Mesquite Star
Clearway Energy Group · Fisher and Nolan counties · ERCOT
Mesquite Star is a 418.9 MW wind facility spanning Fisher and Nolan counties, Texas. EIA's May 2026 inventory reports one operating wind generator with a March 2020 registry date. Mesquite Star Special, LLC owns and operates the facility through a tax-equity structure managed within Clearway's investment platform.
Overview
Key fields
- Operating capacity
- 418.9 MW
EIA and project financials
- Named VPPA capacity
- 228 MW
Five disclosed contracts
- Tax equity investor
- MidAmerican
Project financials
- Registry anchor
- Plant 62587
Mesquite Star Special LLC
Profile
- Grid role
- Large utility-scale wind generation in ERCOT.
- Ownership structure
- Mesquite Star Special owns and operates the facility within a Clearway/HASI investment structure with MidAmerican tax equity.
- Contracted output
- Public financial statements identify 228 MW of named corporate and institutional VPPAs plus a separate 12-year hedge.
Structured profile
- Capacity
- 418.9 MW
EIA May 2026
- Full COD
- May 26, 2020
Project financials
- Registered operator
- Mesquite Star Special LLC
EIA May 2026
Units and generators
Operating generator records and technology attributes reported through EIA-860.
| Generator | Capacity | Technology | Operation | Status |
|---|---|---|---|---|
| MESQ | 418.9 MW 418.9 MW summer | Onshore Wind Turbine Wind · WT | Mar 2020 | Operating |
Performance
Monthly EIA generation history and recent market-resource behavior where linked telemetry is available.
Peer context
- Technology capacity
- 418.9 MW
- National rank
- #24
- TX rank
- #10
Monthly generation
Download CSVMonthly generation is reported through EIA-923. Capacity factor uses the current EIA nameplate capacity and is shown only for complete calendar years.
Grid and market context
Deterministic links to ERCOT market resources, price records, outage disclosures, queue records, and nearby infrastructure. Candidate joins remain labeled until corroborated.
Nearby substations
HIFLD infrastructure inventoryCommercial, land, and environmental record
Source-backed project transactions, agreements, land records, permits, and environmental disclosures. Portfolio and adjacent-project facts remain explicitly scoped.
Land and environmental record
Related parties and identifiers
Parties, market resources, and identifiers tied to this asset, with owner, operator, developer, EPC, compliance provider, and interconnecting entity roles kept separate.
Relationship graph
Drag organizations to explore the network. Select a node to pin its details and available page link.
Parties and identifiers
| Relationship | Entity | Basis |
|---|---|---|
| Owner / operator | Owner / operator for Mesquite Star | |
| Lender | Lender for Mesquite Star | |
| Grid selection | plant:plant-62587 | Canonical asset page /ercot/assets/plant/mesquite-star. |
Reporting portfolio
Portfolio membership follows the latest EIA-860 reporting entity. It does not imply ultimate ownership.
Timeline and sources
Project milestones and public references behind the asset profile.
Project timeline
- Financing closed and construction beganClearway Me...
Clearway announced financing close, notice to proceed to Blattner, and 118 Siemens Gamesa turbines.
- EIA generator operating dateEIA May 202...
EIA reports March 2020 for the operating generator record.
Sources
Related assets
Similar plants ranked by technology, capacity, and distance.
Maverick Creek Wind
Wind · 491.6 MW
Concho County
Stephens Ranch Wind Energy LLC
Wind · 376 MW