# PointOne Remington Technology Park Data Center Campus

PJM data center · https://askthegrid.com/assets/facilities/pointone-remington-technology-park-data-center-campus--grid-load-7cfe5568d1ab90e7

Remington Technology Park is a six-building data center campus on 234 acres in Remington, Fauquier County, Virginia, sponsored by PointOne. The county originally approved it in 2018 and approved an on-site natural gas fuel cell yard in July 2026, when PointOne announced construction was commencing. The company designs the campus for up to 304 MW of critical IT, with expansion toward 600 MW, and a county staff presentation put potential total demand at 600 MW. Dominion Energy has changed its power delivery phases for the site.

## Identity and location

- Operating status: under_construction
- Asset scope: campus
- Location: 12280 Lucky Hill Road, Remington, Fauquier County, VA
- Developer: PointOne, LLC (exact asset)
- Owner: Remington Technology Park Limited Partnership (exact asset)

## Power and grid context

- Critical it load: Up to 304 MW · proposed · exact asset — Current company campus design
- Reported it power: Up to 600 MW · proposed · exact asset — Future expansion capability, described by the company as utility IT
- Campus gross power: Up to 600 MW · proposed · exact asset — Potential total project energy demand in the county staff presentation
- Critical it load: 40 MW · proposed · exact asset — Building 1, Phase 1
- Critical it load: 72 MW · proposed · exact asset — Building 2, Phase 1
- Critical it load: 48 MW · proposed · exact asset — Each of Buildings 3 through 6, Phase 2; not a combined total
- Utility service: Up to 300 MW · proposed · exact asset — Designed on-site substation scalability
- Utility service: 300 MW · proposed · exact asset — Potential second substation noted in the county staff presentation
- Reported unspecified: 50 MW · target · exact asset — Power availability target stated in a February 2025 company announcement
- ISO/RTO: PJM
- Electric utility: Dominion Energy Inc
- Substation: Designed on-site substation with future scalability up to 300 MW; Dominion Energy anticipated to build the Helm Substation to deliver power to the site

## Development

- Buildings: 6

## Compute and operations

- Critical IT load: 304 MW

## Sources

- [PointOne Data Centers](https://www.pointonecorp.com/news/pointone-receives-approval-for-remington-technology-park-fuel-cell-equipment-yard)
- [PointOne Data Center Locations](https://www.pointonecorp.com/locations)
- [https://ukozvhzgrcnkcatjqfoo.supabase.co/storage/v1/object/public/03-00-air-construction/74172_Application_(2025-12-23)_67dee6af](https://ukozvhzgrcnkcatjqfoo.supabase.co/storage/v1/object/public/03-00-air-construction/74172_Application_(2025-12-23)_67dee6af)
- [Remington Technology Park® | PointOne Data Centers](https://www.linkedin.com/posts/pointone-data-centers_remington-technology-park-activity-7010689350724198400-pbJa)
- [PointOne Data Centers](https://www.pointonecorp.com/news/pointone-announces-plan-to-use-fuel-cell-technology-at-remington-technology-park-campus)
- [https://deq.zh-cn.virginia.gov/home/showpublisheddocument/25932/638633798982670000](https://deq.zh-cn.virginia.gov/home/showpublisheddocument/25932/638633798982670000)
- [Fauquier Board of Supervisors approves private power plant f...](https://www.fauquiernow.com/news/article_5991291e-ba38-4d44-9aef-acdabd1d3608-1d342886)
- [PointOne Data Centers Enters into a Strategic Partnership to Support the Execution of it’s Data Center Platform Across Virginia - iMiller Public Relations](https://www.imillerpr.com/news/pointone-data-centers-enters-into-a-strategic-partnership-to-support-the-execution-of-its-data-center-platform-across-virginia/)
- [https://apps.deq.virginia.gov/arcgis/rest/services/public/EDMA/MapServer/294/query?where=PLA_REG_NUM%3D74172&outFields=*&outSR=4326&f=pjson](https://apps.deq.virginia.gov/arcgis/rest/services/public/EDMA/MapServer/294/query?where=PLA_REG_NUM%3D74172&outFields=*&outSR=4326&f=pjson)

---

Canonical page: https://askthegrid.com/assets/facilities/pointone-remington-technology-park-data-center-campus--grid-load-7cfe5568d1ab90e7
Profile generated: 2026-11-02T23:14:20.224969Z
Source: Ask the Grid — https://askthegrid.com/