Rowan Project Stampede is the second phase of Rowan Digital Infrastructure's data center development in east Temple, Texas: two buildings on about 270 acres in Synergy Park. Rowan states in an October 2026 filing that the project is under construction. It has an ERCOT large-load interconnection request through Oncor, tracked as Batch Zero BZ-117, and Rowan has filed a complaint with the Public Utility Commission of Texas over its queue treatment. Capacity is reported at 300 MW, a figure whose basis is not stated.

## Identity and location

- Operating status: under_construction
- Asset scope: campus
- Location: 3151 Tower Road, Temple, Bell County, TX
- Developer: Rowan Digital Infrastructure (exact asset)

## Power and grid context

- Reported unspecified: 300 MW · reported · exact asset — Reported campus size; electrical versus IT basis not stated
- ISO/RTO: ERCOT
- Electric utility: Oncor Electric Delivery
- Point of interconnection: Oncor Electric Delivery Company is the interconnecting transmission service provider
- Queue IDs: ERCOT Batch Zero BZ-117

## Development

- Buildings: 2

## Sources

- [https://interchange.puc.texas.gov/Documents/60396_1_1692761.PDF](https://interchange.puc.texas.gov/Documents/60396_1_1692761.PDF)
- [What's Happening in Energy - June 19](https://halcyon.io/blog/whatshappeninginenergy/june19)
- [Projects &mdash; Rowan in Temple](https://www.rowantemple.com/projects)
- [www.ercot.com](https://www.ercot.com/files/docs/2026/10/14/60396-Complaint-of-Rowan-Stampede-LLC-Against-ERCOT.pdf)
- [www.templetx.gov](https://www.templetx.gov/Utility_Services_Agreement_(Stampede)__City_091626_CLEAN_with_Exhibits.pdf?t=202609222016220)
- [https://records.tceq.texas.gov/cs/idcplg?IdcService=TCEQ_EXTERNAL_SEARCH_GET_FILE&Rendition=Web&dID=9996075&searchType=External](https://records.tceq.texas.gov/cs/idcplg?IdcService=TCEQ_EXTERNAL_SEARCH_GET_FILE&Rendition=Web&dID=9996075&searchType=External)
- [www.templetx.gov](https://www.templetx.gov/City%20Attorney/Data%20Center%20Development/2026-0016.pdf?t=202609101219390)
- [Temple City Council opens 2026 with safety, seniors, sites | News | kdhnews.com](https://kdhnews.com/news/region/temple-city-council-opens-2026-with-safety-seniors-sites/article_54e4a396-29d4-527f-9eb6-e5c6c7583374.html)
- [https://services.arcgis.com/xOi1kZaI0eWDREZv/ArcGIS/rest/services/Address_Points_from_National_Address_Database_view/FeatureServer/0/query?f=json&where=Add_Number%3D3151&geometry=-97.353622%2C31.035192%2C-97.293622%2C31.095192&geometryType=esriGeometryEnvelope&inSR=4326&spatialRel=esriSpatialRelIntersects&outSR=4326&outFields=%2A&returnGeometry=true&resultRecordCount=2000](https://services.arcgis.com/xOi1kZaI0eWDREZv/ArcGIS/rest/services/Address_Points_from_National_Address_Database_view/FeatureServer/0/query?f=json&where=Add_Number%3D3151&geometry=-97.353622%2C31.035192%2C-97.293622%2C31.095192&geometryType=esriGeometryEnvelope&inSR=4326&spatialRel=esriSpatialRelIntersects&outSR=4326&outFields=%2A&returnGeometry=true&resultRecordCount=2000)
- [September 17 Council Recap](https://city-of-temple.prowly.com/471932-september-17-council-recap)
- [Welcome to the City of Temple, TX](https://www.templetx.gov/community/datacenterprojects.php)
- [https://interchange.puc.texas.gov/Documents/60396_9_1693514.PDF](https://interchange.puc.texas.gov/Documents/60396_9_1693514.PDF)

---

Canonical page: https://askthegrid.com/assets/facilities/rowan-project-stampede-data-center-campus--grid-load-57239d23eab49b7e
Profile generated: 2026-11-02T22:40:53.445086Z
Source: Ask the Grid — https://askthegrid.com/