# Ball Hill Wind Energy, LLC

NYISO wind_power_plant · https://askthegrid.com/nyiso/assets/plant/ball-hill-wind-energy-llc

Ball Hill Wind is a 108 MW onshore wind facility located in the Towns of Villenova and Hanover, Chautauqua County, New York. The project consists of 25 Vestas wind turbines (22 V150 4.2 MW units on 150-meter towers and 3 V136 3.45 MW units on 82-meter towers), an interconnection switchyard and substation, an Operations and Management Building, two meteorological towers, underground collection lines, and approximately 13 miles of gravel access roads on leased private property. The project is interconnected to the New York Independent System Operator grid through National Grid's Stebbins Road Station at 230 kV.

## Key facts

- Technology: Onshore Wind Turbine
- Power capacity: 107.5 MW

## Grid and market context

- ISO/RTO: NYISO
- Balancing authority: NYISO

## Source-backed facts

- Asset.location.county: Chautauqua — northlandpower.com · confidence: review_required
- Asset.location.state: New York — northlandpower.com · confidence: review_required
- Asset.location.towns: Villenova and Hanover — documents.dps.ny.gov · confidence: review_required
- Asset.technology: Onshore wind turbine — northlandpower.com · confidence: review_required
- Asset.capacity mw: 108 MW — northlandpower.com · confidence: review_required
- Asset.capacity mw regulatory: 107.5 MW — documents.dps.ny.gov · confidence: review_required
- Asset.site acres: 9715 acres — acoustical-consultants.com · confidence: review_required
- Asset.commercial operation date: October 2023 — northlandpower.com · confidence: review_required
- Asset.turbine count: 25 — documents.dps.ny.gov · confidence: review_required
- Asset.ppa counterparty: NYSERDA — northlandpower.com · confidence: review_required
- Asset.ppa duration years: 20 years — northlandpower.com · confidence: review_required

## Timeline

- 2016-12-20 — Siting exemption granted
  The New York Siting Board ruled that the Ball Hill Wind Project was exempt from the requirement to obtain a Certificate of Environmental Compatibility and Public Need (CECPN).
  Source: documents.dps.ny.gov (https://documents.dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId=%7B6623EDE1-3CDF-4B38-BF7F-16FBB9CD98B8%7D)
- 2019-04-18 — Certificate of Public Convenience and Necessity granted
  The New York Public Service Commission granted Ball Hill Wind Energy, LLC a Certificate of Public Convenience and Necessity (CPCN) and provided lightened regulatory status under PSL § 68.
  Source: documents.dps.ny.gov (https://documents.dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId=%7B6623EDE1-3CDF-4B38-BF7F-16FBB9CD98B8%7D)
- 2020-08-17 — Ownership transfer approved by regulators
  The New York Public Service Commission issued its Declaratory Ruling on Review of Transfer Transaction, finding that the proposed transfer of upstream ownership interests in Ball Hill Wind from RES America Developments, Inc. to Northland required no further review under PSL § 70.
  Source: documents.dps.ny.gov (https://documents.dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId=%7B6623EDE1-3CDF-4B38-BF7F-16FBB9CD98B8%7D)
- 2021-06 — Turbine Supply Agreement signed
  Ball Hill selected Vestas as the turbine manufacturer and signed the Turbine Supply Agreement in June 2021 for 25 wind turbines.
  Source: documents.dps.ny.gov (https://documents.dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId=%7BD5FB2155-058C-4904-A8DD-68C4D6973281%7D)
- 2021-07-23 — Financing authorization petition filed
  Joint Petition of Bluestone Wind, LLC and Ball Hill Wind Energy, LLC for an Order Approving Financing Pursuant to Section 69 of the New York Public Service Law. Sought authorization for up to $381,177,543.80 of indebtedness and authority to guarantee or pledge up to $400 million in debt for construction and operations.
  Source: documents.dps.ny.gov (https://documents.dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId=%7B6623EDE1-3CDF-4B38-BF7F-16FBB9CD98B8%7D)
- 2023-03-10 — Interconnection agreement (Second Amendment)
  Ball Hill Wind Energy, LLC, NYISO, and Niagara Mohawk Power Corporation d/b/a National Grid entered into Service Agreement No. 2473, the Second Amended and Restated Large Generator Interconnection Agreement, effective March 10, 2023.
  Source: nyisoviewer.etariff.biz (https://nyisoviewer.etariff.biz/ViewerDocLibrary/Filing/Filing5027/5027FilingSections/FID5027%20NMPC%20NYISO%20Ball%20Hill%20Wind%20LGIA%20Clean_33452.pdf)
- 2023-10 — Commercial operation / Project energized
  The Ball Hill Wind Project commenced commercial operation and began generating revenue under its 20-year NYSERDA PPA/REC arrangement. NYISO records initially showed September 2023 COD, later updated to October 2023.
  Source: northlandpower.com (https://northlandpower.com/sites/ball-hill/)

## Sources

- [acoustical-consultants.com](https://acoustical-consultants.com/casestudy/ball-hill-wind-turbine-farm-noise-validation-testing-new-york/) — acoustical-consultants.com · tier public_source
- [documents.dps.ny.gov](https://documents.dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId=%7B6623EDE1-3CDF-4B38-BF7F-16FBB9CD98B8%7D) — documents.dps.ny.gov · tier authoritative
- [documents.dps.ny.gov](https://documents.dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId=%7B7015FB8D-0000-CA1A-A394-15CA12AA8F00%7D) — documents.dps.ny.gov · tier authoritative
- [documents.dps.ny.gov](https://documents.dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId=%7BAFD962A9-5CAE-427E-BEA3-49044C61966C%7D) — documents.dps.ny.gov · tier authoritative
- [documents.dps.ny.gov](https://documents.dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId=%7BD5FB2155-058C-4904-A8DD-68C4D6973281%7D) — documents.dps.ny.gov · tier authoritative
- [documents.dps.ny.gov](https://documents.dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId=%7BF0C26D8C-0000-CA19-B8DE-BFE6332CC415%7D) — documents.dps.ny.gov · tier authoritative
- [northlandpower.com](https://northlandpower.com/northland-power-secures-final-tax-equity-funding-on-u-s-based-bluestone-and-ball-hill-wind-farms/) — northlandpower.com · tier public_source
- [northlandpower.com](https://northlandpower.com/sites/ball-hill/) — northlandpower.com · tier public_source
- [nyisoviewer.etariff.biz](https://nyisoviewer.etariff.biz/ViewerDocLibrary/Filing/Filing5027/5027FilingSections/FID5027%20NMPC%20NYISO%20Ball%20Hill%20Wind%20LGIA%20Clean_33452.pdf) — nyisoviewer.etariff.biz · tier public_source

## Data quality

- The project's regulatory capacity is reported as 107.5 MW in New York Public Service Commission filings. Northland Power's operating-asset page reports 108 MW. These are normal differences in how capacity is reported by different entities and contexts (nameplate, gross, interconnection limit, and CRIS). The July 2021 financing petition sought authority for up to $381,177,543.80 of indebtedness payable over more than 12 months and authority to guarantee or pledge up to $400 million in debt. These amounts covered both the Bluestone (112 MW) and Ball Hill (108 MW) projects jointly. The announced figure was not allocated between the two projects, so a Ball Hill-only amount cannot be stated. The ownership transfer in 2020 was from RES America Developments Inc. to Northland at the upstream-ownership level (membership interests in Ball Hill Wind Energy, LLC). No separate Ball Hill-only sale consideration, purchase price, or transaction value was disclosed in the reviewed regulatory filings.

---

Canonical page: https://askthegrid.com/nyiso/assets/plant/ball-hill-wind-energy-llc