Galaxy Helios Campus
Expanding
Expanding
Galaxy Digital owns and operates the Galaxy Helios Campus, a 2,200-acre hyperscale AI/HPC and crypto-mining complex in Afton, Texas, served by AEP Texas. Phase I (126,000 sq ft, energized May 2022, AI/HPC retrofit complete) delivers 200 MW gross power and 133 MW critical IT load to CoreWeave; Phase II (899,124 sq ft, under construction) will add 260 MW critical IT load with data-hall deliveries expected mid-2027; Phase III (133 MW committed) and full campus capacity of 1.63 GW are approved and contracted.
Original Phase 1 was Argo’s Bitcoin-mining facility. It was energized on May 5, 2022 and commenced mining operations. Galaxy later retrofitted the approximately 126,000-square-foot facility for AI/HPC use, delivering approximately 200 MW of gross power and 133 MW of critical IT load to CoreWeave.
Phase II is a greenfield AI/HPC build providing an additional 260 MW of critical IT load. Civil and structural work was underway by July 2026. Public-record reporting identified three permitted buildings near the original facility: Helios 2, Helios 3, and Helios 4. Reported building sizes were 199,124 square feet for one building and nearly 350,000 square feet each for the other two.
CoreWeave’s final option added 133 MW of critical IT load. Across Phases I–III, CoreWeave committed to 526 MW of critical IT load, corresponding to the full 800 MW of gross power then approved and contracted at Helios.
| Capacity | Basis | Status | Scope | As of |
|---|---|---|---|---|
| 200 MW | Campus Gross Power | Energized | Phase I | 2026-07-06 |
| Phase I gross power delivered to the campus and CoreWeave. | ||||
| 133 MW | Critical IT Load | Operating | Phase I | 2026-07-06 |
| Phase I critical IT load delivered to CoreWeave and generating revenue. | ||||
| 260 MW | Critical IT Load | Under Construction | Phase II | 2026-07-06 |
| Critical IT capacity under greenfield construction for Phase II; data-hall deliveries were expected to begin in the first half of 2027. | ||||
| 526 MW | Contracted Power | Contracted | Phases I-III | 2026-07-06 |
| CoreWeave committed critical IT load across Phases I through III under long-term leases. | ||||
| 800 MW | Campus Gross Power | Contracted | Phases I-III | 2026-07-06 |
| Full gross power currently approved and contracted at Helios across Phases I through III. | ||||
| 830 MW | Interconnection Request | Approved | Campus | 2026-01-15 |
| Additional computing demand approved by ERCOT after completion of the Large Load Interconnection Study; Galaxy executed an AEP Texas service agreement for this additional capacity. | ||||
| 1,630 MW | Utility Service | Approved | Campus | 2026-07-06 |
| Total campus power capacity reported as approximately 1.63 GW, representing total approved capacity after the additional 830 MW approval. | ||||
Also reported as Argo Data Center, Helios Data Center, Helios facility, Galaxy Helios.
Galaxy’s Helios campus in Dickens County received ERCOT approval for an additional 830 MW after completion of a Large Load Interconnection Study, bringing approved and utility-contracted capacity above 1.6 GW. The project also has reported Phase 2 building permits and a Dickens County PILOT/tax-abatement agreement. Phase I delivered approximately 200 MW gross power and 133 MW critical IT load to CoreWeave in 2026.
Argo Blockchain sells Dickens County Helios plant to Galaxy in $100M deal — Reports Argo’s sale of the Helios facility to Galaxy and describes staff retention and continuing community commitments, including the Spur swimming-pool project.
$20.5M tax abatement paves way for Galaxy growth in Dickens County — Reports a Dickens County PILOT agreement with Galaxy, a $2 million housing allocation, community programs, and expected employment and housing effects associated with Helios.
West Texas Helios facility leased to Nvidia-backed CrowdWeave — Reports that the Dickens County cryptocurrency facility formerly associated with Argo was transitioning into an AI-oriented data-center operation through a CoreWeave agreement.
Massive $3.5 billion expansion planned at AI data center in Dickens County — Reports permits for Helios 2, Helios 3, and Helios 4 near the initial County Road 112 facility and quotes Galaxy on the campus’s economic impact.
Cryptocurrency miners line up to come to Texas, and rural counties are welcoming them — Reports early local reaction to cryptocurrency-mining development in Afton and Dickens County, stating that residents did not oppose the businesses but had questions about cryptocurrency and its effects.