# Wildcat Point Generation Facility

PJM Natural Gas Fired Combined Cycle · https://askthegrid.com/assets/facilities/wildcat-point-generation-facility

Wildcat Point Generation Facility is a natural gas-fired power facility with 1,113.6 MW of EIA-reported nameplate capacity in Cecil County, Maryland, registered as EIA Plant ID 59220. Old Dominion Electric Coop is the registered plant entity or operator.

## Key facts

- Technology: Natural Gas Fired Combined Cycle
- Power capacity: 1113.6 MW
- Operating status: operating

## Grid and market context

- ISO/RTO: PJM
- Balancing authority: PJM Interconnection, LLC (PJM)

## Source-backed facts

- Owner logo domain: odec.com — Generation Facilities – Old Dominion Electric Cooperative · confidence: high
- Owner name: Old Dominion Electric Cooperative — Wildcat Point Generation Plant | Schnabel Engineering · confidence: high
- Description: Wildcat Point Generation Facility is an operating natural gas-fired combined-cycle plant in Cecil County, Maryland, with 1,113.6 MW of nameplate capacity. Its three generators are CT1 and CT2, each rated at 310.3 MW, and ST1, rated at 493 MW. Old Dominion Electric Cooperative built the facility and is its sole owner; the plant delivers power into PJM. — Generation Facilities – Old Dominion Electric Cooperative · confidence: medium
- Description: Wildcat Point Generation Facility is an operating natural gas-fired combined-cycle plant in Cecil County, Maryland, with 1,113.6 MW of nameplate capacity. Its three generators are CT1 and CT2, each rated at 310.3 MW, and ST1, rated at 493 MW. Old Dominion Electric Cooperative built the facility and is its sole owner; the plant delivers power into PJM. — Wildcat Point Generation Facility, Cecil County, Maryland, US · confidence: medium
- Parties: [{"relationship":"Owner, operator, and developer","name":"Old Dominion Electric Cooperative","official_url":"https://www.odec.com/"},{"relationship":"EPC joint venture","name":"White Oak Power Constructors","official_url":null},{"relationship":"EPC joint-venture partner; detailed design, engineered equipment procurement, commissioning, and executive management","name":"Sargent & Lundy","official_url":"https://www.sargentlundy.com/"},{"relationship":"EPC joint-venture partner","name":"PCL Industrial Construction Company","official_url":"https://www.pcl.com/us/en"},{"relationship":"Gas-turbine OEM and supplier","name":"Mitsubishi Power Systems Americas","official_url":"https://power.mhi.com/regions/amer"},{"relationship":"Steam-tail-package supplier, including HRSGs and steam turbine generator","name":"Alstom","official_url":"https://www.alstom.com/"},{"relationship":"Geotechnical engineering services","name":"Schnabel Engineering","official_url":"https://www.schnabel-eng.com/"},{"relationship":"Siting, development, permitting, and preliminary engineering services","name":"Burns & McDonnell","official_url":"https://www.burnsmcd.com/"}] — Source · confidence: medium
- Parties: [{"relationship":"Owner, operator, and developer","name":"Old Dominion Electric Cooperative","official_url":"https://www.odec.com/"},{"relationship":"EPC joint venture","name":"White Oak Power Constructors","official_url":null},{"relationship":"EPC joint-venture partner; detailed design, engineered equipment procurement, commissioning, and executive management","name":"Sargent & Lundy","official_url":"https://www.sargentlundy.com/"},{"relationship":"EPC joint-venture partner","name":"PCL Industrial Construction Company","official_url":"https://www.pcl.com/us/en"},{"relationship":"Gas-turbine OEM and supplier","name":"Mitsubishi Power Systems Americas","official_url":"https://power.mhi.com/regions/amer"},{"relationship":"Steam-tail-package supplier, including HRSGs and steam turbine generator","name":"Alstom","official_url":"https://www.alstom.com/"},{"relationship":"Geotechnical engineering services","name":"Schnabel Engineering","official_url":"https://www.schnabel-eng.com/"},{"relationship":"Siting, development, permitting, and preliminary engineering services","name":"Burns & McDonnell","official_url":"https://www.burnsmcd.com/"}] — Wildcat Point Generation Facility | Sargent & Lundy · confidence: medium
- Parties: [{"relationship":"Owner, operator, and developer","name":"Old Dominion Electric Cooperative","official_url":"https://www.odec.com/"},{"relationship":"EPC joint venture","name":"White Oak Power Constructors","official_url":null},{"relationship":"EPC joint-venture partner; detailed design, engineered equipment procurement, commissioning, and executive management","name":"Sargent & Lundy","official_url":"https://www.sargentlundy.com/"},{"relationship":"EPC joint-venture partner","name":"PCL Industrial Construction Company","official_url":"https://www.pcl.com/us/en"},{"relationship":"Gas-turbine OEM and supplier","name":"Mitsubishi Power Systems Americas","official_url":"https://power.mhi.com/regions/amer"},{"relationship":"Steam-tail-package supplier, including HRSGs and steam turbine generator","name":"Alstom","official_url":"https://www.alstom.com/"},{"relationship":"Geotechnical engineering services","name":"Schnabel Engineering","official_url":"https://www.schnabel-eng.com/"},{"relationship":"Siting, development, permitting, and preliminary engineering services","name":"Burns & McDonnell","official_url":"https://www.burnsmcd.com/"}] — Wildcat Point Generation Facility, Cecil County, Maryland, US · confidence: medium
- Parties: [{"relationship":"Owner, operator, and developer","name":"Old Dominion Electric Cooperative","official_url":"https://www.odec.com/"},{"relationship":"EPC joint venture","name":"White Oak Power Constructors","official_url":null},{"relationship":"EPC joint-venture partner; detailed design, engineered equipment procurement, commissioning, and executive management","name":"Sargent & Lundy","official_url":"https://www.sargentlundy.com/"},{"relationship":"EPC joint-venture partner","name":"PCL Industrial Construction Company","official_url":"https://www.pcl.com/us/en"},{"relationship":"Gas-turbine OEM and supplier","name":"Mitsubishi Power Systems Americas","official_url":"https://power.mhi.com/regions/amer"},{"relationship":"Steam-tail-package supplier, including HRSGs and steam turbine generator","name":"Alstom","official_url":"https://www.alstom.com/"},{"relationship":"Geotechnical engineering services","name":"Schnabel Engineering","official_url":"https://www.schnabel-eng.com/"},{"relationship":"Siting, development, permitting, and preliminary engineering services","name":"Burns & McDonnell","official_url":"https://www.burnsmcd.com/"}] — Wildcat Point Generation Plant | Schnabel Engineering · confidence: medium
- Identifiers.7: {"value":"WILDCAT POINT CC","system":"PJM RPM resource name"} — Sheet1 · confidence: high
- Identifiers.8: {"value":"EMAAC","system":"PJM RPM zone"} — Sheet1 · confidence: high
- Parties.0: {"relationship":"Owner, operator, and developer","name":"Old Dominion Electric Cooperative","official_url":"https://www.odec.com/"} — Source · confidence: high
- Parties.1: {"relationship":"EPC joint venture","name":"White Oak Power Constructors","official_url":null} — Wildcat Point Generation Facility | Sargent & Lundy · confidence: high
- Parties.2: {"relationship":"EPC joint-venture partner; detailed design, engineered equipment procurement, commissioning, and executive management","name":"Sargent & Lundy","official_url":"https://www.sargentlundy.com/"} — Wildcat Point Generation Facility | Sargent & Lundy · confidence: high
- Parties.3: {"relationship":"EPC joint-venture partner","name":"PCL Industrial Construction Company","official_url":"https://www.pcl.com/us/en"} — Wildcat Point Generation Facility | Sargent & Lundy · confidence: high
- Parties.4: {"relationship":"Gas-turbine OEM and supplier","name":"Mitsubishi Power Systems Americas","official_url":"https://power.mhi.com/regions/amer"} — Wildcat Point Generation Facility, Cecil County, Maryland, US · confidence: medium
- Parties.5: {"relationship":"Steam-tail-package supplier, including HRSGs and steam turbine generator","name":"Alstom","official_url":"https://www.alstom.com/"} — Wildcat Point Generation Facility, Cecil County, Maryland, US · confidence: high
- Parties.6: {"relationship":"Geotechnical engineering services","name":"Schnabel Engineering","official_url":"https://www.schnabel-eng.com/"} — Wildcat Point Generation Plant | Schnabel Engineering · confidence: high
- Parties.7: {"relationship":"Siting, development, permitting, and preliminary engineering services","name":"Burns & McDonnell","official_url":"https://www.burnsmcd.com/"} — Wildcat Point Generation Facility, Cecil County, Maryland, US · confidence: medium
- Construction scope: New approximately 1,000 MW natural-gas combined-cycle facility comprising two Mitsubishi M501GAC combustion-turbine generators, two Alstom heat-recovery steam generators with duct burners, one Alstom steam-turbine generator, one natural-gas-fired auxiliary boiler, one emergency generator, one fire-water pump, SMIT generator step-up transformers, and a 16-cell counterflow mechanical-draft cooling tower. The operating generator inventory is CT1 and CT2 at 310.3 MW each and ST1 at 493 MW. — Wildcat Point Generation Facility | Sargent & Lundy · confidence: medium
- Product url: https://power.mhi.com/regions/amer/products/gas-turbines/m501g — M501G Series Gas Turbines | Mitsubishi Power Americas · confidence: high
- Product url: https://power.mhi.com/regions/amer/products/gas-turbines/m501g — MHI to Supply Two M501GAC Gas Turbines to Old Dominion Electric Cooperative of the United States-- Long-term Service Agreement to Be Signed in Coming Days -- | Mitsubishi Heavy Industries · confidence: high
- Manufacturer domain: power.mhi.com — MHI to Supply Two M501GAC Gas Turbines to Old Dominion Electric Cooperative of the United States-- Long-term Service Agreement to Be Signed in Coming Days -- | Mitsubishi Heavy Industries · confidence: medium
- Equipment models: [{"manufacturer_domain":"power.mhi.com","product_url":"https://power.mhi.com/regions/amer/products/gas-turbines/m501g","count":2,"unit_mw":310.3,"name":"Mitsubishi M501GAC combustion-turbine generators"},{"manufacturer_domain":"alstom.com","product_url":"https://www.alstom.com/press-releases-news/2014/3/alstom-to-supply-steam-equipment-for-wildcat-point-combined-cycle-power-plant-in-maryland-","count":2,"unit_mw":null,"name":"Alstom heat-recovery steam generators"},{"manufacturer_domain":"alstom.com","product_url":"https://www.alstom.com/press-releases-news/2014/3/alstom-to-supply-steam-equipment-for-wildcat-point-combined-cycle-power-plant-in-maryland-","count":1,"unit_mw":493,"name":"Alstom steam-turbine generator"}] — Wildcat Point Generation Facility | Sargent & Lundy · confidence: medium
- Equipment models: [{"manufacturer_domain":"power.mhi.com","product_url":"https://power.mhi.com/regions/amer/products/gas-turbines/m501g","count":2,"unit_mw":310.3,"name":"Mitsubishi M501GAC combustion-turbine generators"},{"manufacturer_domain":"alstom.com","product_url":"https://www.alstom.com/press-releases-news/2014/3/alstom-to-supply-steam-equipment-for-wildcat-point-combined-cycle-power-plant-in-maryland-","count":2,"unit_mw":null,"name":"Alstom heat-recovery steam generators"},{"manufacturer_domain":"alstom.com","product_url":"https://www.alstom.com/press-releases-news/2014/3/alstom-to-supply-steam-equipment-for-wildcat-point-combined-cycle-power-plant-in-maryland-","count":1,"unit_mw":493,"name":"Alstom steam-turbine generator"}] — MHI to Supply Two M501GAC Gas Turbines to Old Dominion Electric Cooperative of the United States-- Long-term Service Agreement to Be Signed in Coming Days -- | Mitsubishi Heavy Industries · confidence: medium
- Equipment models: [{"manufacturer_domain":"power.mhi.com","product_url":"https://power.mhi.com/regions/amer/products/gas-turbines/m501g","count":2,"unit_mw":310.3,"name":"Mitsubishi M501GAC combustion-turbine generators"},{"manufacturer_domain":"alstom.com","product_url":"https://www.alstom.com/press-releases-news/2014/3/alstom-to-supply-steam-equipment-for-wildcat-point-combined-cycle-power-plant-in-maryland-","count":2,"unit_mw":null,"name":"Alstom heat-recovery steam generators"},{"manufacturer_domain":"alstom.com","product_url":"https://www.alstom.com/press-releases-news/2014/3/alstom-to-supply-steam-equipment-for-wildcat-point-combined-cycle-power-plant-in-maryland-","count":1,"unit_mw":493,"name":"Alstom steam-turbine generator"}] — Alstom to supply equipment for Wildcat Point combined-cycle power plant in Maryland | Alstom · confidence: medium
- Product family: M501GAC — MHI to Supply Two M501GAC Gas Turbines to Old Dominion Electric Cooperative of the United States-- Long-term Service Agreement to Be Signed in Coming Days -- | Mitsubishi Heavy Industries · confidence: high
- Product family: M501GAC — M501G/GAC Series | Mitsubishi Power · confidence: high
- Manufacturer name: Mitsubishi Heavy Industries (MHI) — MHI to Supply Two M501GAC Gas Turbines to Old Dominion Electric Cooperative of the United States-- Long-term Service Agreement to Be Signed in Coming Days -- | Mitsubishi Heavy Industries · confidence: medium
- Manufacturer name: Mitsubishi Heavy Industries (MHI) — Wildcat Point Generation Facility | Sargent & Lundy · confidence: medium
- Equipment models.0: {"manufacturer_domain":"power.mhi.com","product_url":"https://power.mhi.com/regions/amer/products/gas-turbines/m501g","count":2,"unit_mw":310.3,"name":"Mitsubishi M501GAC combustion-turbine generators"} — MHI to Supply Two M501GAC Gas Turbines to Old Dominion Electric Cooperative of the United States-- Long-term Service Agreement to Be Signed in Coming Days -- | Mitsubishi Heavy Industries · confidence: medium
- Equipment models.1: {"manufacturer_domain":"alstom.com","product_url":"https://www.alstom.com/press-releases-news/2014/3/alstom-to-supply-steam-equipment-for-wildcat-point-combined-cycle-power-plant-in-maryland-","count":2,"unit_mw":null,"name":"Alstom heat-recovery steam generators"} — Alstom to supply equipment for Wildcat Point combined-cycle power plant in Maryland | Alstom · confidence: high
- Equipment models.1: {"manufacturer_domain":"alstom.com","product_url":"https://www.alstom.com/press-releases-news/2014/3/alstom-to-supply-steam-equipment-for-wildcat-point-combined-cycle-power-plant-in-maryland-","count":2,"unit_mw":null,"name":"Alstom heat-recovery steam generators"} — Wildcat Point Generation Facility | Sargent & Lundy · confidence: high
- Equipment models.2: {"manufacturer_domain":"alstom.com","product_url":"https://www.alstom.com/press-releases-news/2014/3/alstom-to-supply-steam-equipment-for-wildcat-point-combined-cycle-power-plant-in-maryland-","count":1,"unit_mw":493,"name":"Alstom steam-turbine generator"} — Alstom to supply equipment for Wildcat Point combined-cycle power plant in Maryland | Alstom · confidence: medium
- Description: Wildcat Point is an operating natural-gas-fired combined-cycle facility in Cecil County, Maryland, with EIA generator nameplate capacity totaling 1,113.6 MW across two combustion-turbine generators and one steam-turbine generator. The plant uses a 2×1 configuration with two Mitsubishi combustion turbines, two heat-recovery steam generators, and one steam turbine generator. ODEC developed, built, owns, and operates the facility; Maryland’s environmental review identified ODEC as the project’s sole developer and owner. Construction began with a 2014-10-14 groundbreaking, followed by commercial operation in April 2018. — Wildcat Point Generation Facility, Cecil County, Maryland, US · confidence: medium
- Description: Wildcat Point is an operating natural-gas-fired combined-cycle facility in Cecil County, Maryland, with EIA generator nameplate capacity totaling 1,113.6 MW across two combustion-turbine generators and one steam-turbine generator. The plant uses a 2×1 configuration with two Mitsubishi combustion turbines, two heat-recovery steam generators, and one steam turbine generator. ODEC developed, built, owns, and operates the facility; Maryland’s environmental review identified ODEC as the project’s sole developer and owner. Construction began with a 2014-10-14 groundbreaking, followed by commercial operation in April 2018. — cik0000885568-10k_20181231.htm · confidence: medium
- Quality notes: ["Reported project-cost figures are not sale consideration: the preliminary $675 million estimate excluded startup and financing costs, while another project source describes an $800 million plant.","Capacity figures use different conventions: EIA generator nameplate capacity totals 1,113.6 MW, ODEC cites 980 MW, and ODEC’s 2018 filing reports a 940 MW net capacity entitlement.","The 2018-09-14 transaction identified in ODEC’s filing was the sale of ODEC’s interest in the adjacent Rock Springs facility and related assets, not a sale of Wildcat Point.","No post-commercial-operation expansion, repowering, or retirement milestone is reported for Wildcat Point through 2026-08-02; the plant remains listed as operating."] — ODEC ready to buy turbines for Maryland power plant - Virginia Business · confidence: medium
- Quality notes: ["Reported project-cost figures are not sale consideration: the preliminary $675 million estimate excluded startup and financing costs, while another project source describes an $800 million plant.","Capacity figures use different conventions: EIA generator nameplate capacity totals 1,113.6 MW, ODEC cites 980 MW, and ODEC’s 2018 filing reports a 940 MW net capacity entitlement.","The 2018-09-14 transaction identified in ODEC’s filing was the sale of ODEC’s interest in the adjacent Rock Springs facility and related assets, not a sale of Wildcat Point.","No post-commercial-operation expansion, repowering, or retirement milestone is reported for Wildcat Point through 2026-08-02; the plant remains listed as operating."] — Wildcat Point Generation Plant · confidence: medium
- Quality notes: ["Reported project-cost figures are not sale consideration: the preliminary $675 million estimate excluded startup and financing costs, while another project source describes an $800 million plant.","Capacity figures use different conventions: EIA generator nameplate capacity totals 1,113.6 MW, ODEC cites 980 MW, and ODEC’s 2018 filing reports a 940 MW net capacity entitlement.","The 2018-09-14 transaction identified in ODEC’s filing was the sale of ODEC’s interest in the adjacent Rock Springs facility and related assets, not a sale of Wildcat Point.","No post-commercial-operation expansion, repowering, or retirement milestone is reported for Wildcat Point through 2026-08-02; the plant remains listed as operating."] — Source · confidence: medium
- Financing summary: No dedicated project-finance facility or Wildcat Point sale consideration is identified. Public records describe a preliminary $675 million project cost excluding startup and financing costs and an $800 million project description. Fitch reported that borrowings related to Wildcat Point construction increased ODEC’s debt to approximately $1.3 billion in 2017 from $835 million in 2014; ODEC’s 2018 filing separately reports a $250 million 2017 long-term-debt issuance and a 2017 credit agreement involving Wells Fargo Bank as administrative agent and swingline lender, without allocating the issuance to Wildcat Point specifically. The 2018 filing also reports $53.2 million of liquidated damages offsetting capitalized Wildcat Point construction costs. — ODEC ready to buy turbines for Maryland power plant - Virginia Business · confidence: medium
- Financing summary: No dedicated project-finance facility or Wildcat Point sale consideration is identified. Public records describe a preliminary $675 million project cost excluding startup and financing costs and an $800 million project description. Fitch reported that borrowings related to Wildcat Point construction increased ODEC’s debt to approximately $1.3 billion in 2017 from $835 million in 2014; ODEC’s 2018 filing separately reports a $250 million 2017 long-term-debt issuance and a 2017 credit agreement involving Wells Fargo Bank as administrative agent and swingline lender, without allocating the issuance to Wildcat Point specifically. The 2018 filing also reports $53.2 million of liquidated damages offsetting capitalized Wildcat Point construction costs. — Fitch Affirms Old Dominion Electric Coop at 'A+' · confidence: medium
- Financing summary: No dedicated project-finance facility or Wildcat Point sale consideration is identified. Public records describe a preliminary $675 million project cost excluding startup and financing costs and an $800 million project description. Fitch reported that borrowings related to Wildcat Point construction increased ODEC’s debt to approximately $1.3 billion in 2017 from $835 million in 2014; ODEC’s 2018 filing separately reports a $250 million 2017 long-term-debt issuance and a 2017 credit agreement involving Wells Fargo Bank as administrative agent and swingline lender, without allocating the issuance to Wildcat Point specifically. The 2018 filing also reports $53.2 million of liquidated damages offsetting capitalized Wildcat Point construction costs. — Source · confidence: medium
- Timeline: [{"event":"Project proposed and regulatory approval","date":"2014-04-08","detail":"The Maryland Public Service Commission order for the proposed Wildcat Point project became final; the environmental review described ODEC as the sole developer and owner."},{"event":"EPC contract awarded","date":"2014-06","detail":"ODEC awarded the engineering, procurement, and construction project to White Oak Power Constructors, a joint venture of Sargent & Lundy and PCL Industrial Construction Company."},{"event":"Construction groundbreaking","date":"2014-10-14","detail":"The $675 million Wildcat Point construction project held its groundbreaking ceremony."},{"event":"Construction-related financing","date":"2017","detail":"Fitch reported that borrowings related to Wildcat Point construction pushed ODEC’s debt to approximately $1.3 billion in 2017 from $835 million in 2014. ODEC’s 2018 filing also reports a $250 million long-term-debt issuance in 2017, without identifying it as a dedicated Wildcat Point financing."},{"event":"Construction progress","date":"2017-01","detail":"Engineering and procurement were reported complete, with the facility then scheduled for completion in June 2017; the original mid-2017 operating schedule was subsequently delayed."},{"event":"Commercial operation","date":"2018-04-17","detail":"Wildcat Point achieved commercial operation and became available for dispatch by PJM."},{"event":"Separate adjacent-asset sale","date":"2018-09-14","detail":"ODEC sold its interest in Rock Springs and related assets to EPRS. The filing identifies this as a Rock Springs transaction separate from Wildcat Point, which it reported as 100% ODEC-owned."},{"event":"Operating status","date":"2026-08-02","detail":"The EIA-derived plant record lists Wildcat Point’s three generators as operating, with generation recorded through May 2026; no post-commercial-operation expansion, repowering, or retirement milestone is reported."}] — Source · confidence: medium
- Timeline: [{"event":"Project proposed and regulatory approval","date":"2014-04-08","detail":"The Maryland Public Service Commission order for the proposed Wildcat Point project became final; the environmental review described ODEC as the sole developer and owner."},{"event":"EPC contract awarded","date":"2014-06","detail":"ODEC awarded the engineering, procurement, and construction project to White Oak Power Constructors, a joint venture of Sargent & Lundy and PCL Industrial Construction Company."},{"event":"Construction groundbreaking","date":"2014-10-14","detail":"The $675 million Wildcat Point construction project held its groundbreaking ceremony."},{"event":"Construction-related financing","date":"2017","detail":"Fitch reported that borrowings related to Wildcat Point construction pushed ODEC’s debt to approximately $1.3 billion in 2017 from $835 million in 2014. ODEC’s 2018 filing also reports a $250 million long-term-debt issuance in 2017, without identifying it as a dedicated Wildcat Point financing."},{"event":"Construction progress","date":"2017-01","detail":"Engineering and procurement were reported complete, with the facility then scheduled for completion in June 2017; the original mid-2017 operating schedule was subsequently delayed."},{"event":"Commercial operation","date":"2018-04-17","detail":"Wildcat Point achieved commercial operation and became available for dispatch by PJM."},{"event":"Separate adjacent-asset sale","date":"2018-09-14","detail":"ODEC sold its interest in Rock Springs and related assets to EPRS. The filing identifies this as a Rock Springs transaction separate from Wildcat Point, which it reported as 100% ODEC-owned."},{"event":"Operating status","date":"2026-08-02","detail":"The EIA-derived plant record lists Wildcat Point’s three generators as operating, with generation recorded through May 2026; no post-commercial-operation expansion, repowering, or retirement milestone is reported."}] — Wildcat Point Generation Facility | Sargent & Lundy · confidence: medium
- Timeline: [{"event":"Project proposed and regulatory approval","date":"2014-04-08","detail":"The Maryland Public Service Commission order for the proposed Wildcat Point project became final; the environmental review described ODEC as the sole developer and owner."},{"event":"EPC contract awarded","date":"2014-06","detail":"ODEC awarded the engineering, procurement, and construction project to White Oak Power Constructors, a joint venture of Sargent & Lundy and PCL Industrial Construction Company."},{"event":"Construction groundbreaking","date":"2014-10-14","detail":"The $675 million Wildcat Point construction project held its groundbreaking ceremony."},{"event":"Construction-related financing","date":"2017","detail":"Fitch reported that borrowings related to Wildcat Point construction pushed ODEC’s debt to approximately $1.3 billion in 2017 from $835 million in 2014. ODEC’s 2018 filing also reports a $250 million long-term-debt issuance in 2017, without identifying it as a dedicated Wildcat Point financing."},{"event":"Construction progress","date":"2017-01","detail":"Engineering and procurement were reported complete, with the facility then scheduled for completion in June 2017; the original mid-2017 operating schedule was subsequently delayed."},{"event":"Commercial operation","date":"2018-04-17","detail":"Wildcat Point achieved commercial operation and became available for dispatch by PJM."},{"event":"Separate adjacent-asset sale","date":"2018-09-14","detail":"ODEC sold its interest in Rock Springs and related assets to EPRS. The filing identifies this as a Rock Springs transaction separate from Wildcat Point, which it reported as 100% ODEC-owned."},{"event":"Operating status","date":"2026-08-02","detail":"The EIA-derived plant record lists Wildcat Point’s three generators as operating, with generation recorded through May 2026; no post-commercial-operation expansion, repowering, or retirement milestone is reported."}] — Source · confidence: medium
- Timeline: [{"event":"Project proposed and regulatory approval","date":"2014-04-08","detail":"The Maryland Public Service Commission order for the proposed Wildcat Point project became final; the environmental review described ODEC as the sole developer and owner."},{"event":"EPC contract awarded","date":"2014-06","detail":"ODEC awarded the engineering, procurement, and construction project to White Oak Power Constructors, a joint venture of Sargent & Lundy and PCL Industrial Construction Company."},{"event":"Construction groundbreaking","date":"2014-10-14","detail":"The $675 million Wildcat Point construction project held its groundbreaking ceremony."},{"event":"Construction-related financing","date":"2017","detail":"Fitch reported that borrowings related to Wildcat Point construction pushed ODEC’s debt to approximately $1.3 billion in 2017 from $835 million in 2014. ODEC’s 2018 filing also reports a $250 million long-term-debt issuance in 2017, without identifying it as a dedicated Wildcat Point financing."},{"event":"Construction progress","date":"2017-01","detail":"Engineering and procurement were reported complete, with the facility then scheduled for completion in June 2017; the original mid-2017 operating schedule was subsequently delayed."},{"event":"Commercial operation","date":"2018-04-17","detail":"Wildcat Point achieved commercial operation and became available for dispatch by PJM."},{"event":"Separate adjacent-asset sale","date":"2018-09-14","detail":"ODEC sold its interest in Rock Springs and related assets to EPRS. The filing identifies this as a Rock Springs transaction separate from Wildcat Point, which it reported as 100% ODEC-owned."},{"event":"Operating status","date":"2026-08-02","detail":"The EIA-derived plant record lists Wildcat Point’s three generators as operating, with generation recorded through May 2026; no post-commercial-operation expansion, repowering, or retirement milestone is reported."}] — Fitch Affirms Old Dominion Electric Coop at 'A+' · confidence: medium
- Timeline: [{"event":"Project proposed and regulatory approval","date":"2014-04-08","detail":"The Maryland Public Service Commission order for the proposed Wildcat Point project became final; the environmental review described ODEC as the sole developer and owner."},{"event":"EPC contract awarded","date":"2014-06","detail":"ODEC awarded the engineering, procurement, and construction project to White Oak Power Constructors, a joint venture of Sargent & Lundy and PCL Industrial Construction Company."},{"event":"Construction groundbreaking","date":"2014-10-14","detail":"The $675 million Wildcat Point construction project held its groundbreaking ceremony."},{"event":"Construction-related financing","date":"2017","detail":"Fitch reported that borrowings related to Wildcat Point construction pushed ODEC’s debt to approximately $1.3 billion in 2017 from $835 million in 2014. ODEC’s 2018 filing also reports a $250 million long-term-debt issuance in 2017, without identifying it as a dedicated Wildcat Point financing."},{"event":"Construction progress","date":"2017-01","detail":"Engineering and procurement were reported complete, with the facility then scheduled for completion in June 2017; the original mid-2017 operating schedule was subsequently delayed."},{"event":"Commercial operation","date":"2018-04-17","detail":"Wildcat Point achieved commercial operation and became available for dispatch by PJM."},{"event":"Separate adjacent-asset sale","date":"2018-09-14","detail":"ODEC sold its interest in Rock Springs and related assets to EPRS. The filing identifies this as a Rock Springs transaction separate from Wildcat Point, which it reported as 100% ODEC-owned."},{"event":"Operating status","date":"2026-08-02","detail":"The EIA-derived plant record lists Wildcat Point’s three generators as operating, with generation recorded through May 2026; no post-commercial-operation expansion, repowering, or retirement milestone is reported."}] — Wildcat Point on schedule for early summer completion · confidence: medium
- Timeline: [{"event":"Project proposed and regulatory approval","date":"2014-04-08","detail":"The Maryland Public Service Commission order for the proposed Wildcat Point project became final; the environmental review described ODEC as the sole developer and owner."},{"event":"EPC contract awarded","date":"2014-06","detail":"ODEC awarded the engineering, procurement, and construction project to White Oak Power Constructors, a joint venture of Sargent & Lundy and PCL Industrial Construction Company."},{"event":"Construction groundbreaking","date":"2014-10-14","detail":"The $675 million Wildcat Point construction project held its groundbreaking ceremony."},{"event":"Construction-related financing","date":"2017","detail":"Fitch reported that borrowings related to Wildcat Point construction pushed ODEC’s debt to approximately $1.3 billion in 2017 from $835 million in 2014. ODEC’s 2018 filing also reports a $250 million long-term-debt issuance in 2017, without identifying it as a dedicated Wildcat Point financing."},{"event":"Construction progress","date":"2017-01","detail":"Engineering and procurement were reported complete, with the facility then scheduled for completion in June 2017; the original mid-2017 operating schedule was subsequently delayed."},{"event":"Commercial operation","date":"2018-04-17","detail":"Wildcat Point achieved commercial operation and became available for dispatch by PJM."},{"event":"Separate adjacent-asset sale","date":"2018-09-14","detail":"ODEC sold its interest in Rock Springs and related assets to EPRS. The filing identifies this as a Rock Springs transaction separate from Wildcat Point, which it reported as 100% ODEC-owned."},{"event":"Operating status","date":"2026-08-02","detail":"The EIA-derived plant record lists Wildcat Point’s three generators as operating, with generation recorded through May 2026; no post-commercial-operation expansion, repowering, or retirement milestone is reported."}] — cik0000885568-10k_20181231.htm · confidence: medium
- Commercial parties: [{"relationship":"Owner, operator, and developer","name":"Old Dominion Electric Cooperative","detail":"ODEC developed and built Wildcat Point and is identified as its sole owner; the facility is part of ODEC’s generation portfolio.","official_url":"https://www.odec.com/"},{"relationship":"EPC joint venture","name":"White Oak Power Constructors","detail":"White Oak Power Constructors was awarded the Wildcat Point engineering, procurement, and construction project in June 2014 as a joint venture of Sargent & Lundy and PCL Industrial Construction Company.","official_url":null},{"relationship":"EPC joint-venture partner; detailed design, equipment procurement, commissioning, and executive management","name":"Sargent & Lundy","detail":"Sargent & Lundy provided detailed design, engineered equipment procurement, commissioning, and executive management for the EPC joint venture.","official_url":"https://www.sargentlundy.com/"},{"relationship":"EPC joint-venture partner","name":"PCL Industrial Construction Company","detail":"PCL Industrial Construction Company was the construction partner in White Oak Power Constructors with Sargent & Lundy.","official_url":"https://www.pcl.com/"},{"relationship":"Gas-turbine and generator supplier","name":"Mitsubishi Power Systems Americas","detail":"Mitsubishi Power Systems Americas supplied two natural-gas-fired M501GAC combustion turbines and associated electric generators and also contracted for turbine maintenance.","official_url":"https://power.mhi.com/regions/amer/"},{"relationship":"Steam-tail-package supplier","name":"Alstom","detail":"Alstom supplied the steam-tail package, including two heat-recovery steam generators and one steam turbine generator; the reported contract value was $100 million.","official_url":"https://www.alstom.com/"},{"relationship":"Geotechnical engineering services","name":"Schnabel Engineering","detail":"Schnabel Engineering performed geotechnical investigation, construction observation, materials testing, and related services for ODEC’s Wildcat Point project.","official_url":"https://www.schnabel-eng.com/"},{"relationship":"Natural-gas transporter and pipeline supplier","name":"Transco, a Williams company","detail":"Transco supplied natural gas to Wildcat Point through an approximately 11-mile pipeline associated with the Rock Springs expansion project.","official_url":"https://www.williams.com/transco/"},{"relationship":"Administrative agent and swingline lender under ODEC credit agreement","name":"Wells Fargo Bank, National Association","detail":"ODEC’s 2018 filing identifies Wells Fargo Bank as administrative agent and swingline lender under ODEC’s March 2017 credit agreement.","official_url":"https://www.wellsfargo.com/"}] — Wildcat Point Generation Facility | Sargent & Lundy · confidence: medium
- Commercial parties: [{"relationship":"Owner, operator, and developer","name":"Old Dominion Electric Cooperative","detail":"ODEC developed and built Wildcat Point and is identified as its sole owner; the facility is part of ODEC’s generation portfolio.","official_url":"https://www.odec.com/"},{"relationship":"EPC joint venture","name":"White Oak Power Constructors","detail":"White Oak Power Constructors was awarded the Wildcat Point engineering, procurement, and construction project in June 2014 as a joint venture of Sargent & Lundy and PCL Industrial Construction Company.","official_url":null},{"relationship":"EPC joint-venture partner; detailed design, equipment procurement, commissioning, and executive management","name":"Sargent & Lundy","detail":"Sargent & Lundy provided detailed design, engineered equipment procurement, commissioning, and executive management for the EPC joint venture.","official_url":"https://www.sargentlundy.com/"},{"relationship":"EPC joint-venture partner","name":"PCL Industrial Construction Company","detail":"PCL Industrial Construction Company was the construction partner in White Oak Power Constructors with Sargent & Lundy.","official_url":"https://www.pcl.com/"},{"relationship":"Gas-turbine and generator supplier","name":"Mitsubishi Power Systems Americas","detail":"Mitsubishi Power Systems Americas supplied two natural-gas-fired M501GAC combustion turbines and associated electric generators and also contracted for turbine maintenance.","official_url":"https://power.mhi.com/regions/amer/"},{"relationship":"Steam-tail-package supplier","name":"Alstom","detail":"Alstom supplied the steam-tail package, including two heat-recovery steam generators and one steam turbine generator; the reported contract value was $100 million.","official_url":"https://www.alstom.com/"},{"relationship":"Geotechnical engineering services","name":"Schnabel Engineering","detail":"Schnabel Engineering performed geotechnical investigation, construction observation, materials testing, and related services for ODEC’s Wildcat Point project.","official_url":"https://www.schnabel-eng.com/"},{"relationship":"Natural-gas transporter and pipeline supplier","name":"Transco, a Williams company","detail":"Transco supplied natural gas to Wildcat Point through an approximately 11-mile pipeline associated with the Rock Springs expansion project.","official_url":"https://www.williams.com/transco/"},{"relationship":"Administrative agent and swingline lender under ODEC credit agreement","name":"Wells Fargo Bank, National Association","detail":"ODEC’s 2018 filing identifies Wells Fargo Bank as administrative agent and swingline lender under ODEC’s March 2017 credit agreement.","official_url":"https://www.wellsfargo.com/"}] — Wildcat Point Generation Facility, Cecil County, Maryland, US · confidence: medium
- Commercial parties: [{"relationship":"Owner, operator, and developer","name":"Old Dominion Electric Cooperative","detail":"ODEC developed and built Wildcat Point and is identified as its sole owner; the facility is part of ODEC’s generation portfolio.","official_url":"https://www.odec.com/"},{"relationship":"EPC joint venture","name":"White Oak Power Constructors","detail":"White Oak Power Constructors was awarded the Wildcat Point engineering, procurement, and construction project in June 2014 as a joint venture of Sargent & Lundy and PCL Industrial Construction Company.","official_url":null},{"relationship":"EPC joint-venture partner; detailed design, equipment procurement, commissioning, and executive management","name":"Sargent & Lundy","detail":"Sargent & Lundy provided detailed design, engineered equipment procurement, commissioning, and executive management for the EPC joint venture.","official_url":"https://www.sargentlundy.com/"},{"relationship":"EPC joint-venture partner","name":"PCL Industrial Construction Company","detail":"PCL Industrial Construction Company was the construction partner in White Oak Power Constructors with Sargent & Lundy.","official_url":"https://www.pcl.com/"},{"relationship":"Gas-turbine and generator supplier","name":"Mitsubishi Power Systems Americas","detail":"Mitsubishi Power Systems Americas supplied two natural-gas-fired M501GAC combustion turbines and associated electric generators and also contracted for turbine maintenance.","official_url":"https://power.mhi.com/regions/amer/"},{"relationship":"Steam-tail-package supplier","name":"Alstom","detail":"Alstom supplied the steam-tail package, including two heat-recovery steam generators and one steam turbine generator; the reported contract value was $100 million.","official_url":"https://www.alstom.com/"},{"relationship":"Geotechnical engineering services","name":"Schnabel Engineering","detail":"Schnabel Engineering performed geotechnical investigation, construction observation, materials testing, and related services for ODEC’s Wildcat Point project.","official_url":"https://www.schnabel-eng.com/"},{"relationship":"Natural-gas transporter and pipeline supplier","name":"Transco, a Williams company","detail":"Transco supplied natural gas to Wildcat Point through an approximately 11-mile pipeline associated with the Rock Springs expansion project.","official_url":"https://www.williams.com/transco/"},{"relationship":"Administrative agent and swingline lender under ODEC credit agreement","name":"Wells Fargo Bank, National Association","detail":"ODEC’s 2018 filing identifies Wells Fargo Bank as administrative agent and swingline lender under ODEC’s March 2017 credit agreement.","official_url":"https://www.wellsfargo.com/"}] — Wildcat Point Generation Plant | Schnabel Engineering · confidence: medium
- Timeline.0: {"event":"Project proposed and regulatory approval","date":"2014-04-08","detail":"The Maryland Public Service Commission order for the proposed Wildcat Point project became final; the environmental review described ODEC as the sole developer and owner."} — Source · confidence: high
- Timeline.1: {"event":"EPC contract awarded","date":"2014-06","detail":"ODEC awarded the engineering, procurement, and construction project to White Oak Power Constructors, a joint venture of Sargent & Lundy and PCL Industrial Construction Company."} — Wildcat Point Generation Facility | Sargent & Lundy · confidence: high
- Timeline.2: {"event":"Construction groundbreaking","date":"2014-10-14","detail":"The $675 million Wildcat Point construction project held its groundbreaking ceremony."} — Source · confidence: medium
- Timeline.3: {"event":"Construction-related financing","date":"2017","detail":"Fitch reported that borrowings related to Wildcat Point construction pushed ODEC’s debt to approximately $1.3 billion in 2017 from $835 million in 2014. ODEC’s 2018 filing also reports a $250 million long-term-debt issuance in 2017, without identifying it as a dedicated Wildcat Point financing."} — Fitch Affirms Old Dominion Electric Coop at 'A+' · confidence: medium
- Timeline.3: {"event":"Construction-related financing","date":"2017","detail":"Fitch reported that borrowings related to Wildcat Point construction pushed ODEC’s debt to approximately $1.3 billion in 2017 from $835 million in 2014. ODEC’s 2018 filing also reports a $250 million long-term-debt issuance in 2017, without identifying it as a dedicated Wildcat Point financing."} — Source · confidence: medium
- Timeline.4: {"event":"Construction progress","date":"2017-01","detail":"Engineering and procurement were reported complete, with the facility then scheduled for completion in June 2017; the original mid-2017 operating schedule was subsequently delayed."} — Wildcat Point on schedule for early summer completion · confidence: high
- Timeline.5: {"event":"Commercial operation","date":"2018-04-17","detail":"Wildcat Point achieved commercial operation and became available for dispatch by PJM."} — cik0000885568-10k_20181231.htm · confidence: high
- Timeline.6: {"event":"Separate adjacent-asset sale","date":"2018-09-14","detail":"ODEC sold its interest in Rock Springs and related assets to EPRS. The filing identifies this as a Rock Springs transaction separate from Wildcat Point, which it reported as 100% ODEC-owned."} — Source · confidence: high
- Commercial parties.1: {"relationship":"EPC joint venture","name":"White Oak Power Constructors","detail":"White Oak Power Constructors was awarded the Wildcat Point engineering, procurement, and construction project in June 2014 as a joint venture of Sargent & Lundy and PCL Industrial Construction Company.","official_url":null} — Wildcat Point Generation Facility | Sargent & Lundy · confidence: high

## Timeline

- 2014-04-08 — Project proposed and regulatory approval
  The Maryland Public Service Commission order for the proposed Wildcat Point project became final; the environmental review described ODEC as the sole developer and owner.
  Source: Source (https://msa.maryland.gov/megafile/msa/speccol/sc5300/sc5339/000113/021000/021531/unrestricted/20151697e.pdf)
- 2014-06 — EPC contract awarded
  ODEC awarded the engineering, procurement, and construction project to White Oak Power Constructors, a joint venture of Sargent & Lundy and PCL Industrial Construction Company.
  Source: Wildcat Point Generation Facility | Sargent & Lundy (https://www.sargentlundy.com/projects/wildcat-combined-cycle-project/)

## Sources

- [Generation Facilities – Old Dominion Electric Cooperative](https://www.odec.com/generation-transmission/generation-facilities/) — odec.com · tier other
- [Sheet1](https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/2025-2026/2025-2026-rpm-existing-resource-list-post.xlsx) — pjm.com · tier other
- [Source](https://msa.maryland.gov/megafile/msa/speccol/sc5300/sc5339/000113/021000/021531/unrestricted/20151697e.pdf) — msa.maryland.gov · tier regulatory
- [Wildcat Point Generation Plant | Schnabel Engineering](https://www.schnabel-eng.com/projects/wildcat-point-generation-plant/) — schnabel-eng.com · tier other
- [Wildcat Point Generation Facility, Cecil County, Maryland, US](https://www.power-technology.com/projects/wildcat-point-generation-facility-cecil-county-maryland/) — power-technology.com · tier other
- [Wildcat Point Generation Facility | Sargent & Lundy](https://www.sargentlundy.com/projects/wildcat-combined-cycle-project/) — sargentlundy.com · tier other
- [M501G Series Gas Turbines | Mitsubishi Power Americas](https://power.mhi.com/regions/amer/products/gas-turbines/m501g) — power.mhi.com · tier other
- [MHI to Supply Two M501GAC Gas Turbines to Old Dominion Electric Cooperative of the United States-- Long-term Service Agreement to Be Signed in Coming Days -- | Mitsubishi Heavy Industries](https://www.mhi.com/news/1308021702.html) — mhi.com · tier other
- [Alstom to supply equipment for Wildcat Point combined-cycle power plant in Maryland | Alstom](https://www.alstom.com/press-releases-news/2014/3/alstom-to-supply-steam-equipment-for-wildcat-point-combined-cycle-power-plant-in-maryland-) — alstom.com · tier other
- [M501G/GAC Series | Mitsubishi Power](https://power.mhi.com/products/gasturbines/lineup/m501g) — power.mhi.com · tier other
- [Source](https://www.sec.gov/Archives/edgar/data/885568/000156459019006434/cik0000885568-10k_20181231.htm) — sec.gov · tier regulatory
- [ODEC ready to buy turbines for Maryland power plant - Virginia Business](https://www.virginiabusiness.com/article/odec-ready-to-buy-turbines-for-maryland-power-plant/) — virginiabusiness.com · tier other
- [Fitch Affirms Old Dominion Electric Coop at 'A+'](https://www.fitchratings.com/research/us-public-finance/fitch-affirms-old-dominion-electric-coop-at-a-outlook-stable-02-11-2022) — fitchratings.com · tier other
- [Source](https://power-technology.com/projects/wildcat-point-generation-facility-cecil-county-maryland) — power-technology.com · tier other
- [Wildcat Point on schedule for early summer completion](https://www.cecildaily.com/news/local_news/wildcat-point-on-schedule-for-early-summer-completion/article_789df8c7-fa1f-53b7-a081-da4c28d87db5.html) — cecildaily.com · tier other
- [History – Old Dominion Electric Cooperative](https://www.odec.com/our-cooperative/history/) — odec.com · tier other
- [Public Comment on Maryland's Climate Pathway Report](https://mde.maryland.gov/programs/air/ClimateChange/2031%20GHG%20REDUCTION%20PLAN%20STAKEHOLDER%20LETTERS/Old%20Dominion%20Elecretic%20Cooperative%20Comments.pdf) — mde.maryland.gov · tier regulatory
- [Source](https://power-technology.com/data-insights/power-plant-profile-wildcat-point-generation-facility-us) — power-technology.com · tier other

## Data quality

- Reported project-cost figures are not sale consideration: the preliminary $675 million estimate excluded startup and financing costs, while another project source describes an $800 million plant. Capacity figures use different conventions: EIA generator nameplate capacity totals 1,113.6 MW, ODEC cites 980 MW, and ODEC’s 2018 filing reports a 940 MW net capacity entitlement. The September 14, 2018 transaction identified in ODEC’s filing was the sale of ODEC’s interest in the adjacent Rock Springs facility and related assets, not a sale of Wildcat Point. No post-commercial-operation expansion, repowering, or retirement milestone is reported for Wildcat Point through August 2, 2026; the plant remains listed as operating.

---