **EPC contractor / construction contractor:** Blattner Energy — EPC Contractor
- **Offtaker / power marketer:** Pacific Gas & Electric Company (PG&E) — Electricity Generation Offtaker ([source](https://www.pge.com))
- **EPC contractor / equipment supplier:** Sener — Solar Collector Manufacturer; Collector Engineering/IP Owner ([source](https://www.sener.es))
- **Equipment supplier:** Eastman/Solutia — Receiver Working-Fluid Manufacturer ([source](https://www.eastman.com))
- **Equipment supplier:** ARB Inc. — Receiver Manufacturer
- **Transmission owner / interconnecting utility:** Southern California Edison — Transmission Owner; Interconnection Utility ([source](https://www.sce.com))
- **Lender / lead arranger:** Credit Suisse — Loan-Guarantee Applicant; Project-Bond Purchaser; Term-Loan Lender ([source](https://www.ubs.com))
- **Investor / tax equity investor / equity investor:** Kohlberg Kravis Roberts & Co. (KKR) — Portfolio Financing Investor ([source](https://www.kkr.com))
- **Owner / asset manager:** NextEra Energy Partners, LP — Portfolio Acquirer and Asset Manager
- **Parent company:** NextEra Energy Inc. — Parent Company

## Sources

- [sec.gov](http://sec.gov/Archives/edgar/data/1603145/000160314515000101/R10.htm) — sec.gov · authoritative — Source retained for exact-record publication review.
- [sec.gov](http://sec.gov/Archives/edgar/data/1603145/000160314520000073/nep-20201218.htm) — sec.gov · authoritative — Source retained for exact-record publication review.
- [docs.cpuc.ca.gov](https://docs.cpuc.ca.gov/PUBLISHED/FINAL_RESOLUTION/122173.htm) — docs.cpuc.ca.gov · authoritative — Source retained for exact-record publication review.
- [newsroom.nexteraenergy.com](https://newsroom.nexteraenergy.com/NextEra-Energy-Resources-subsidiary-closes-on-935-million-financing-and-secures-a-DOE-loan-guarantee-for-its-Genesis-solar-project?l=12) — newsroom.nexteraenergy.com · public_source — Source retained for exact-record publication review.
- [About Blattner](https://www.blattnercompany.com/about) — Blattner Company · authoritative — Official company page identifying Blattner Energy and its utility-scale EPC role.

---

Canonical page: https://askthegrid.com/assets/facilities/genesis-solar-energy-project
Website: [NextEra Energy Resources LLC](https://www.nexteraenergyresources.com)

Source: Ask the Grid — https://askthegrid.com/