Nexus Data Center Hubbard is a multi-phase data center campus under construction near Hubbard in Hill County, Texas, and it is built to run on its own natural-gas power plant. The first phase reached a Final Investment Decision in August 2026. Press coverage describes 600 to 612 MW proposed, 500 MW aimed for later in 2026, and an eventual expansion of around 7,700 MW. The applicant says it will not be physically interconnected with a utility distribution system, so the load shows up as onsite generation rather than a grid request.

## Identity and location

- Operating status: under_construction
- Asset scope: campus
- Location: 880 State Highway 171, Hubbard, Hill County, TX
- Developer: Nexus Data Centers, LLC (campus)
- Owner: Nexus Data Centers Hubbard LLC (exact asset)
- Operator: Nexus Hubbard Power, LLC (campus)

## Power and grid context

- Reported unspecified: 600 MW · proposed · campus — Headline capacity in December 2025 press coverage; the basis is not stated
- Reported unspecified: 612 MW · proposed · campus — Campus capacity powered by natural gas turbines behind the meter; the basis is not stated
- Reported unspecified: 500 MW · target · campus — March 2026 report of capacity aimed for later that year
- Reported unspecified: About 7,700 MW · proposed · campus — Eventual expansion reported as around 7.7 GW
- Reported unspecified: 500–612 MW · reported · campus — Initial-phase range from a third-party case study
- Onsite generation: 612.93 MW · proposed · campus — Dedicated power supply: Original natural-gas engine registration, generation rather than IT load
- Onsite generation: 1,600 MW · reported · campus — Dedicated power supply: Press-reported capacity of the natural-gas power plant
- Onsite generation: Up to 7,200 MW · proposed · campus — Dedicated power supply: Environmental-organization reporting on the proposed plant
- Backup generation: 152.75 MW · proposed · campus — Dedicated power supply: Original emergency diesel proposal, 47 units
- ISO/RTO: ERCOT

## Development

- Buildings: 4

## Sources

- [Access Denied](https://www.businesswire.com/news/home/20260819787644/en/Eagle-Point-Leads-HoldCo-Financing-for-Nexus-AI-Data-Center-Campus-in-Texas)
- [Just a moment...](https://www.datacenterdynamics.com/en/news/600mw-natural-gas-powered-data-center-campus-proposed-in-hubbard-texas/)
- [Just a moment...](https://www.datacenterdynamics.com/en/news/google-to-provide-financial-backing-for-multi-billion-dollar-anthropic-data-center-in-texas-report/)
- [https://checkmarkpro.com/assets/Case-Study-Nexus-Data-Center-Campus-Hubbard-Texas.pdf](https://checkmarkpro.com/assets/Case-Study-Nexus-Data-Center-Campus-Hubbard-Texas.pdf)
- [https://records.tceq.texas.gov/cs/idcplg?IdcService=TCEQ_EXTERNAL_SEARCH_GET_FILE&Rendition=Web&dID=8922185](https://records.tceq.texas.gov/cs/idcplg?IdcService=TCEQ_EXTERNAL_SEARCH_GET_FILE&Rendition=Web&dID=8922185)
- [www.investing.com](https://www.investing.com/news/stock-market-news/banks-in-talks-to-lend-15-billion-for-anthropic-data-center-backed-by-google-wsj-reports-4825894)
- [EIP Oil & Gas Watch](https://oilandgaswatch.org/alert/88bfbf53-5f31-4709-850a-6c0a122b2b2d)
- [https://records.tceq.texas.gov/cs/idcplg?IdcService=TCEQ_EXTERNAL_SEARCH_GET_FILE&Rendition=Web&dID=8914934](https://records.tceq.texas.gov/cs/idcplg?IdcService=TCEQ_EXTERNAL_SEARCH_GET_FILE&Rendition=Web&dID=8914934)
- [TDLR TABS - Project Details](https://www.tdlr.texas.gov/TABS/Projects/TABS2026022673)
- [TDLR TABS - Project Details](https://www.tdlr.texas.gov/TABS/Projects/TABS2026023798)
- [Commissioners approve Hubbard data center reinvestment zone &#8211; The Lakelander](https://lakelander.com/2026/02/19/commissioners-approve-hubbard-data-center-reinvestment-zone/)
- [FAQ - Nexus Data Centers](https://nexus-datacenters.com/faq/)
- [https://ukozvhzgrcnkcatjqfoo.supabase.co/storage/v1/object/public/03-00-air-construction/2026.09.18_Nexus_Data_Center_Hubbard_183046_PSDTX1700_GHGPSDTX269_NAPD_29425378](https://ukozvhzgrcnkcatjqfoo.supabase.co/storage/v1/object/public/03-00-air-construction/2026.09.18_Nexus_Data_Center_Hubbard_183046_PSDTX1700_GHGPSDTX269_NAPD_29425378)
- [https://ukozvhzgrcnkcatjqfoo.supabase.co/storage/v1/object/public/03-00-air-construction/application_55a9525e](https://ukozvhzgrcnkcatjqfoo.supabase.co/storage/v1/object/public/03-00-air-construction/application_55a9525e)
- [www.prairielandsgcd.org](https://www.prairielandsgcd.org/wp-content/uploads/2026/02/OP-Hearing-Notice_02.17.26.pdf)
- [www.tceq.texas.gov](https://www.tceq.texas.gov/downloads/permitting/air/bilingual/pending-permit-notices/183046-pls-english.pdf)
- [www.tceq.texas.gov](https://www.tceq.texas.gov/downloads/permitting/air/bilingual/pending-permit-notices/183046-nori-english.pdf)

---

Canonical page: https://askthegrid.com/assets/facilities/nexus-data-center-hubbard--grid-load-3ad683b062de37e5
Profile generated: 2026-11-02T19:00:01.643886Z
Source: Ask the Grid — https://askthegrid.com/