Kelly Creek Wind Project is an operating 184 MW onshore wind facility in Ford and Kankakee counties, Illinois. It consists of 92 Vestas V100-2.0 wind turbines, began commercial operation in December 2016, and sells electricity into the PJM wholesale market on a merchant basis. The project is located at 1456 E 3900N Rd, Cabery, IL 60919, at coordinates 40.9675, -88.1975, and connects to the transmission system at 138 kV.

## Metrics

- **Nameplate capacity:** 184 MW — Canonical EIA plant baseline.
- **Registry anchor:** Plant 60587 — plant-60587

## Facts

- **Technology:** Onshore Wind Turbine
- **Operator:** EDF Renewables

## Related parties

- **Asset manager:** Shiloh IV Lessee, LLC — FERC asset-appendix applicant
- **Equipment supplier:** Vestas — Turbine manufacturer ([source](https://www.vestas.com/en))
- **Balancing authority / market operator:** PJM Interconnection, LLC — Balancing authority and wholesale market ([source](https://www.pjm.com/))
- **Former owner / developer:** Vision Energy, LLC — Predecessor developer

## Sources

- [mbrweb.ferc.gov](https://mbrweb.ferc.gov/SearchMBRAssetAppendix/AssetAppendixDetails?AssetAppendixId=5285) — mbrweb.ferc.gov · authoritative — Source retained for exact-record publication review.
- [casemine.com](https://www.casemine.com/judgement/us/67c7d3941ee4d73a47b633fc) — casemine.com · public_source — Source retained for exact-record publication review.
- [edf-re.com](https://www.edf-re.com/press-release/edf-renewable-energy-announces-commercial-operation-kelly-creek-wind-project/) — edf-re.com · public_source — Source retained for exact-record publication review.

---

Canonical page: https://askthegrid.com/assets/facilities/kelly-creek-wind-project
Website: [EDF Renewables](https://www.edf-re.com/)

Source: Ask the Grid — https://askthegrid.com/