RetrospectivePJM

The Day PJM Broke Its Demand Record

July 2, 2026. Extreme heat pushed estimated electricity demand to 168,158 MW. Demand response, emergency generation, and a federal permit order kept the grid balanced; a separate data-center backup order was never activated.

PJM map showing extreme heat across its 13-state footprint during the July 2026 heat wave
The July 2 heat covered the full PJM footprint. The operator measured a 97 F regional average, the hottest in its post-event record. Graphic: PJM July 9 hot-weather review.

At 5:55 p.m. on July 2, the largest power market in the United States was using effectively everything it had. Air conditioners were pulling harder just as power plants were failing in the heat. PJM had recalled maintenance outages, called demand response, raised every available generator, and obtained federal permission for some plants to run beyond their environmental permit limits.

The meter reached 162,713 megawatts. But that was not the record.

The record was the electricity PJM estimates would have been consumed if it had not paid customers to stop consuming it. Add the curtailed demand back and the system wanted 168,158 MW between 5 and 6 p.m. - 2,595 MW above a mark that had stood since 2006. The estimate remains preliminary while PJM completes its demand-response accounting, but the shape of the event is already clear in the public grid data.

Physical load approached the 2006 unrestricted record
059.6k119.2k178.8kJun 29Jul 1Jul 3Jul 52006 unrestricted recordJul 2 peak
Hourly served load(MW)drag to zoom
Two-hour samples of preliminary hourly served load across PJM, June 29 to July 5, with the 5 p.m. peak hour retained (pjm.hrl_load_prelim). The line reaches 162,569 MW; PJM's weather-normalized unrestricted estimate was 168,158 MW, because it adds curtailed demand back to the meter.

The record is bigger than the meter#

Ask the Grid's hourly series reaches 162,569 MW at 5 p.m., almost exactly matching PJM's 162,713 MW instantaneous reading at 5:55. The difference is measurement: our line is an hourly average assembled from PJM's load areas; PJM's figure is the single highest instant.

Neither number includes all the electricity consumers wanted. PJM estimates that demand response delivered 6,113 MW of reduction on July 2. It is not correct to simply add that number to the metered peak - the reductions have different baselines and are not all coincident - but demand-response performance is what allowed PJM to estimate an unrestricted peak of 168,158 MW.

That distinction matters. PJM did not serve 168 GW through wires at one moment. It kept the system balanced while serving 162.7 GW and making a material block of demand disappear on purpose.

PJM event summary listing the record demand, high temperatures, forced outages, demand response and permit relief
PJM's preliminary accounting of the July 2-4 event. The 168,158 MW unrestricted peak adds estimated curtailed demand back to physical load. Graphic: PJM.

At 5:18, the emergency stopped being theoretical#

The public operations log lets us rebuild the critical 37 minutes. At 5:18 p.m., PJM declared a Maximum Generation Emergency Action for the Mid-Atlantic and Southern regions. Every available online unit was to move toward emergency maximum output.

At 5:32 p.m., PJM issued an Emergency Use of Back-Up Generator Warning. Large loads in the two regions were being told to prepare for the possibility that they would have 15 minutes to disconnect from utility power and move onto their own generators.

At 5:36 p.m., it issued a Deploy All Resources Action specifically for BGE, PEPCO and Dominion. Generators were ordered to full output, offline generation was to start as quickly as possible, and dispatched load-management customers were to reduce consumption immediately. The instantaneous peak arrived 19 minutes later.

Thirty-seven minutes into the emergency
Time (ET)PJM actionWhat changed
5:18 p.m.Maximum Generation ActionAll available generation called
5:32 p.m.Backup Generator WarningLarge-load backup action prepared, not deployed
5:36 p.m.Deploy All ResourcesBGE, Dominion and PEPCO targeted
5:55 p.m.Estimated instantaneous peak162,713 MW physically served
8:40 p.m.Maximum Generation endedEmergency actions cleared
PJM emergency postings and the operator's July 9 event review. The backup-generator step remained a warning; PJM never issued the separate action that would have directed large loads to transfer to on-site generators.
PJM timeline of emergency procedures across July 2, July 3 and July 4
PJM's full emergency-procedure timeline. The July 2 escalation reached Maximum Generation and a backup-generator warning, then cleared that evening. Graphic: PJM.
The full PJM footprint at 5 p.m. Eastern, just before the estimated instantaneous peak. Every available resource had been called, and demand response was already deployed.
Open on the main map
1/2

The data-center order never came#

The word warning is doing crucial work.

Three days earlier, PJM had asked the Department of Energy for unusual authority: if the grid reached the last step before voltage reduction or forced outages, PJM wanted to direct large loads with backup generation to leave the grid. The application specifically discussed data centers and hyperscalers. DOE granted that authority in Order 202-26-33.

But authority is not activation. PJM's public emergency log contains the 5:32 warning and no Emergency Use of Back-Up Generator Action. PJM's own post-event report is explicit: the action was not needed and was never issued.

The public record therefore does not support the claim that PJM ordered data centers onto diesel generators on July 2. It supports a narrower and more revealing statement: the system got close enough that operators warned large loads to be ready.

Six gigawatts disappeared on purpose#

This does not mean behind-the-meter generators stayed idle. PJM's separate, market-based demand-response programs were already running. Pre-emergency resources began reducing load at 1:30 p.m. Emergency products followed later, including resources PJM defines as behind-the-meter generators whose permits require an EEA2 condition before they can operate.

The difference is between a registered resource performing under an existing demand-response contract and the federal last-resort order aimed at large loads. The first happened. The second did not.

Demand response was part of the record calculation
DayPreliminary responseShare of unrestricted peak
July 26,113 MW3.6%
July 35,037 MW3.2%
PJM preliminary demand-response performance. The unrestricted peak estimate adds curtailed demand back to physical load; it is therefore larger than the meter reading at the same time.
PJM chart of preliminary demand-response performance from June 29 through July 5
Preliminary demand response delivered 6,113 MW on July 2 and 5,037 MW on July 3. Graphic: PJM.

Public data gives the program-level result, but not the customer list. It does not say which participants were data centers, how many megawatts they curtailed, or which facilities started engines. A data center could have participated as registered demand response without being ordered to do so under the federal authority. PJM does not publish enough detail to separate those cases.

Oil went from spare tire to six-gigawatt resource#

While demand moved down, the generation stack moved up. At the 5 p.m. hourly peak, natural gas supplied 70,435 MW, nuclear plants 31,704 MW, and coal 28,761 MW. Solar was still producing 11,477 MW. The unusual resource was oil.

At 6 a.m. Eastern, oil was supplying 639 MW. Eleven hours later it was producing 6,194 MW, and it reached 6,425 MW at 7 p.m. Oil is expensive and emissions-intensive, and much of this fleet exists for exactly these hours: when the system has exhausted cheaper options.

Gas carried the day; oil supplied the last six gigawatts
026.0k52.0k78.0kJul 2Jul 2Jul 2Jul 2System peak
GasNuclearCoalSolarOil(MW)drag to zoom
Hourly PJM generation by fuel on July 2 (pjm.gen_by_fuel). Oil rose from 639 MW at 6 a.m. Eastern to 6,194 MW at the 5 p.m. load peak, then reached 6,425 MW at 7 p.m.
Oil generation stayed elevated through the holiday weekend
02.3k4.7k7.0kJun 29Jul 1Jul 3Jul 5
Daily oil peak(MW)drag to zoom
Daily peak oil-fired output in PJM, June 29 to July 5 (pjm.gen_by_fuel). Oil peaked at 6,519 MW on July 3, the day after the demand record.

The most expensive power was where the grid was tightest#

The stress was not evenly distributed. PJM's deploy-all-resources action named BGE, PEPCO and Dominion, the same Mid-Atlantic corridor where heat, outages and transmission constraints converged.

Day-ahead prices had already anticipated trouble. In BGE, the July 2 hourly price reached $1,598.77/MWh. PEPCO reached $1,533.62/MWh. The PJM-wide reference reached $1,219.91/MWh an hour later. Most days in the preceding week averaged tens of dollars per megawatt-hour at PJM-RTO.

The highest day-ahead prices formed around Baltimore and Washington
05761.2k1.7kJul 2Jul 2Jul 2Jul 2
BGEPEPCOWestern HubPJM-RTODominion Hub($/MWh)drag to zoom
Hourly day-ahead locational marginal prices for July 2 (pjm.da_hrl_lmps). These are wholesale prices, not retail bills. BGE reached $1,598.77/MWh in the 6 p.m. hour; the PJM-wide reference reached $1,219.91/MWh an hour later.

This is evidence of wholesale system stress, not a direct measure of anyone's electric bill. Retail customers buy through utilities, suppliers, hedges and regulated procurement plans. Emergency costs may also be allocated later through uplift. The event created expensive wholesale hours; the public data cannot turn those hours into a universal household bill increase.

The grid lost plants while it needed them most#

Demand alone did not create the emergency. Supply was eroding underneath it. PJM reported 18,363 MW of generation outages at the July 2 peak, compared with roughly 12,800 MW on the ten highest summer peak days of the previous three years. Across July 2-4, forced outages ranged from 18.1 to 19.4 GW. Plant equipment was the largest reported cause, followed by ambient-air limitations and other operating problems.

PJM comparison of generation outages during the July 2026 heat wave with prior summer peak days
Forced outages were materially higher than during recent summer peak days. Graphic: PJM.
PJM breakdown of forced outage causes during the July 2026 heat wave
Equipment failures made up the largest reported block of forced outages; ambient conditions also reduced output. Graphic: PJM.

Ninety-four generators crossed permit lines#

DOE's other order, 202-26-32, addressed the supply side. It covered 594 units at 51 plants, about 20.4 GW of installed capacity, whose environmental permits or operating restrictions could limit them during the emergency.

PJM now says 94 units at 17 plants, representing approximately 3.25 GW, actually ran beyond permit limits under that authority. Together they accumulated 1,107 unit-hours above those limits.

PJM summary of generators operating beyond environmental permit limits during the July 2026 heat wave
The supply-side federal order was used: 94 units at 17 plants reported operating beyond permit limits. Graphic: PJM.
Ozone was unhealthy at several Maryland monitors
MonitorJuly 2 ozone AQICategory
Edgewood136Unhealthy for sensitive groups
Essex115Unhealthy for sensitive groups
Fair Hill108Unhealthy for sensitive groups
Aldino105Unhealthy for sensitive groups
Southern Maryland101Unhealthy for sensitive groups
AirNow daily ozone AQI for July 2. These readings establish the air-quality conditions, not causation. Public monitoring cannot isolate the effect of PJM's temporary generator permit relief from heat, regional chemistry, transport, or other emissions sources.

That is an unusually concrete environmental finding. It is also the boundary of the public record. PJM says unit owners reported waiver-dependent operations daily, but the unit-level notices are not posted alongside DOE's order. DOE publishes changing lists of eligible units; those lists are not proof that every listed plant ran or exceeded a permit.

AirNow monitors recorded unhealthy-for-sensitive-groups ozone in parts of Maryland on July 2, including AQI 136 at Edgewood. Those readings cannot attribute a monitor result to the federal waiver. Heat and sunlight drive ozone formation, and power plants are only one source among several. The supportable conclusion is that plants operated beyond permit limits. The unsupported one is that the order caused a particular community's bad-air day.

Data centers are part of the load, not a smoking gun#

Data centers are not incidental to PJM's problem. They are one of its largest new facts. PJM's May forecast-accuracy report puts the 2026 data-center July peak at 11,479 MW, up from 8,167 MW observed in July 2025 - an increase of about 41 percent in one year. The forecast is equivalent to 6.8 percent of a peak the size of 168,158 MW.

PJM's data-center forecast is large, but it is not an event meter
Area2025 observed July peak2026 forecast July peak
Dominion5,432 MW7,066 MW
AEP1,603 MW2,699 MW
Rest of PJM1,132 MW1,714 MW
PJM total8,167 MW11,479 MW
PJM 2026 Load Forecast Accuracy Report. The 11,479 MW forecast is 6.8% of a peak the size of 168,158 MW, but PJM does not publish site-level, event-hour data-center load sufficient to assign the emergency to specific campuses or companies.

The load is geographically concentrated. Dominion's 2026 data-center July peak forecast is 7,066 MW. AEP accounts for 2,699 MW. The rest of PJM combined accounts for roughly 1,714 MW. Northern Virginia is therefore central to the region's new load shape and to the transmission constraints that matter on its hottest afternoons.

But a structural driver is not the same as an event trigger. PJM does not publish actual data-center demand for 5:55 p.m. on July 2. It does not publish a site-by-site curtailment list. It does not identify operators or owners among the 6,113 MW of demand response. The forecast can tell us how large the sector has become, not which server hall created the final megawatt of the emergency.

The public record ends before the site gate#

PJM got through the hottest regional day it has measured without voltage reduction, manual load shed, or the special backup-generator action. It did so by calling every available generator, paying roughly 6.1 GW of demand to move out of the way, and allowing 94 units to operate beyond permit limits. Emergency actions concentrated in the corridor where data-center growth is largest.

That is more consequential than saying data centers caused an emergency. It shows exactly how close the system came, exactly which levers operators pulled, and exactly where public transparency stopped.

We know the grid warned large loads. We know registered behind-the-meter resources were eligible and deployed within demand-response programs. We know 17 plants exceeded permit limits. We know PJM's forecast data-center peak is almost 7 percent of a system peak this size.

We still do not know which data centers reduced load, which ones started generators, or what they emitted. For a resource PJM may increasingly depend on during emergencies, that is not a small missing field. It is the next story.

The charts above are frozen from the PJM data behind Ask the Grid at publication. Open PJM on the main map and replay July 2, 2026.