Argent LNG
Large load · Port Fourchon, Lafourche Parish, LA, Port Fourchon, LA
Argent LNG is a planned LNG export terminal at Port Fourchon in Lafourche Parish, Louisiana. The project is in FERC pre-filing and has not been approved. It plans a 350-megawatt natural gas-fired power generation facility on site.
Loading map…
Overview
FERC staff approved the Argent LNG, LLC request to enter the Pre-filing Process for the planned Argent LNG Project on October 1, 2025. The project has not been approved at this time. The schedule anticipates construction by December 2027 and an in-service date of Q1 2030.
Profile
- Electricity and grid
- The project plans a 350-megawatt natural gas-fired power generation facility. Argent LNG plans a modular design that uses more efficient gas-generated electric compression motors on the liquefaction trains. It intends to purchase Baker Hughes LM9000 gas turbine driven electric generators upon final investment decision.
- Permits
- The project is advancing through the Federal Energy Regulatory Commission pre-filing process (Docket No. PF25-11). Argent LNG, LLC owns the assets for the project.
Facility
- Activity
- Liquefied natural gas export
- Industry
- Industrial
- Site type
- Facility
- Operating status
- Planned
Reported Jul 24, 2026
Permits and agreements
- Permit
- FERC pre-filing, Docket No. PF25-11