# Morris Ridge Solar

NYISO asset profile · https://askthegrid.com/assets/facilities/morris-ridge-solar

Morris Ridge Solar Energy Center, LLC - Livingston County - NYISO

Morris Ridge Solar is a 177 MWac solar photovoltaic generating facility in the Town of Mount Morris, Livingston County, New York. The facility includes an 83 MW battery energy storage system with four hours of duration. The project interconnects to the NYSEG 230 kV transmission system through a point of interconnection governed by NYISO Service Agreement No. 2790.

## Metrics

- **Nameplate capacity:** 177 MW — Canonical EIA plant baseline.
- **Registry anchor:** Plant 68274 — plant-68274

## Facts

- **Technology:** Solar Photovoltaic
- **Operator:** Morris Ridge Solar Energy Center, LLC

## Related parties

- **Project company / owner / operator:** Morris Ridge Solar Energy Center, LLC — Project company, permit holder, owner, and interconnection customer
- **Developer / sponsor:** EDF Renewables North America — Developer and project sponsor ([source](https://www.edf-re.com/))
- **Balancing authority / market operator:** New York Independent System Operator, Inc. — Transmission provider and market operator ([source](https://www.nyiso.com/about-us))
- **Transmission owner / interconnecting utility:** New York State Electric & Gas Corporation — Connecting transmission owner and recipient of interconnection assets

## Sources

- [documents.dps.ny.gov](https://documents.dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId=%7B90652D8A-0000-CB96-A9EE-23C7B0B4FA22%7D&DocTitle=Executed%20Version_Morris%20Ridge%20Solar%20LGIA_88381783_51_REDACTED) — documents.dps.ny.gov · authoritative — Source retained for exact-record publication review.

---

Canonical page: https://askthegrid.com/assets/facilities/morris-ridge-solar

Source: Ask the Grid — https://askthegrid.com/