# Stony Creek Wind Farm NY

NYISO wind_power_plant · https://askthegrid.com/nyiso/assets/plant/stony-creek-wind-farm-ny

Stony Creek Wind Farm NY is a 94.4 MW onshore wind facility located in the Town of Orangeville, Wyoming County, New York. The facility has operated since November 2013 and consists of 58 General Electric wind turbines (17 rated at 1.62 MW and 41 rated at 1.69 MW).

## Key facts

- Technology: Onshore Wind Turbine
- Power capacity: 94.4 MW

## Grid and market context

- ISO/RTO: NYISO
- Balancing authority: NYISO

## Source-backed facts

- Location.town: Town of Orangeville — nyisoviewer.etariff.biz · confidence: review_required
- Regulatory.ferc market based rate docket: ER11-3872-000 — federalregister.gov · confidence: review_required

## Timeline

- 2007-10-12 — Interconnection request filed
  Stony Creek Wind Farm LLC submitted an interconnection request for the proposed large generating facility.
  Source: documents.dps.ny.gov (https://documents.dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId=%7BC2FC1EE1-65E7-4BAF-BCC2-CAF1B5C8BA7B%7D)
- 2013-07-01 — Construction financing closed
  Invenergy Wind LLC announced the closing of construction financing for the Orangeville Wind Farm (Stony Creek) project. The financing consisted of a construction loan and letter of credit. Rabobank acted as mandated lead arranger, administrative agent, and collateral agent; Union Bank S.A. acted as syndication agent and joint lead arranger. The facility was described as a 94 MW project with 58 GE 1.6-100 turbines. Construction contractors were Tetra Tech Construction, O'Connell Electric Company, and Henkels & McCoy.
  Source: yumpu.com (https://www.yumpu.com/en/document/view/23463514/invenergy-closes-financing-for-orangeville-wind-invenergy-llc)

## Sources

- [documents.dps.ny.gov](https://documents.dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId=%7BC2FC1EE1-65E7-4BAF-BCC2-CAF1B5C8BA7B%7D) — documents.dps.ny.gov · tier authoritative
- [nyisoviewer.etariff.biz](https://nyisoviewer.etariff.biz/ViewerDocLibrary/temp/924c1f88-340e-424c-86d2-4da4354abb56.pdf) — nyisoviewer.etariff.biz · tier public_source
- [federalregister.gov](https://www.federalregister.gov/documents/2011/07/07/2011-17000/stony-creek-energy-llc-supplemental-notice-that-initial-market-based-rate-filing-includes-request) — federalregister.gov · tier authoritative
- [ge.com](https://www.ge.com/news/press-releases/ge-launches-16-100-secures-more-half-gigawatt-commitments-worlds-most-efficient-wind) — ge.com · tier public_source
- [yumpu.com](https://www.yumpu.com/en/document/view/23463514/invenergy-closes-financing-for-orangeville-wind-invenergy-llc) — yumpu.com · tier public_source

## Data quality

- The exact asset is identified by EIA plant ID 58088, its Wyoming County location in Orangeville, 94.4 MW operating nameplate capacity, 58-turbine configuration, and November 2013 operation date. A conflict exists between the EIA operating nameplate capacity (94.4 MW) and the NYISO interconnection agreement facility rating (96.83 MW derived from 17 × 1.62 MW + 41 × 1.69 MW). Both values are retained; the 94.4 MW is the EIA-documented plant rating and the 96.83 MW is the interconnection facility rating. The NYISO interconnection agreement explicitly specifies 17 GE 1.62 MW turbines and 41 GE 1.69 MW turbines. The EIA plant record lists GE as the predominant turbine manufacturer and GE 1.6-100 as the predominant model; both designations are consistent with the 1.62/1.69 MW variants. The project was initially proposed at up to 59 turbines in regulatory decommissioning plans, while the completed and operating configuration is 58 turbines. This was an upstream ownership change, not an outright sale of the facility. Stony Creek continued to own its assets and facilities. The available operating record shows generation data through December 2024. No expansion, repowering, or retirement event for this exact plant (EIA 58088) was identified. The development name 'Orangeville Wind' was used before the project was distinguished from an unrelated Pennsylvania wind farm also named Stony Creek. The facility is listed as 100% Invenergy-controlled as of January 30, 2026 New York PSC report; that report excludes passive tax-equity investments from listed percentages.

---

Canonical page: https://askthegrid.com/nyiso/assets/plant/stony-creek-wind-farm-ny

Source: Ask the Grid — https://askthegrid.com/