MetricRobert Moses Power Dam
St Lawrence County
Rainbow Falls Hydro
St Lawrence County
Capacity855 MW25 MW
TechnologyConventional HydroelectricConventional Hydroelectric
OperatorNew York Power AuthorityErie Boulevard Hydropower LP
Operating units161
Latest 12-month generation6.66 TWh108.7 GWh
Latest complete-year capacity factor89.8% (2025)49.5% (2024)
National technology rank#14 of 1,349#405 of 1,349
Latest EIA report2026-042024-12