Aligned Phoenix PHX-01/02/03
Operating · Aligned Data Centers · 2500 W Union Hills Drive, Phoenix, AZ
Aligned's Phoenix campus (PHX-01/02/03) is at 2500 W Union Hills Drive, Phoenix, on a 55-acre site designed to Tier III standards. Arizona Public Service and Aligned announced a new 69 kV substation at Union Hills Drive and I-17, fed by four lines from three sources, plus a planned 63-megawatt microgrid. Aligned said the campus can isolate itself from the grid during congestion and guaranteed a PUE of 1.15. Cooling uses a closed-loop chilled water design.
Overview
- Campus power
- Not disclosed
- No exact-site MW figure in cited sources.
- Status
- Operating
- Operating campus
- Site
- 55 acres
- Campus
- Compute profile
- Colocation
- Project scope
- Campus at 2500 W Union Hills Drive, Phoenix, AZ.
- Power and grid
- N+1 block redundant topology, 415V distribution to racks (A+B distribution)
Power and grid
- Substation
- New 69 kV enhanced-capability substation at Union Hills Drive and I-17
- Point of interconnection
- On-site APS substation fed by four power lines from three sources
- Interconnection voltage (kV)
- 69
- Redundancy
- N+1 block redundant topology, 415V distribution to racks (A+B distribution)
Facility and development
- Site area (acres)
- 55
- Facility class
- Colocation
- Availability tier
- Tier III (design standard)
- Cooling medium
- Closed-loop chilled water
- Efficiency
- PUE 1.15 · design · Exact Asset