Hopkins Solar is a 250 MW photovoltaic facility in Hopkins County, Texas. EIA's May 2026 inventory lists one operating generator under Plant ID 67424, with service beginning in June 2024 and Hopkins Energy LLC as the registered operator. ENGIE describes the project as a long-term owned and operated 250 MW ERCOT asset and reports operation since 2023. A Texas regulatory filing identifies Hopkins Energy LLC as an indirect ENGIE subsidiary and Oncor as the interconnection counterparty. The different operation dates are retained with their source scopes rather than collapsed into one date.

## Profile

- **Grid role:** Utility-scale photovoltaic generation in ERCOT.
- **Operating record:** 250 MW · Jun 2024 EIA service month · ENGIE reports operation since 2023.
- **Corporate structure:** Hopkins Energy LLC is the project company and an indirect ENGIE subsidiary.
- **Interconnection:** Texas regulatory filing identifies Oncor as the interconnection counterparty.

## Metrics

- **Operating capacity:** 250 MW — EIA and ENGIE
- **EIA service month:** Jun 2024 — Plant 67424
- **Developer operation year:** 2023 — ENGIE
- **Registry anchor:** Plant 67424 — Hopkins Energy LLC

## Facts

- **Operating capacity:** 250 MW — EIA and ENGIE · confidence: high
- **Registered operator:** Hopkins Energy LLC — EIA · confidence: high
- **Parent and long-term operator:** ENGIE — ENGIE and Texas filing · confidence: high
- **Interconnection counterparty:** Oncor — Texas filing · confidence: high

## Related parties

- **Project company and EIA registered operator:** Hopkins Energy LLC — EIA May 2026 generator inventory
- **Indirect parent long-term owner and operator:** ENGIE North America — ENGIE Hopkins project page ([source](https://www.engie-na.com/))
- **Interconnection counterparty:** Oncor Electric Delivery — Hopkins Texas regulatory filing ([source](https://www.oncor.com/))

## Sources

- [EIA May 2026 generator inventory](https://www.eia.gov/electricity/data/eia860m/) — U.S. Energy Information Administration · regulatory — Current generator records, capacity scopes, dates, status, operator, and technology.
- [ENGIE Hopkins project page](https://www.engie-na.com/project/hopkins/) — ENGIE North America · official — Project capacity location ownership and developer-reported operation year.
- [Hopkins Texas regulatory filing](https://interchange.puc.texas.gov/Documents/20311_541_1326602.PDF) — Public Utility Commission of Texas · regulatory — Project-company ENGIE affiliation and Oncor interconnection context.

---

Canonical page: https://askthegrid.com/assets/facilities/hopkins-energy-llc
Website: [ENGIE](https://www.engie-na.com/project/hopkins/)
Profile published: 2026-07-17T03:34:25.456Z
Source: Ask the Grid — https://askthegrid.com/