Mariah del Norte is a 230.4 MW wind facility in Parmer County, Texas. EIA's May 2026 inventory lists one operating aggregate generator under Plant ID 59005, with service beginning in November 2016 and BHE Renewables as the registered operator. BHE's current project page reports 230 MW, 96 turbines and 25,024 acres. BHE's page labels 2022 as its 'year operational,' which conflicts with the 2016 EIA service record and is not used as the commissioning date here.
Overview
Key fields
- Operating capacity
- 230.4 MW
EIA May 2026
- Company project rating
- 230 MW
BHE Renewables
- Turbines
- 96
BHE Renewables
- Site area
- 25,024 acres
BHE Renewables
- Project cost
- Approx. $350M
First Reserve 2016
- Settlement point
- MARIAH_ALL
ERCOT settlement point.
- Registry anchor
- Plant 59005
BHE Renewables
Resource stack
- 2 resources
MARIAH_NORTE1 · MARIAH_NORTE2
Profile
- Grid role
- Utility-scale wind generation in ERCOT.
- Operating record
- 230.4 MW EIA nameplate · November 2016 service.
- Equipment and land
- 96 turbines · 25,024 acres.
Structured profile
- Operating capacity
- 230.4 MW
EIA
- Equipment
- 96 wind turbines
BHE Renewables
- Site area
- 25,024 acres
BHE Renewables
Units and generators
Operating generator records and technology attributes reported through EIA-860.
| Generator | Capacity | Technology | Operation | Status |
|---|---|---|---|---|
| MAR1 | 230.4 MW 230.4 MW summer | Onshore Wind Turbine Wind · WT | Nov 2016 | Operating |
Performance
Monthly EIA generation history and recent market-resource behavior where linked telemetry is available.
Peer context
- Technology capacity
- 230.4 MW
- National rank
- #177
- TX rank
- #60
Monthly generation
Download CSVMonthly generation is reported through EIA-923. Capacity factor uses the current EIA nameplate capacity and is shown only for complete calendar years.
ERCOT disclosed dispatch
2 ERCOT market resources · Wind
Generation
3 mo through May 22, 2026Capacity factor is average output vs. this plant's observed peak.
Output by hourlocal time · 90 days through May 22, 2026
Latest disclosed outputhourly · 2 weeks ending May 22, 2026
Generation from ERCOT's 60-Day SCED Disclosure (≈60-day lag), summed over this site's market resources.
Grid and market context
Deterministic links to ERCOT market resources, price records, outage disclosures, queue records, and nearby infrastructure. Candidate joins remain labeled until corroborated.
Market registration
ERCOT public disclosuresOperating context
ERCOT market recordsNearby substations
HIFLD infrastructure inventoryRelated parties and identifiers
Parties, market resources, and identifiers tied to this asset, with owner, operator, developer, EPC, compliance provider, and interconnecting entity roles kept separate.
Parties and identifiers
| Relationship | Entity | Basis |
|---|---|---|
| Portfolio tax-equity investor | Financing covers a portfolio that includes Mariah del Norte. | |
| Portfolio tax-equity investor | Financing covers a portfolio that includes Mariah del Norte. | |
| Portfolio tax-equity investor | Financing covers a portfolio that includes Mariah del Norte. | |
| Market resources | MARIAH_NORTE1, MARIAH_NORTE2 | Linked ERCOT resources. |
| Grid selection | plant:plant-59005 | Canonical asset page /ercot/assets/plant/mariah-del-norte. |
Reporting portfolio
| Largest reported plants | Capacity | State |
|---|---|---|
| Grande Prairie Wind Farm | 400 MW | NE |
| Santa Rita Wind Energy | 300 MW | TX |
| Mariah del NorteCurrent | 230.4 MW | TX |
| Walnut Ridge Wind Farm | 212 MW | IL |
| Flat Top Wind I | 200 MW | TX |
| Alamo 6 | 105 MW | TX |
| Marshall Wind Farm | 73.8 MW | KS |
| Pearl Solar | 50 MW | TX |
Portfolio membership follows the latest EIA-860 reporting entity. It does not imply ultimate ownership.
View full reporting portfolioTimeline and sources
Project milestones and public references behind the asset profile.
Project timeline
- Project Entered ServiceEIA May 202...
EIA reports November 2016.
- Latest disclosed generation interval
ERCOT SCED disclosure is delayed, so plant performance windows end at the latest disclosed interval.
Sources
Related assets
Similar plants ranked by technology, capacity, and distance.
Bethel Wind Farm LLC
Wind · 276 MW
Castro County
TX Hereford Wind
Wind · 200 MW
Deaf Smith County
Canadian Breaks, LLC
Wind · 210.1 MW
Deaf Smith County
TX Jumbo Road Wind
Wind · 299.7 MW
Deaf Smith County