Misae Solar
Copenhagen Infrastructure Partners · Childress County · ERCOT
Misae Solar is a 240 MWac photovoltaic facility near Childress, Texas. EIA's May 2026 inventory lists one operating generator under Plant ID 62249, with service beginning in January 2020 and Misae Lessee LLC as the registered operator. Copenhagen Infrastructure Partners reports commercial operations beginning in the fourth quarter of 2019 and a 1,674-acre site. Ingka Investments completed the acquisition of a 49% interest on March 31, 2020 and reports 823,228 panels.
Overview
Key fields
- Reported capacity
- 240 MW
EIA-reported operating capacity; nameplate, seasonal, AC/DC, and unit ratings may differ.
- Operating capacity
- 240 MWac
EIA May 2026
- Solar panels
- 823,228
Ingka
- Site area
- 1,674 acres
CIP
- Registry anchor
- Plant 62249
Misae Lessee LLC
Resource stack
- 2 resources
MISAE_UNIT1 · MISAE_UNIT2
Profile
- Grid role
- Utility-scale photovoltaic generation in ERCOT.
- Ownership
- CIP fund investment · Ingka Investments 49% interest.
Structured profile
- Operating capacity
- 240 MWac
EIA
- Minority investor
- Ingka Investments · 49%
CIP and Ingka
- Annual generation
- 567 GWh
Ingka
Units and generators
Operating generator records and technology attributes reported through EIA-860.
| Generator | Capacity | Technology | Operation | Status |
|---|---|---|---|---|
| 77777 | 240 MW 240 MW summer | Solar Photovoltaic Solar · PV | Jan 2020 | Operating |
Performance
Monthly EIA generation history and recent market-resource behavior where linked telemetry is available.
Peer context
- Technology capacity
- 240 MW
- National rank
- #109
- TX rank
- #47
Monthly generation
Download CSVMonthly generation is reported through EIA-923. Capacity factor uses the current EIA nameplate capacity and is shown only for complete calendar years.
ERCOT disclosed dispatch
2 ERCOT market resources · Solar
Generation
3 mo through May 22, 2026Capacity factor is average output vs. this plant's observed peak.
Output by hourlocal time · 90 days through May 22, 2026
Latest disclosed outputhourly · 2 weeks ending May 22, 2026
Generation from ERCOT's 60-Day SCED Disclosure (≈60-day lag), summed over this site's market resources.
Grid and market context
Deterministic links to ERCOT market resources, price records, outage disclosures, queue records, and nearby infrastructure. Candidate joins remain labeled until corroborated.
Market registration
ERCOT public disclosuresOperating context
ERCOT market recordsInterconnection record
ERCOT GIS ReportMatched to the latest available ERCOT generation-interconnection queue record. Queue status and completion dates describe the queue record; operating status is verified separately against plant and market registrations.
Nearby substations
HIFLD infrastructure inventoryCommercial, land, and environmental record
Source-backed project transactions, agreements, land records, permits, and environmental disclosures. Portfolio and adjacent-project facts remain explicitly scoped.
Land and environmental record
Related parties and identifiers
Parties, market resources, and identifiers tied to this asset, with owner, operator, developer, EPC, compliance provider, and interconnecting entity roles kept separate.
Relationship graph
Drag organizations to explore the network. Select a node to pin its details and available page link.
Parties and identifiers
| Relationship | Entity | Basis |
|---|---|---|
| Project company and EIA registered operator | Misae Lessee LLC | EIA May 2026 generator inventory |
| Portfolio project investor through copenhagen infrastructure iii | Financing covers a portfolio that includes Misae Solar. | |
| Portfolio 49% project investor since march 2020 | Financing covers a portfolio that includes Misae Solar. | |
| Market resources | MISAE_UNIT1, MISAE_UNIT2 | Linked ERCOT resources. |
| Grid selection | plant:plant-62249 | Canonical asset page /ercot/assets/plant/misae-solar. |
Reporting portfolio
Portfolio membership follows the latest EIA-860 reporting entity. It does not imply ultimate ownership.
Timeline and sources
Project milestones and public references behind the asset profile.
Project timeline
- Generator enters operationEIA-860
EIA-860 lists generator 77777 with this operating date.
- Latest disclosed generation interval
ERCOT SCED disclosure is delayed, so plant performance windows end at the latest disclosed interval.
Sources
Related assets
Similar plants ranked by technology, capacity, and distance.
Texas Solar Nova 1
Solar · 252 MW
Kent County
Texas Solar Nova 2
Solar · 200 MW
Kent County
ENGIE Long Draw Solar LLC
Solar · 225 MW
Borden County
Porter Solar, LLC (TX)
Solar · 245 MW
Denton County