Crossett is a battery energy storage facility in Crane County, Texas. EIA's May 2026 inventory reports a current operating rating of 203 MW / 400 MWh and a June 2022 service month. Jupiter Power's June 2022 commissioning announcement described the initial facility as 200 MW / 200 MWh. The page preserves both dated configurations rather than treating the original one-hour rating as current.
Mapped infrastructure geometry associated with this asset.
EIA May 2026
Jupiter Power
Jupiter Power
EIA plant 66009 · Inventory for Sep 2026.
| Generator | Technology | Status | Power (MW) | Energy (MWh) |
|---|---|---|---|---|
| BA | Batteries | Operating | 203 | 400 |
Similar plants ranked by technology, capacity, and distance.
Current generator records and technology attributes reported through EIA-860.
| Generator | Capacity | Technology | Operation | Status |
|---|---|---|---|---|
| BA | 203 MW 203 MW summer | Batteries BA | Jun 2022 | Operating |
Monthly EIA generation history and recent market-resource behavior where linked telemetry is available.
Deterministic links to ERCOT market resources, price records, outage disclosures, queue records, and nearby infrastructure. Candidate joins remain labeled until corroborated.
Source-backed project transactions, agreements, land records, permits, and environmental disclosures. Portfolio and adjacent-project facts remain explicitly scoped.
Parties, market resources, and identifiers tied to this asset, with owner, operator, developer, EPC, compliance provider, and interconnecting entity roles kept separate.
Drag organizations to explore the network. Select a node to pin its details and available page link.
Project milestones and public references behind the asset profile.
EIA reports June 2022 for the current generator record.
EIA-923 reports gross generation and net grid exchange for storage plants. Gross generation is shown as a discharge proxy; it is not a cycle count or conventional capacity factor.
2 ERCOT market resources · Battery / storage
Cycles/day is discharged energy vs. usable capacity (~209 MWh). Capacity factor is avg discharge vs. peak.
Observed ERCOT settlement prices at CROSSETT_ALL over 365 days (2025-10-26 to 2026-10-25).
The TB1 figure is a price benchmark, not revenue: it values one perfect-foresight cycle per day between the cheapest and dearest hour of each day, gross of round-trip losses, and excludes ancillary services. It describes what this node’s price shape was worth over the window — it is not this asset’s realized capture, and no dispatch is assumed or modelled.
Matched to the latest available ERCOT generation-interconnection queue record. Queue status and completion dates describe the queue record; operating status is verified separately against plant and market registrations.
Portfolio membership follows the latest EIA-860 reporting entity. It does not imply ultimate ownership.
Jupiter Power announced the 200 MW / 200 MWh configuration in commercial operation.
EIA's May 2026 inventory reports 203 MW / 400 MWh.
ERCOT SCED disclosure is delayed, so plant performance windows end at the latest disclosed interval.
Answered from the published record above. Questions whose inputs this profile does not carry are omitted rather than estimated.
Crossett Power Management reports 203 MW battery storage of operating nameplate capacity. These technology ratings do not establish a common export limit. Source: EIA Sep 2026.
Crossett Power Management is a batteries facility in Crane County, TX, participating in the ERCOT market.
Crossett Power Management is in Crane County, TX, inside the ERCOT balancing area.
Crossett Power Management is operated by Crossett Power Management LLC according to the EIA generator inventory. Reporting membership does not by itself establish ultimate ownership.
Crossett Power Management reported 70.1 GWh over the twelve months to 2026-07. For a storage plant this is reported gross generation — a discharge proxy, not a cycle count or a conventional capacity factor.
By capacity, Crossett Power Management ranks #57 of 1,061 operating plants of the same technology nationally. It ranks #19 of 254 in TX.
Plants within 25 km, nearest first, regardless of technology. Proximity is straight-line distance between mapped plant coordinates; it does not by itself establish a shared point of interconnection.