RetrospectivePJM

The Day PJM Broke Its Demand Record

PJM met a preliminary record on July 2 using demand response, additional generation and federal operating authority. The emergency timeline shows how operators managed the hottest regional day in their record.

PJM map showing extreme heat across its 13-state footprint during the July 2026 heat wave
The July 2 heat covered the full PJM footprint. The operator measured a 97 F regional average, the hottest in its post-event record. Graphic: PJM July 9 hot-weather review.

On July 2, extreme heat pushed PJM to a preliminary all-time unrestricted peak of 168,158 MW. The system physically served an instantaneous peak of 162,713 MW while PJM deployed demand response, called available generation in constrained areas, and relied on a federal order allowing selected generators to operate beyond normal environmental permit limits. Those measures helped PJM maintain reliability. A separate federal order authorizing backup generation at large loads, including data centers, was available but never activated.

PJM's unrestricted estimate adds curtailed demand back to the load the grid served. The 168,158 MW figure exceeded the previous 2006 benchmark by 2,595 MW, while the metered instantaneous peak reached 162,713 MW. Together, the preliminary figures show the demand placed on the system and the role of measures taken to manage it.

Physical load approached PJM's previous all-time peak benchmark
059.6k119.2k178.8kJun 29Jul 1Jul 3Jul 5Previous PJM all-time peak, 2006Jul 2 peak
Hourly served load(MW)drag to zoom
Two-hour samples of preliminary hourly served load across PJM, June 29 to July 5, with the 5 p.m. peak hour retained (PJM's preliminary hourly load feed, stored as pjm.hrl_load_prelim). The line reaches 162,569 MW; PJM separately reported a preliminary unrestricted peak load of 168,158 MW after accounting for estimated curtailments.

Demand response helped manage a record peak#

Ask the Grid's hourly series reaches 162,569 MW at 5 p.m., almost exactly matching PJM's 162,713 MW instantaneous reading at 5:55. The difference is measurement: our line is an hourly average assembled from PJM's load areas; PJM's figure is the single highest instant.

Curtailment service providers reported an average of approximately 6,113 MW of expected reductions during the July 2 mandatory availability period. Actual demand-response performance remained preliminary and could take up to three months to finalize.

The 6,113 MW is an average of expected reductions across the mandatory availability period, hourly-ending 11 through 22. PJM's unrestricted estimate and instantaneous served peak describe different time bases. The expected-reduction figure puts the scale of the demand-response call alongside the event's peak measurements.

PJM event summary listing record demand, high temperatures, generation outages, expected demand response and permit relief
PJM's preliminary accounting of the July 2-4 event. The 168,158 MW unrestricted peak adds estimated curtailed demand back to physical load. Graphic: PJM.

At 5:18, the emergency stopped being theoretical#

The public operations log lets us rebuild the critical 37 minutes. At 5:18 p.m., PJM declared a Maximum Generation Emergency Action for the Mid-Atlantic and Southern regions. Every available online unit was to move toward emergency maximum output.

At 5:32 p.m., PJM issued an Emergency Use of Back-Up Generator Warning. Large loads in the two regions were being told to prepare for the possibility that they would have 15 minutes to disconnect from utility power and move onto their own generators.

At 5:36 p.m., it issued a Deploy All Resources Action specifically for BGE, PEPCO and Dominion. Generators were ordered to full output, offline generation was to start as quickly as possible, and dispatched load-management customers were to reduce consumption immediately. The instantaneous peak arrived 19 minutes later.

Thirty-seven minutes into the emergency
Time (ET)PJM actionWhat changed
5:18 p.m.Maximum Generation ActionAll available generation called
5:32 p.m.Backup Generator WarningLarge-load backup action prepared, not deployed
5:36 p.m.Deploy All ResourcesBGE, Dominion and PEPCO targeted
5:55 p.m.Estimated instantaneous peak162,713 MW physically served
8:40 p.m.Maximum Generation endedEmergency actions cleared
PJM emergency postings and the operator's July 9 event review. The backup-generator step remained a warning; PJM never issued the separate action that would have directed large loads to transfer to on-site generators.
PJM timeline of emergency procedures across July 2, July 3 and July 4
PJM's full emergency-procedure timeline. The July 2 escalation reached Maximum Generation and a backup-generator warning, then cleared that evening. Graphic: PJM.
PJM at the July 2 peak. The emergency applied across the 13-state footprint, while the most acute price pressure formed in the eastern BGE and PEPCO zones.

The large-load backup action never came#

PJM had secured an additional option for the emergency. Its June 27 application sought authority to call backup generation at large loads, including industrial, commercial and data-center sites with at least 50 MW at a delivery point or interconnection. DOE granted that authority on June 30 in Order 202-26-33.

At 5:32 p.m. on July 2, PJM warned those loads to prepare for a possible transfer to backup power. The operator's post-event report says the corresponding action was never needed or issued. The system was managed using the other available resources and procedures.

Registered demand response was already operating#

PJM's existing demand-response programs were already active. Pre-emergency resources began reducing load at 1:30 p.m. Emergency products followed, including a class of registered behind-the-meter generators permitted to run under EEA2 conditions.

Those market programs provided a separate route for reducing grid demand. Their dispatch record shows the products and regions called, with the final measured response still preliminary at publication. The special federal large-load action remained an additional option throughout the event.

PJM's six-gigawatt figure was an expected reduction
DayCSP-reported expected reductionsMeasurement window
July 26,113 MW averageMandatory availability period, HE11-HE22
July 35,037 MW averageMandatory availability period, HE11-HE22
PJM labels these values CSP-reported expected reductions averaged over the mandatory availability period. They are not settled performance at the instantaneous peak; actual reductions may take up to three months to finalize.
PJM chart of CSP-reported expected demand reductions from June 29 through July 5
Curtailment service providers reported average expected reductions of 6,113 MW on July 2 and 5,037 MW on July 3 during the mandatory availability period. Actual reductions were not yet final. Graphic: PJM.

Oil went from spare tire to six-gigawatt resource#

While demand moved down, the generation stack moved up. At the 5 p.m. hourly peak, natural gas supplied 70,435 MW, nuclear plants 31,704 MW, and coal 28,761 MW. Solar was still producing 11,477 MW. The unusual resource was oil.

At 6 a.m. Eastern, oil was supplying 639 MW. Eleven hours later it was producing 6,194 MW, and it reached 6,425 MW at 7 p.m. Oil is expensive and emissions-intensive, and much of this fleet exists for exactly these hours: when the system has exhausted cheaper options.

Gas carried the day; oil supplied the last six gigawatts
026.0k52.0k78.0k12 AM7 AM3 PM11 PMSystem peak
GasNuclearCoalSolarOil(MW)drag to zoom
Hourly PJM generation by fuel on July 2 (pjm.gen_by_fuel). Oil rose from 639 MW at 6 a.m. Eastern to 6,194 MW at the 5 p.m. load peak, then reached 6,425 MW at 7 p.m.
Oil generation stayed elevated through the holiday weekend
02.3k4.7k7.0kJun 29Jul 1Jul 3Jul 5
Daily oil peak(MW)drag to zoom
Daily peak oil-fired output in PJM, June 29 to July 5 (pjm.gen_by_fuel). Oil peaked at 6,519 MW on July 3, the day after the demand record.

The most expensive power was where the grid was tightest#

The stress was not evenly distributed. PJM's deploy-all-resources action named BGE, PEPCO and Dominion, the same Mid-Atlantic corridor where heat, outages and transmission constraints converged.

Day-ahead prices had already anticipated trouble. In BGE, the July 2 hourly price reached $1,598.77/MWh. PEPCO reached $1,533.62/MWh. The PJM-wide reference reached $1,219.91/MWh an hour later. Most days in the preceding week averaged tens of dollars per megawatt-hour at PJM-RTO.

The highest day-ahead prices formed around Baltimore and Washington
05761.2k1.7k12 AM7 AM3 PM11 PM
BGEPEPCOWestern HubPJM-RTODominion Hub($/MWh)drag to zoom
Hourly day-ahead locational marginal prices for July 2 (pjm.da_hrl_lmps). These are wholesale prices, not retail bills. BGE reached $1,598.77/MWh in the 6 p.m. hour; the PJM-wide reference reached $1,219.91/MWh an hour later.

These expensive wholesale hours created exposure for utilities and suppliers according to their procurement and hedging arrangements. Retail effects depend on those contracts, state regulation and later cost allocation, including any uplift arising from emergency operations.

Generation outages rose during the heat event#

Demand alone did not create the emergency. PJM reported 18,363 MW of generation outages at the July 2 peak and 18,071 MW at the July 3 peak, compared with roughly 12,800 MW on the ten highest summer peak days of the previous three years. Its preliminary event-period chart subsequently reached 19,395 MW around July 5.

Generation outages and derates were elevated during the heat event. Plant-equipment problems accounted for the largest category, while ambient-air limitations and other or unknown causes were also significant.

PJM comparison of generation outages during the July 2026 heat wave with prior summer peak days
Generation outages were elevated during the event. PJM reported 18,363 MW at the July 2 peak, 18,071 MW at the July 3 peak, and a later event-period maximum of 19,395 MW around July 5. Graphic: PJM.
PJM breakdown of generation outage causes during the July 2026 heat wave
Plant-equipment problems were the largest reported outage category. Ambient-air limitations and other or unknown causes were also significant. Graphic: PJM.

Ninety-four generators crossed permit lines#

DOE's other order, 202-26-32, addressed the supply side. It covered 594 units at 51 plants, about 20.4 GW of installed capacity, whose environmental permits or operating restrictions could limit them during the emergency.

PJM now says 94 units at 17 plants, representing approximately 3.25 GW, actually ran beyond permit limits under that authority. Together they accumulated 1,107 unit-hours above those limits.

PJM summary of generators operating beyond environmental permit limits during the July 2026 heat wave
The supply-side federal order was used: 94 units at 17 plants reported operating beyond permit limits. Graphic: PJM.
Preliminary AirNow daily ozone AQI
MonitorJuly 2 ozone AQICategory
Edgewood136Unhealthy for sensitive groups
Essex115Unhealthy for sensitive groups
Fair Hill108Unhealthy for sensitive groups
Aldino105Unhealthy for sensitive groups
Southern Maryland101Unhealthy for sensitive groups
Preliminary AirNow daily ozone AQI for July 2. AirNow data undergo preliminary quality checks but are not fully validated for regulatory use. These readings establish air-quality conditions, not causation, and cannot isolate the effect of PJM's temporary generator permit relief.

The 1,107 unit-hours describe actual operations reported under the supply-side authority, across the 94 units PJM identified. The larger list of eligible equipment defined the resources available to call during the emergency.

The event also coincided with ozone rated unhealthy for sensitive groups in parts of Maryland, including AQI 136 at Edgewood. Heat, sunlight and emissions from multiple sources contribute to those conditions. The monitor readings describe local air quality during the event; PJM's operating report supplies the separate account of waiver-dependent generation.

Large-load growth shapes future emergency planning#

PJM's load forecast shows why large facilities matter to future emergency planning. Its May forecast-accuracy report put the 2026 data-center July peak at 11,479 MW, equivalent to 6.8 percent of a system peak the size of the preliminary July 2 unrestricted estimate.

PJM's forecast places data-center demand in the eastern load areas
AreaShare of 2026 forecast at July peak
Dominion61.6%
AEP23.5%
ComEd7.7%
PS2.7%
Other zones4.4%
PJM forecast total11,479 MW
PJM 2026 Load Forecast Accuracy Report. Zone shares are PJM's published rounded values; they sum to 99.9% because of rounding. The values are forecast peak demand and zone shares for planning year 2026.

The forecast was concentrated in the same broad geography as much of the operating pressure: 61.6 percent of data-center peak demand was assigned to Dominion and 23.5 percent to AEP, followed by ComEd at 7.7 percent and PS at 2.7 percent. These are forecast zone shares, establishing the scale and location of the demand PJM was planning to serve.

The response the next emergency will require#

PJM maintained service through the event without voltage reduction, manual load shedding or activation of the special large-load backup action. It relied on load management, all available resources in affected areas and supply-side federal authority that allowed 94 units at 17 plants to operate beyond permit limits.

That combination defines the operating lesson of July 2. Record demand arrived with elevated generation outages and constrained transfer capability in the east, requiring both additional supply and reduced demand. The preliminary unrestricted peak captures the size of the challenge; the emergency timeline shows the steps used to manage it.

The next operational test is the availability of those responses when heat and equipment outages coincide again. Final demand-response performance and the reported use of emergency generation provide concrete measures for evaluating how much flexibility the system can count on.

The charts above are frozen from the PJM data behind Ask the Grid at publication. Open PJM on the main map and replay July 2, 2026.

Share this story#

The day PJM broke its demand record, shareable chart card
01The day PJM broke its demand record
The seven-day load profile, shareable chart card
02The seven-day load profile
Two different PJM peak numbers, shareable chart card
03Two different PJM peak numbers
Warning is not action, shareable chart card
04Warning is not action
A four-card visual summary of the event. Open any card full size, share the image directly, or download the 2160 px PNG.