# Hudson - High Desert Hybrid

CAISO Batteries, Solar Photovoltaic · https://askthegrid.com/assets/facilities/hudson-high-desert-hybrid

Hudson - High Desert Hybrid is a hybrid solar and battery storage facility with 150 MW of EIA-reported total operating capacity and 50 MWh of reported storage energy capacity in San Bernardino County, California, registered as EIA Plant ID 64624. MN8 Energy LLC is the registered plant entity or operator. Project filings list 295,344 solar panels and 123 inverters for the facility. Commercial operation began on August 1, 2021.

## Key facts

- Technology: Batteries, Solar Photovoltaic
- Power capacity: 150 MW
- Operating status: operating

## Grid and market context

- ISO/RTO: CAISO
- Balancing authority: CISO

## Source-backed facts

- Identifiers: [{"value":"64624","system":"EIA plant ID"},{"value":"61944","system":"EIA utility ID"},{"value":"BESS1","system":"EIA generator ID"},{"value":"GEN1","system":"EIA generator ID"},{"value":"32181","system":"FERC EIA ID"},{"value":"64624","system":"FERC plant code"},{"value":"C011798","system":"FERC company identifier (CID)"},{"value":"ER21-133-000","system":"FERC MBR docket"},{"value":"21-2","system":"FERC exempt-wholesale-generator docket"},{"value":"CISO","system":"Balancing authority"},{"value":"CAISO","system":"Power market / ISO"}] — MBR | Index · confidence: medium
- Description: Hudson - High Desert Hybrid is an operational 150 MW solar-and-battery power plant in San Bernardino County, California, near Victorville. The facility has two generating units: a 100 MW photovoltaic generator and a 50 MW battery energy-storage generator. The solar portion came online in August 2021, and the plant's EIA record lists December 2021 as the first unit operation date. MN8 Energy LLC is the listed operator, while HDSI, LLC is identified as the owner of both generators. — New Solar-plus-Storage Clean Energy Facility Now Online · confidence: medium
- Identifiers.4: {"value":"32181","system":"FERC EIA ID"} — MBR | Index · confidence: medium
- Parties.2: {"relationship":"Historical owner / project acquirer","name":"Goldman Sachs Renewable Power","official_url":"https://www.gsam.com/"} — New Solar-plus-Storage Clean Energy Facility Now Online · confidence: medium
- Parties.3: {"relationship":"Developer","name":"Middle River Power","official_url":"https://middleriverpower.com/"} — High Desert Solar Project, US · confidence: medium
- Parties.5: {"relationship":"Solar inverter and power-station OEM","name":"Ingeteam Inc.","official_url":"https://www.ingeteam.com/en"} — Ingeteam makes its largest supply of solar inverters in the US | Ingeteam · confidence: high
- Parties.6: {"relationship":"Offtaker / power-purchase-agreement counterparty","name":"Clean Power Alliance","official_url":"https://cleanpoweralliance.org/"} — New Solar-plus-Storage Clean Energy Facility Now Online · confidence: high
- Parties.9: {"relationship":"Sale transaction adviser","name":"Marathon Capital, LLC","official_url":null} — Marathon Capital Advises Middle River Power on Sale of California Solar Project · confidence: high
- Interconnection: SCE Victor Substation; the project’s 230-kV gen-tie connects to the Victor-Caldwell 230-kV line upstream of the first pole on the Southern California Edison system. — High Desert Solar Project · confidence: medium
- Commercial operation date: 2021-10-15 — New Solar-plus-Storage Clean Energy Facility Now Online · confidence: medium
- Battery units: 321 — New Solar-plus-Storage Clean Energy Facility Now Online · confidence: medium
- Product url: https://www.ingeteam.com/en/Pressroom/Corporate/tabid/1574/articleType/ArticleView/articleId/3234/Ingeteam-makes-its-largest-supply-of-solar-inverters-in-the-US.aspx — Ingeteam makes its largest supply of solar inverters in the US | Ingeteam · confidence: high
- Pcs or inverters: 123 — Ingeteam makes its largest supply of solar inverters in the US | Ingeteam · confidence: medium
- Kind: solar — New Solar-plus-Storage Clean Energy Facility Now Online · confidence: medium
- Manufacturer domain: ingeteam.com — Ingeteam makes its largest supply of solar inverters in the US | Ingeteam · confidence: high
- Modules or panels: 295344 — New Solar-plus-Storage Clean Energy Facility Now Online · confidence: high
- Equipment models: [{"manufacturer_domain":"ingeteam.com","product_url":"https://www.ingeteam.com/en/Pressroom/Corporate/tabid/1574/articleType/ArticleView/articleId/3234/Ingeteam-makes-its-largest-supply-of-solar-inverters-in-the-US.aspx","count":123,"unit_mw":3.28,"name":"DUAL INGECON SUN 1640TL U B630"}] — Ingeteam makes its largest supply of solar inverters in the US | Ingeteam · confidence: medium
- Product family: DUAL INGECON SUN 1640TL U B630 — Ingeteam makes its largest supply of solar inverters in the US | Ingeteam · confidence: high
- Manufacturer name: Ingeteam — Ingeteam makes its largest supply of solar inverters in the US | Ingeteam · confidence: high
- Equipment models.0: {"manufacturer_domain":"ingeteam.com","product_url":"https://www.ingeteam.com/en/Pressroom/Corporate/tabid/1574/articleType/ArticleView/articleId/3234/Ingeteam-makes-its-largest-supply-of-solar-inverters-in-the-US.aspx","count":123,"unit_mw":3.28,"name":"DUAL INGECON SUN 1640TL U B630"} — Ingeteam makes its largest supply of solar inverters in the US | Ingeteam · confidence: medium
- Description: Hudson - High Desert Hybrid is an operational 150 MW CAISO facility near Victorville in San Bernardino County, comprising a 100 MW photovoltaic generator and a 50 MW battery-storage generator. EIA data identify HDSI, LLC as the owner of both generators and MN8 Energy LLC as the operator. Middle River Power developed the project and sold it in August 2020 to Goldman Sachs Renewable Power, which completed the solar-plus-storage facility under a 15-year power-purchase agreement with Clean Power Alliance. The solar portion came online on August 19, 2021, and Clean Power Alliance commemorated full operations on October 15, 2021. — Marathon Capital · confidence: medium
- Description: Hudson - High Desert Hybrid is an operational 150 MW CAISO facility near Victorville in San Bernardino County, comprising a 100 MW photovoltaic generator and a 50 MW battery-storage generator. EIA data identify HDSI, LLC as the owner of both generators and MN8 Energy LLC as the operator. Middle River Power developed the project and sold it in August 2020 to Goldman Sachs Renewable Power, which completed the solar-plus-storage facility under a 15-year power-purchase agreement with Clean Power Alliance. The solar portion came online on August 19, 2021, and Clean Power Alliance commemorated full operations on October 15, 2021. — New Solar-plus-Storage Clean Energy Facility Now Online · confidence: medium
- Quality notes: ["Operation dates differ by milestone: the PPA listed August 1, 2021 as the expected commercial-operation date, Clean Power Alliance reported solar service beginning August 19, 2021 and full operations on October 15, 2021, while the EIA record lists December 2021 as the first-operation date for both units.","The contemporaneous sale announcement identifies Middle River Power as seller and Goldman Sachs Renewable Power as buyer. Middle River Power's later corporate timeline labels the August 2020 sale as a sale to MN8 Energy; MN8's June 2022 announcement explains that Goldman Sachs Renewable Power was separated into an independent company renamed MN8 Energy.","The EIA 860 record lists the 100 MW PV and 50 MW battery units as operating, with no completed uprate or derate and no planned units; no separate expansion or repowering milestone is reflected in the operating record. The 50 MW battery rating is nameplate power and should not be treated as a separately verified MWh duration."] — New Solar-plus-Storage Clean Energy Facility Now Online · confidence: medium
- Quality notes: ["Operation dates differ by milestone: the PPA listed August 1, 2021 as the expected commercial-operation date, Clean Power Alliance reported solar service beginning August 19, 2021 and full operations on October 15, 2021, while the EIA record lists December 2021 as the first-operation date for both units.","The contemporaneous sale announcement identifies Middle River Power as seller and Goldman Sachs Renewable Power as buyer. Middle River Power's later corporate timeline labels the August 2020 sale as a sale to MN8 Energy; MN8's June 2022 announcement explains that Goldman Sachs Renewable Power was separated into an independent company renamed MN8 Energy.","The EIA 860 record lists the 100 MW PV and 50 MW battery units as operating, with no completed uprate or derate and no planned units; no separate expansion or repowering milestone is reflected in the operating record. The 50 MW battery rating is nameplate power and should not be treated as a separately verified MWh duration."] — Marathon Capital · confidence: medium
- Quality notes: ["Operation dates differ by milestone: the PPA listed August 1, 2021 as the expected commercial-operation date, Clean Power Alliance reported solar service beginning August 19, 2021 and full operations on October 15, 2021, while the EIA record lists December 2021 as the first-operation date for both units.","The contemporaneous sale announcement identifies Middle River Power as seller and Goldman Sachs Renewable Power as buyer. Middle River Power's later corporate timeline labels the August 2020 sale as a sale to MN8 Energy; MN8's June 2022 announcement explains that Goldman Sachs Renewable Power was separated into an independent company renamed MN8 Energy.","The EIA 860 record lists the 100 MW PV and 50 MW battery units as operating, with no completed uprate or derate and no planned units; no separate expansion or repowering milestone is reflected in the operating record. The 50 MW battery rating is nameplate power and should not be treated as a separately verified MWh duration."] — Middle River Power | Leading the Energy Transition · confidence: medium
- Financing summary: No closed project-level debt or tax-equity amount or lender is identified in the available project materials. The public PPA requires financing commitments sufficient to construct the facility and permits tax-equity or portfolio financing, but its financing provisions do not disclose executed financing terms. A secondary project profile reports an estimated project cost of $107.8 million; this is a project-cost estimate, not sale consideration or a financing amount. — High Desert Solar Project, US · confidence: medium
- Timeline: [{"event":"Development initiated","date":"2017","detail":"Middle River Power's corporate project history says development began on the High Desert Solar and battery-storage project."},{"event":"Project sale announced and completed","date":"2020-08-19","detail":"Marathon Capital announced that it advised Middle River Power, the operating and development platform of Avenue Capital, on the sale of the 100 MW AC solar and 50 MW AC battery project to Goldman Sachs Renewable Power. The transaction amount was undisclosed."},{"event":"Construction-start certificate","date":"2020-11-20","detail":"The public High 5 Solar PPA includes a construction-start date certificate executed by HDSI, LLC and dated November 20, 2020."},{"event":"Expected commercial operation","date":"2021-08-01","detail":"The PPA cover sheet listed August 1, 2021 as the expected commercial-operation date and provided for a 15-contract-year delivery term."},{"event":"Solar generation began","date":"2021-08-19","detail":"Clean Power Alliance reported that the 100 MW photovoltaic portion came online on August 19, 2021."},{"event":"Full operations commemorated","date":"2021-10-15","detail":"Clean Power Alliance and Goldman Sachs held a ribbon-cutting event to commemorate commencement of full operations, with 100 MW of generation capacity and 50 MW of storage capacity serving the alliance."},{"event":"EIA first-operation date","date":"2021-12","detail":"The EIA-derived plant record lists December 2021 as the first-operation date for both the 100 MW solar generator and the 50 MW battery generator."},{"event":"Goldman Sachs Renewable Power separated into MN8 Energy","date":"2022-06-02","detail":"Goldman Sachs Asset Management announced an agreement to separate Goldman Sachs Renewable Power LLC into an independent company to be renamed MN8 Energy, providing the corporate succession underlying the later MN8 operator name."}] — Middle River Power | Leading the Energy Transition · confidence: medium
- Timeline: [{"event":"Development initiated","date":"2017","detail":"Middle River Power's corporate project history says development began on the High Desert Solar and battery-storage project."},{"event":"Project sale announced and completed","date":"2020-08-19","detail":"Marathon Capital announced that it advised Middle River Power, the operating and development platform of Avenue Capital, on the sale of the 100 MW AC solar and 50 MW AC battery project to Goldman Sachs Renewable Power. The transaction amount was undisclosed."},{"event":"Construction-start certificate","date":"2020-11-20","detail":"The public High 5 Solar PPA includes a construction-start date certificate executed by HDSI, LLC and dated November 20, 2020."},{"event":"Expected commercial operation","date":"2021-08-01","detail":"The PPA cover sheet listed August 1, 2021 as the expected commercial-operation date and provided for a 15-contract-year delivery term."},{"event":"Solar generation began","date":"2021-08-19","detail":"Clean Power Alliance reported that the 100 MW photovoltaic portion came online on August 19, 2021."},{"event":"Full operations commemorated","date":"2021-10-15","detail":"Clean Power Alliance and Goldman Sachs held a ribbon-cutting event to commemorate commencement of full operations, with 100 MW of generation capacity and 50 MW of storage capacity serving the alliance."},{"event":"EIA first-operation date","date":"2021-12","detail":"The EIA-derived plant record lists December 2021 as the first-operation date for both the 100 MW solar generator and the 50 MW battery generator."},{"event":"Goldman Sachs Renewable Power separated into MN8 Energy","date":"2022-06-02","detail":"Goldman Sachs Asset Management announced an agreement to separate Goldman Sachs Renewable Power LLC into an independent company to be renamed MN8 Energy, providing the corporate succession underlying the later MN8 operator name."}] — Marathon Capital · confidence: medium
- Timeline: [{"event":"Development initiated","date":"2017","detail":"Middle River Power's corporate project history says development began on the High Desert Solar and battery-storage project."},{"event":"Project sale announced and completed","date":"2020-08-19","detail":"Marathon Capital announced that it advised Middle River Power, the operating and development platform of Avenue Capital, on the sale of the 100 MW AC solar and 50 MW AC battery project to Goldman Sachs Renewable Power. The transaction amount was undisclosed."},{"event":"Construction-start certificate","date":"2020-11-20","detail":"The public High 5 Solar PPA includes a construction-start date certificate executed by HDSI, LLC and dated November 20, 2020."},{"event":"Expected commercial operation","date":"2021-08-01","detail":"The PPA cover sheet listed August 1, 2021 as the expected commercial-operation date and provided for a 15-contract-year delivery term."},{"event":"Solar generation began","date":"2021-08-19","detail":"Clean Power Alliance reported that the 100 MW photovoltaic portion came online on August 19, 2021."},{"event":"Full operations commemorated","date":"2021-10-15","detail":"Clean Power Alliance and Goldman Sachs held a ribbon-cutting event to commemorate commencement of full operations, with 100 MW of generation capacity and 50 MW of storage capacity serving the alliance."},{"event":"EIA first-operation date","date":"2021-12","detail":"The EIA-derived plant record lists December 2021 as the first-operation date for both the 100 MW solar generator and the 50 MW battery generator."},{"event":"Goldman Sachs Renewable Power separated into MN8 Energy","date":"2022-06-02","detail":"Goldman Sachs Asset Management announced an agreement to separate Goldman Sachs Renewable Power LLC into an independent company to be renamed MN8 Energy, providing the corporate succession underlying the later MN8 operator name."}] — New Solar-plus-Storage Clean Energy Facility Now Online · confidence: medium
- Timeline.0: {"event":"Development initiated","date":"2017","detail":"Middle River Power's corporate project history says development began on the High Desert Solar and battery-storage project."} — Middle River Power | Leading the Energy Transition · confidence: medium
- Timeline.1: {"event":"Project sale announced and completed","date":"2020-08-19","detail":"Marathon Capital announced that it advised Middle River Power, the operating and development platform of Avenue Capital, on the sale of the 100 MW AC solar and 50 MW AC battery project to Goldman Sachs Renewable Power. The transaction amount was undisclosed."} — Marathon Capital · confidence: high
- Timeline.3: {"event":"Expected commercial operation","date":"2021-08-01","detail":"The PPA cover sheet listed August 1, 2021 as the expected commercial-operation date and provided for a 15-contract-year delivery term."} — Source · confidence: high
- Timeline.4: {"event":"Solar generation began","date":"2021-08-19","detail":"Clean Power Alliance reported that the 100 MW photovoltaic portion came online on August 19, 2021."} — New Solar-plus-Storage Clean Energy Facility Now Online · confidence: high
- Timeline.5: {"event":"Full operations commemorated","date":"2021-10-15","detail":"Clean Power Alliance and Goldman Sachs held a ribbon-cutting event to commemorate commencement of full operations, with 100 MW of generation capacity and 50 MW of storage capacity serving the alliance."} — New Solar-plus-Storage Clean Energy Facility Now Online · confidence: high
- Commercial parties.0: {"relationship":"Legal owner of generating units and PPA seller","name":"HDSI, LLC","detail":"EIA data identify HDSI, LLC as the 100% owner of both the BESS1 and GEN1 generators. HDSI, LLC is also the seller named in the High 5 Solar PPA with Clean Power Alliance.","official_url":null} — Source · confidence: high
- Commercial parties.2: {"relationship":"Historical acquirer and project owner during construction","name":"Goldman Sachs Renewable Power","detail":"Goldman Sachs Renewable Power acquired the 150 MW High Desert Solar project from Middle River Power in August 2020 and announced completion of its first internally built solar-plus-storage project.","official_url":"https://www.gsam.com/"} — Marathon Capital · confidence: high
- Commercial parties.2: {"relationship":"Historical acquirer and project owner during construction","name":"Goldman Sachs Renewable Power","detail":"Goldman Sachs Renewable Power acquired the 150 MW High Desert Solar project from Middle River Power in August 2020 and announced completion of its first internally built solar-plus-storage project.","official_url":"https://www.gsam.com/"} — New Solar-plus-Storage Clean Energy Facility Now Online · confidence: high
- Commercial parties.3: {"relationship":"Developer and historical seller","name":"Middle River Power","detail":"Middle River Power developed the High Desert Solar and battery-storage project and sold it to Goldman Sachs Renewable Power in August 2020. Its sale announcement describes it as the operating and development platform of Avenue Capital.","official_url":"https://middleriverpower.com/"} — Marathon Capital · confidence: high
- Commercial parties.4: {"relationship":"Offtaker and PPA buyer","name":"Clean Power Alliance of Southern California","detail":"Clean Power Alliance executed a 15-year PPA with HDSI, LLC for the project's full energy output, resource adequacy, and ancillary attributes.","official_url":"https://cleanpoweralliance.org/"} — Marathon Capital · confidence: high
- Commercial parties.5: {"relationship":"Sale transaction adviser","name":"Marathon Capital, LLC","detail":"Marathon Capital advised Middle River Power as exclusive adviser during the marketing, power-marketing, and execution process for the project sale.","official_url":"https://marathoncapital.com/"} — Marathon Capital · confidence: high
- Commercial parties.6: {"relationship":"Developer and EPC partner","name":"Swinerton Renewable Energy","detail":"Project profiles identify Middle River Power and Swinerton Renewable Energy as the developers; Swinerton's business includes engineering, procurement, and construction for solar PV and energy-storage facilities.","official_url":"https://swinerton.com/"} — Power plant profile: High Desert Solar Project, US · confidence: medium
- Commercial parties.7: {"relationship":"Solar inverter supplier and commissioning contractor","name":"Ingeteam Inc.","detail":"Ingeteam supplied the High Desert project's solar power-station equipment and inverters and commissioned the High Desert solar plant.","official_url":"https://www.ingeteam.com/en"} — Ingeteam supplies inverters for 350 MW of solar projects - pv magazine USA · confidence: high
- Quality notes.0: Operation dates differ by milestone: the PPA listed August 1, 2021 as the expected commercial-operation date, Clean Power Alliance reported solar service beginning August 19, 2021 and full operations on October 15, 2021, while the EIA record lists December 2021 as the first-operation date for both units. — High Desert Solar Project, US · confidence: medium
- Quality notes.1: The contemporaneous sale announcement identifies Middle River Power as seller and Goldman Sachs Renewable Power as buyer. Middle River Power's later corporate timeline labels the August 2020 sale as a sale to MN8 Energy; MN8's June 2022 announcement explains that Goldman Sachs Renewable Power was separated into an independent company renamed MN8 Energy. — Source · confidence: high
- Quality notes.1: The contemporaneous sale announcement identifies Middle River Power as seller and Goldman Sachs Renewable Power as buyer. Middle River Power's later corporate timeline labels the August 2020 sale as a sale to MN8 Energy; MN8's June 2022 announcement explains that Goldman Sachs Renewable Power was separated into an independent company renamed MN8 Energy. — New Solar-plus-Storage Clean Energy Facility Now Online · confidence: high
- Quality notes.2: The EIA 860 record lists the 100 MW PV and 50 MW battery units as operating, with no completed uprate or derate and no planned units; no separate expansion or repowering milestone is reflected in the operating record. The 50 MW battery rating is nameplate power and should not be treated as a separately verified MWh duration. — Middle River Power | Leading the Energy Transition · confidence: medium
- Acquisition detail: Middle River Power sold the exact High Desert Solar Project—100 MW AC solar plus 50 MW AC battery storage in San Bernardino County—to Goldman Sachs Renewable Power. Goldman Sachs Renewable Power was later renamed MN8 Energy LLC. — Marathon Capital · confidence: high
- Seller: Middle River Power — Marathon Capital · confidence: high
- Acquirer: Goldman Sachs Renewable Power (GSRP; later renamed MN8 Energy LLC) — Marathon Capital · confidence: high
- Transaction scope: exact_asset — Goldman Sachs buys 150 MW High Desert Solar Project in San B... | Energy Finance & Investment · confidence: high
- Interconnection voltage kv: 230 — High Desert Solar Project · confidence: medium
- Transmission owner: Southern California Edison — High Desert Solar Project · confidence: medium
- Grid role: Solar-plus-storage energy shifting and renewable firming: the battery stores solar energy generated during the day and delivers it to the grid when customers need it. — New Solar-plus-Storage Clean Energy Facility Now Online · confidence: high
- Grid role: Solar-plus-storage energy shifting and renewable firming: the battery stores solar energy generated during the day and delivers it to the grid when customers need it. — High Desert Solar Project · confidence: high

## Timeline

- 2017 — Development initiated
  Middle River Power's corporate project history says development began on the High Desert Solar and battery-storage project.
  Source: Middle River Power | Leading the Energy Transition (https://middleriverpower.com/)
- 2021-08-01 — Planned commercial operation
  The PPA cover sheet listed August 1, 2021 as the expected commercial-operation date and provided for a 15-contract-year delivery term.
  Source: Source (https://files.cleanpoweralliance.org/uploads/2021/02/High-5-Solar-PUBLIC.pdf)
- 2021-08-19 — Solar generation began
  Clean Power Alliance reported that the 100 MW photovoltaic portion came online on August 19, 2021.
  Source: New Solar-plus-Storage Clean Energy Facility Now Online (https://cleanpoweralliance.org/2022/03/25/new-solar-plus-storage-clean-energy-facility-now-online/)
- 2021-10-15 — Full operations commemorated
  Clean Power Alliance and Goldman Sachs held a ribbon-cutting event to commemorate commencement of full operations, with 100 MW of generation capacity and 50 MW of storage capacity serving the alliance.
  Source: New Solar-plus-Storage Clean Energy Facility Now Online (https://cleanpoweralliance.org/2022/03/25/new-solar-plus-storage-clean-energy-facility-now-online/)

## Sources

- [MBR | Index](https://mbrweb.ferc.gov/SearchlkpEIA/Index?page=639) — mbrweb.ferc.gov · tier regulatory
- [New Solar-plus-Storage Clean Energy Facility Now Online](https://cleanpoweralliance.org/2022/03/25/new-solar-plus-storage-clean-energy-facility-now-online/) — cleanpoweralliance.org · tier other
- [High Desert Solar Project, US](https://www.power-technology.com/marketdata/high-desert-solar-project-us/) — power-technology.com · tier other
- [Ingeteam makes its largest supply of solar inverters in the US | Ingeteam](https://www.ingeteam.com/en/Pressroom/Corporate/tabid/1574/articleType/ArticleView/articleId/3234/Ingeteam-makes-its-largest-supply-of-solar-inverters-in-the-US.aspx) — ingeteam.com · tier other
- [Marathon Capital Advises Middle River Power on Sale of California Solar Project](https://www.prnewswire.com/news-releases/marathon-capital-advises-middle-river-power-on-sale-of-california-solar-project-301115968.html) — prnewswire.com · tier other
- [Source](https://files.cleanpoweralliance.org/uploads/2021/02/High-5-Solar-PUBLIC.pdf) — files.cleanpoweralliance.org · tier other
- [High Desert Solar Project](https://ceqanet.lci.ca.gov/2019059120/2) — ceqanet.lci.ca.gov · tier regulatory
- [Marathon Capital](https://marathoncapital.com/news-events/marathon-capital-advises-middle-river-power-on-sale-of-california-solar-project) — marathoncapital.com · tier other
- [Middle River Power | Leading the Energy Transition](https://middleriverpower.com/) — middleriverpower.com · tier other
- [Power plant profile: High Desert Solar Project, US](https://www.power-technology.com/data-insights/power-plant-profile-high-desert-solar-project-us/) — power-technology.com · tier other
- [Ingeteam supplies inverters for 350 MW of solar projects - pv magazine USA](https://pv-magazine-usa.com/2021/09/07/ingeteam-supplies-inverters-for-350-mw-of-solar-projects/) — pv-magazine-usa.com · tier other
- [Goldman Sachs buys 150 MW High Desert Solar Project in San B... | Energy Finance & Investment](https://ippjournal.com/update/goldman-sachs-buys-150-mw-high-desert-solar-project-in-san-bernardino-county) — ippjournal.com · tier other

## Data quality

- Operation dates differ by milestone: the PPA listed August 1, 2021 as the expected commercial-operation date, Clean Power Alliance reported solar service beginning August 19, 2021 and full operations on October 15, 2021, while the EIA record lists December 2021 as the first-operation date for both units. The contemporaneous sale announcement identifies Middle River Power as seller and Goldman Sachs Renewable Power as buyer. The EIA 860 record lists the 100 MW PV and 50 MW battery units as operating, with no completed uprate or derate and no planned units; no separate expansion or repowering milestone is reflected in the operating record. The 50 MW battery rating is nameplate power and should not be treated as a separately verified MWh duration.

---