# Castleton Energy Center

NYISO power_plant · https://askthegrid.com/nyiso/assets/plant/castleton-energy-center

Castleton Energy Center is a 72 MW natural-gas-fired combined-cycle power plant located at 1902 River Road, Castleton-on-Hudson, Rensselaer County, New York. The plant comprises one GE Frame 6B natural-gas-fired combustion turbine generator coupled with a Deltak heat-recovery steam generator and supplementary duct burner, followed by a steam turbine in a combined-cycle configuration, plus an auxiliary natural-gas boiler.

## Key facts

- Technology: Natural Gas Fired Combined Cycle
- Power capacity: 72 MW

## Grid and market context

- ISO/RTO: NYISO
- Balancing authority: NYISO

## Source-backed facts

- Technical.power mw: 72 MW — nyiso.com · confidence: review_required
- Operations.market resource ids: 23900 — nyiso.com · confidence: review_required
- Operations.settlement point: Castleton, NYISO Zone F — nyiso.com · confidence: review_required
- Technical.unit count: 1 — extapps.dec.ny.gov · confidence: review_required
- Identity.owner name: Castleton Power LLC — documents.dps.ny.gov · confidence: review_required

## Timeline

- 1999 — Acquisition by TransCanada
  TransCanada Power (Castleton) LLC purchased the facility from Cogen Energy Technology L.P.
  Source: documents.dps.ny.gov (https://documents.dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId=%7B77911EF3-2054-47E1-9D01-291EBD23F5C7%7D)
- 2002 — Conversion to exempt wholesale generator
  The facility ceased operating as a qualified cogeneration facility. FERC determined TransCanada Power (Castleton) LLC to be an exempt wholesale generator (docket 01-89-000), establishing it as a non-utility generator selling at market-based rates into NYISO.
  Source: documents.dps.ny.gov (https://documents.dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId=%7B77911EF3-2054-47E1-9D01-291EBD23F5C7%7D)
- 2006 — Transfer to EPCOR-affiliated ownership
  Upstream transfer: TransCanada Power, L.P. transferred 100% of the ownership interests in TransCanada Power (Castleton) LLC to two Alberta corporations indirectly owned by EPCOR Utilities, Inc. The facility entity was renamed EPCOR Power (Castleton) LLC.
  Source: documents.dps.ny.gov (https://documents.dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId=%7B77911EF3-2054-47E1-9D01-291EBD23F5C7%7D)
- 2009 — Transfer from EPCOR to Castleton Energy Center LLC
  New York PSC approved the transfer of EPCOR Power (Castleton) LLC to Castleton Energy Center LLC (a Wayzata Investment Partners portfolio company). The facility entity was renamed Castleton Power.
  Source: documents.dps.ny.gov (https://documents.dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId=%7B77911EF3-2054-47E1-9D01-291EBD23F5C7%7D)
- 2016-07-14 — New York PSC approval of Fortistar ownership transfer
  New York Public Service Commission (Case 16-E-0244) approved the transfer of ownership interests in Castleton Power and Castleton Energy Services LLC to Fortistar Castleton LLC, a Fortistar subsidiary. Lightened regulation status continued.
  Source: documents.dps.ny.gov (https://documents.dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId=%7B77911EF3-2054-47E1-9D01-291EBD23F5C7%7D)
- 2016-07-20 — Fortistar acquisition of Castleton Power closed
  Fortistar announced that it had closed on its purchase of Castleton Power LLC from Castleton Energy Center LLC. The 72 MW GE Frame 6 combined-cycle plant dispatches into NYISO Zone F.
  Source: powermag.com (https://www.powermag.com/press-releases/fortistar-acquires-castleton-power-plant-in-new-york/)
- 2018-01-12 — Joint financing petition for up to $200 million
  Castleton Power LLC and Lockport Energy Associates, L.P. petitioned the New York PSC for approval to incur up to $200 million of joint and several indebtedness, guarantees, and pledges of ownership interests.
  Source: documents.dps.ny.gov (https://documents.dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId=%7B3BC32365-88FB-45E8-8BF0-EFAD8F91035E%7D)
- 2018-04-19 — New York PSC approval of financing and internal restructuring
  New York PSC (Case 18-E-0023) approved joint financing authority of up to $200 million aggregate for Castleton Power and Lockport Energy Associates, including indebtedness, guarantees, and pledges of ownership interests and jurisdictional assets. Approved intra-corporate restructuring did not change ultimate ownership of the facilities.
  Source: documents.dps.ny.gov (https://documents.dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId=%7B3BC32365-88FB-45E8-8BF0-EFAD8F91035E%7D)

## Sources

- [documents.dps.ny.gov](https://documents.dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId=%7B3BC32365-88FB-45E8-8BF0-EFAD8F91035E%7D) — documents.dps.ny.gov · tier authoritative
- [documents.dps.ny.gov](https://documents.dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId=%7B77911EF3-2054-47E1-9D01-291EBD23F5C7%7D) — documents.dps.ny.gov · tier authoritative
- [documents.dps.ny.gov](https://documents.dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId=%7BB00B2B89-0000-C817-B64E-ACE9DC8847C4%7D) — documents.dps.ny.gov · tier authoritative
- [extapps.dec.ny.gov](https://extapps.dec.ny.gov/data/dar/afs/permits/prr_438440000800006_r1.pdf) — extapps.dec.ny.gov · tier authoritative
- [ippjournal.com](https://ippjournal.com/news/fortistar-signs-purchase-agreement-for-castleton-power-plant-in-new-york) — ippjournal.com · tier public_source
- [gevernova.com](https://www.gevernova.com/gas-power/products/gas-turbines/6b) — gevernova.com · tier public_source
- [nyiso.com](https://www.nyiso.com/documents/20142/2226333/2023-Gold-Book-Public.pdf) — nyiso.com · tier authoritative
- [powermag.com](https://www.powermag.com/press-releases/fortistar-acquires-castleton-power-plant-in-new-york/) — powermag.com · tier public_source

## Data quality

- The exact plant is distinguished by EIA plant ID 10190, the 1902 River Road address, 72 MW capacity, GE Frame 6 technology, generator code CCCC, and NYISO Zone F. These identifiers separate it from other Castleton-named or nearby facilities. The 2016 transaction was an acquisition of Castleton Power LLC and related ownership interests, not a disclosed project-finance amount. Public transaction coverage and deal-flow reporting do not state a purchase price; the deal-flow record marks the value as undisclosed. The 2018 New York PSC financing approval authorized aggregate indebtedness of up to $200 million for Castleton Power and Lockport Energy Associates jointly. It should not be treated as a Castleton-only project-financing amount. Available plant data continued to identify it as operating. The facility ceased qualified-cogeneration operation in 2002 and became an exempt wholesale generator; it is classified as IPP non-CHP in current EIA and regulatory records. Equipment detail (GE turbine model PG6541B, Deltak HRSG, COEN duct burner, Johnston boiler) is sourced from official NYSDEC permit and EPA technical support documents. Ownership chain is fully documented through regulatory PSC orders and transaction announcements: Cogen Energy Technology (1992–1999) → TransCanada Power (1999–2006) → EPCOR (2006–2009) → Castleton Energy Center/Wayzata (2009–2016) → Fortistar (2016–present). Fortistar Castleton LLC is the acquisition subsidiary through which Fortistar LLC acquired Castleton Power LLC on 2016-07-20. It is a separate legal entity created for the transaction and documented in New York PSC filings.
- Open question: [object Object]
- Open question: [object Object]

---

Canonical page: https://askthegrid.com/nyiso/assets/plant/castleton-energy-center

Source: Ask the Grid — https://askthegrid.com/