ERCOTGenerator outage
HEADCAMP_ESR1 Forced
Open 3d
ERCOT · posted Oct 21, 5:01 AM CDT
HEADCAMP_ESR1 Forced · 40 MW reduction
110 MW of 150 MW available · BATT · Other
Reduction
40MW
110 MW of 150 MW still available
Event record
- State
- Active
- Severity
- Info
- Since
- Oct 18, 8:32 PM CDT
- Posted by source
- Oct 21, 5:01 AM CDT
- First seen by Ask the Grid
- Oct 21, 9:35 AM CDT
As ERCOT filed it
- Fuel type
- BATT
- Nature of work
- Other