Mesquite Wind Power LLC
Mesquite Wind LLC · Shackelford County · ERCOT
Mesquite Wind Power is the 200 MW first phase of the Lone Star wind development in Shackelford County, Texas. EIA's May 2026 inventory lists one aggregate generator under Mesquite Wind LLC with a November 2007 operating month. Post Oak Wind is a separate second-phase plant and is not treated as an owner or component of this listing.
Overview
Key fields
- Operating capacity
- 200 MW
EIA
- Turbines
- 100
88 G83 · 12 G87
- Commercial operation
- Nov 2007
EIA
- Registry anchor
- Plant 56395
Mesquite Wind LLC
Resource stack
- 3 resources
LNCRK2_G871 · LNCRK2_G872
Profile
- Grid role
- Utility-scale onshore wind generation in ERCOT.
- Project identity
- The 200 MW first phase of the Lone Star wind development; Post Oak Wind is a separate second phase.
- Physical build
- 88 Gamesa G83 2 MW turbines and 12 Gamesa G87 2 MW turbines.
Structured profile
- Nameplate capacity
- 200 MW
EIA and PUCT
- Equipment
- 88 Gamesa G83 + 12 Gamesa G87
PUCT
- Registered operator
- Mesquite Wind LLC
EIA
- Development phase
- Lone Star first phase
PUCT
Units and generators
Operating generator records and technology attributes reported through EIA-860.
| Generator | Capacity | Technology | Operation | Status |
|---|---|---|---|---|
| 1 | 200 MW 200 MW summer | Onshore Wind Turbine Wind · WT | Nov 2007 | Operating |
Performance
Monthly EIA generation history and recent market-resource behavior where linked telemetry is available.
Peer context
- Technology capacity
- 200 MW
- National rank
- #276
- TX rank
- #93
Monthly generation
Download CSVMonthly generation is reported through EIA-923. Capacity factor uses the current EIA nameplate capacity and is shown only for complete calendar years.
ERCOT disclosed dispatch
3 ERCOT market resources · Wind
Output by hourlocal time · 90 days through May 22, 2026
Latest disclosed outputhourly · 2 weeks ending May 22, 2026
Generation from ERCOT's 60-Day SCED Disclosure (≈60-day lag), summed over this site's market resources.
Grid and market context
Deterministic links to ERCOT market resources, price records, outage disclosures, queue records, and nearby infrastructure. Candidate joins remain labeled until corroborated.
Market registration
ERCOT public disclosuresOperating context
ERCOT market recordsNearby substations
HIFLD infrastructure inventoryCommercial, land, and environmental record
Source-backed project transactions, agreements, land records, permits, and environmental disclosures. Portfolio and adjacent-project facts remain explicitly scoped.
Land and environmental record
Related parties and identifiers
Parties, market resources, and identifiers tied to this asset, with owner, operator, developer, EPC, compliance provider, and interconnecting entity roles kept separate.
Relationship graph
Drag organizations to explore the network. Select a node to pin its details and available page link.
Parties and identifiers
| Relationship | Entity | Basis |
|---|---|---|
| Project company and registered operator | Mesquite Wind LLC | EIA May 2026 generator inventory |
| Turbine supplier | PUCT Mesquite registration | |
| Market resources | LNCRK2_G871, LNCRK2_G872, LNCRK_G83 | Linked ERCOT resources. |
| Grid selection | plant:plant-56395 | Canonical asset page /ercot/assets/plant/mesquite-wind-power-llc. |
Reporting portfolio
| Largest reported plants | Capacity | State |
|---|---|---|
| Post Oak Wind LLC | 200 MW | TX |
| Mesquite Wind Power LLCCurrent | 200 MW | TX |
Portfolio membership follows the latest EIA-860 reporting entity. It does not imply ultimate ownership.
View full reporting portfolioTimeline and sources
Project milestones and public references behind the asset profile.
Project timeline
- PUCT Registration FiledPUCT Mesqui...
The filing documented the 100-turbine equipment plan and 345 kV interconnection.
- Plant Entered ServiceEIA May 202...
EIA dates the operating generator to November 2007.
- Latest disclosed generation interval
ERCOT SCED disclosure is delayed, so plant performance windows end at the latest disclosed interval.
Sources
Related assets
Similar plants ranked by technology, capacity, and distance.
Post Oak Wind LLC
Wind · 200 MW
Shackelford County
King Creek Wind Farm 2, LLC
Wind · 209 MW
Throckmorton County
Hackberry Wind Farm
Wind · 162.3 MW
Shackelford County