CyrusOne Durham DUR1 (NC-1)
Operating · CyrusOne · 2223 NE Creek Parkway, Durham, NC
CyrusOne's DUR1 data center is at 2223 NE Creek Parkway in Durham, North Carolina, in Research Triangle Park. The operator says it spans more than 420,000 sq ft with 92,320 sq ft of raised floor across eleven data halls. The DUR1-DUR2 campus, which includes the DUR2 shell delivered in 2025, has 40 MW of total IT capacity.
Overview
- Exact-site power
- Not disclosed
- No exact-site MW figure in cited sources.
- Status
- Operating
- Operating facility
- IT floor area
- 92,320 sq ft
- Facility
- Campus power
- 40 MW
- Parent campus · Capacity basis unspecified
- Project scope
- Facility at 2223 NE Creek Parkway, Durham, NC.
- Power and grid
Power and grid
| Capacity | Basis | Status | Scope | As of |
|---|---|---|---|---|
| 40 MW | Capacity basis unspecified | Reported | Campus | — |
| Operator-reported total IT capacity across the DUR1-DUR2 campus; basis unspecified. | ||||
Facility and development
- IT floor area (sq ft)
- 92,320
- Grid record
- Interconnection not publicly disclosed