# Vantage New Albany OH1 Building 3

PJM data center · https://askthegrid.com/assets/facilities/vantage-new-albany-oh1-building-3

Vantage New Albany OH1 Building 3 is the data-center project at 3205 Horizon Court. New Albany’s construction register lists 500,107 square feet and Turner Construction as contractor; its June 2025 report gives a March 2025 start. Vantage’s three-building OH1 plan specifies 64 MW of critical IT capacity per building, not current demand. The planned campus design combines diverse AEP Ohio feeds, closed-loop chilled-water cooling and carrier-neutral connectivity. This building profile keeps the campus’s 192 MW total and 70 acres separate from its own scope.

## Identity and location

- Operating status: unknown
- Asset scope: building
- Location: 3205 Horizon Court, New Albany, OH
- Operator: Vantage Data Centers (exact asset) — https://vantage-dc.com/data-center-locations/north-america/new-albany-ohio

## Power and grid context

- Critical it load: 64 MW · target · exact asset · Building 3 — Operator plan explicitly specifies64MW per building across three OH1 buildings. Not measured demand or proof of energization.
- Electric utility: AEP Ohio

## Development

- Site status: The building is part of the three-building OH1 development. The operator describes further campus phases through 2028 without assigning a verified opening date to this building.
- Gross floor area: 500,107 square feet
- Buildings: 1
- Construction: New Albany's June 2025 report records a March 2025 construction start. The city project register identifies Turner Construction as contractor.

## Compute and operations

- Facility classes: hyperscale

## Sources

- [https://newalbanyohio.org/community-development/project-updates/](https://newalbanyohio.org/community-development/project-updates/)
- [https://newalbanyohio.org/wp-content/uploads/2025/07/CD-2025-06.pdf](https://newalbanyohio.org/wp-content/uploads/2025/07/CD-2025-06.pdf)
- [https://vantage-dc.com/data-center-locations/north-america/new-albany-ohio](https://vantage-dc.com/data-center-locations/north-america/new-albany-ohio)

## Data quality

- Power values retain their reported, requested, contracted, energized, gross-campus, or critical-IT basis.

---