Appearance Dark Light Data centers in Texas: 174 sites, operators and power · Ask the Grid
Ask the Grid profiles 174 data centers in Texas: 111 operating, 29 under construction, and 23 proposed or approved. The largest clusters are in San Antonio (22), Dallas (19), and Austin (14). Oncor is the utility named for 26 of them. The largest operators are DataBank (14), Digital Realty (11), and CyrusOne (6).
profiled sites 174
operating 111
under construction 29
proposed or approved 23 Generation Data centers Storage Solar Wind Nuclear
Profiled facilities Ordered by reported MW Stream Data Centers 5 data centers
2020 Live Oak Data Center Facility profile · Dallas, TX
Dallas, TX ERCOT
Operating
Not disclosed No exact-asset power figure · building
365 Data Centers Richardson 365 Data Centers · Facility profile · Richardson, TX Richardson, TX ERCOT
Operating
6.2 MW Capacity basis unspecified · Reported · facility
ACS Hicks Field Data Center Vanguard US Serviceco, LLC · Facility profile · Fort Worth, TX Fort Worth, TX ERCOT
Under Construction
Up to 335 MW Utility Service · Contracted · campus
Alcon Data Center Alcon Vision · Facility profile · Fort Worth, TX Fort Worth, TX ERCOT
Operating
Not disclosed No exact-asset power figure · facility
Aligned DFW-03 Data Center Aligned Data Centers · Facility profile · Mansfield, TX Mansfield, TX ERCOT
Operating
Not disclosed No exact-asset power figure · facility
Amazon Ezell Drive Data Center Campus Amazon Data Services · Facility profile · DeSoto, TX DeSoto, TX ERCOT
Approved
Not disclosed No exact-asset power figure · campus
Amazon Horizon Junction Data Center Campus Amazon Data Services, Inc. · Facility profile · Floydada, TX Floydada, TX Grid context in profile
Proposed
Not disclosed No exact-asset power figure · campus
Amazon Pecos County Data Center Campus Amazon · Facility profile · Fort Stockton, TX Fort Stockton, TX ERCOT
Under Construction
Not disclosed No exact-asset power figure · campus
Amazon Web Services Facility profile · Euless, TX Euless, TX ERCOT
Unknown
Not disclosed No exact-asset power figure · facility
BBT Midland Data Center Big Bend Telephone Company · Facility profile · Midland, TX Midland, TX ERCOT
Operating
5 MW Critical IT Load · Target · campus
Beacon Westline Energy & Infrastructure Campus Westline TX Holdings LLC · Facility profile · Tom Green, TX Tom Green, TX ERCOT
Proposed
Not disclosed No exact-asset power figure · campus
Big Watt Digital and PowerHouse Taylor Technology Campus Big Watt Digital · Facility profile · Taylor, TX Taylor, TX ERCOT
Approved
Up to 1,000 MW Capacity basis unspecified · Target · campus
Bitter Blue — Building B Amazon Data Services Inc · Facility profile · San Antonio, TX San Antonio, TX ERCOT
Approved
Not disclosed No exact-asset power figure · building
Bitter Blue Campus Amazon Web Services · Facility profile · San Antonio, TX San Antonio, TX ERCOT
Proposed
Not disclosed No exact-asset power figure · campus
BlackChamber Cedar Creek Campus (Project Longhorn) BlackChamber · Facility profile · Cedar Creek, TX Cedar Creek, TX ERCOT
Proposed
About 490 MW Reported IT Power · Proposed · campus
Centersquare Dallas (DA1-Allen) Data Center Centersquare · Facility profile · Allen, TX Allen, TX ERCOT
Operating
12 MW Utility Service · Reported · facility · 2024-01
Charles Schwab Data Center Facility profile · Denton, TX Denton, TX ERCOT
Operating
Not disclosed No exact-asset power figure · building
CHRISTUS DATA CENTER CHRISTUS Health · Facility profile · San Antonio, TX San Antonio, TX ERCOT
Operating
Not disclosed No exact-asset power figure · facility
Cipher Colchis Data Center Campus Cipher Digital Inc. · Facility profile · San Angelo, TX San Angelo, TX ERCOT
Proposed
1,000 MW Contracted Power · Contracted · campus
Cipher Digital Barber Lake Facility profile · Colorado City, TX Colorado City, TX ERCOT
Under Construction
168 MW Critical IT Load · Reported · facility
Cipher Digital Black Pearl Data Center Cipher Digital Inc. · Facility profile · Wink, TX Wink, TX ERCOT
Under Construction
216 MW Critical IT Load · Contracted · campus
Cipher Digital Odessa Cipher Digital · Facility profile · Odessa, TX Odessa, TX ERCOT
Operating
207 MW Capacity basis unspecified · Reported · facility
Cipher Digital Stingray Cipher Digital · Facility profile · Andrews, TX Andrews, TX ERCOT
Under Construction
100 MW Capacity basis unspecified · Reported · facility
CISCO SYSTEMS DATA CENTER Cisco Systems Inc. · Facility profile · Allen, TX Allen, TX ERCOT
Operating
Not disclosed No exact-asset power figure · building
CITIGROUP TECHNOLOGY INC CITIGROUP TECHNOLOGY INC · Facility profile · Roanoke, TX Roanoke, TX ERCOT
Operating
Not disclosed No exact-asset power figure · facility
CloudBurst San Marcos Data Center I Cloudburst Texas, LLC · Facility profile · New Braunfels, TX New Braunfels, TX ERCOT
Under Construction
1,450 MW Campus Gross Power · Proposed · campus
Colovore Alliance DFW02 Data Center Colovore · Facility profile · Fort Worth, TX Fort Worth, TX ERCOT
Proposed
32 MW Capacity basis unspecified · Proposed · building
Colovore Mesquite DFW01 Data Center Facility profile · Mesquite, TX Mesquite, TX ERCOT
Under Construction
44.8 MW Capacity basis unspecified · Reported · building
Compass Red Oak Campus Compass Datacenters · Facility profile · Red Oak, TX Red Oak, TX ERCOT
Expanding
180 MW Energized Power · Operating · campus
Core Scientific Austin 1 Core Scientific · Facility profile · Austin, TX Austin, TX ERCOT
Operating
Not disclosed No exact-asset power figure · facility
Core Scientific Cottonwood 1 & 2 (Pecos) Core Scientific · Facility profile · Pecos, TX Pecos, TX ERCOT
Expanding
300 MW Utility Service · Reported · campus · Bitcoin mining
Core Scientific Hunt County Campus Core Scientific · Facility profile · Quinlan, TX Quinlan, TX ERCOT
Proposed
430 MW Utility Service · Reported · campus
CoreSpace Dallas CoreSpace, Inc. · Facility profile · Dallas, TX Dallas, TX ERCOT
Operating
2.5 MW Utility Service · Operating · facility
Cortex supercomputer Tesla, Inc. · Facility profile · Austin, TX Austin, TX ERCOT
Operating
130 MW Critical IT Load · Reported · building · Cortex 1 · 2025-05-15
Crusoe and Lancium Childress AI Data Center Campus Crusoe · Facility profile · Childress, TX Childress, TX SPP
Under Construction
1,000 MW Campus Gross Power · Proposed · campus
Csquare DFW3 Csquare · Facility profile · Dallas, TX Dallas, TX ERCOT
Operating
4.8 MW UPS capacity · Reported · facility
Csquare Fort Worth DFW1 Csquare · Facility profile · Fort Worth, TX Fort Worth, TX ERCOT
Operating
51.9 MW Utility Service · Reported · facility
CyrusOne Allen Campus (DFW3-DFW5) CyrusOne · Facility profile · TX TX ERCOT
Expanding
50 MW Critical IT Load · Reported · campus
CyrusOne Austin III CyrusOne · Facility profile · Austin, TX Austin, TX ERCOT
Operating
Not disclosed No exact-asset power figure · building
CyrusOne Dallas Carrollton DFW1 CyrusOne · Facility profile · Carrollton, TX Carrollton, TX ERCOT
Operating
45 MW Capacity basis unspecified · Reported · facility
CyrusOne DFW2 CyrusOne · Facility profile · Lewisville, TX Lewisville, TX ERCOT
Operating
12 MW Capacity basis unspecified · Reported · facility
CyrusOne San Antonio IV CyrusOne · Facility profile · San Antonio, TX San Antonio, TX ERCOT
Operating
Not disclosed No exact-asset power figure · facility
CyrusOne San Antonio SAT1 CyrusOne · Facility profile · San Antonio, TX San Antonio, TX ERCOT
Unknown
9 MW Critical IT Load · Reported · facility
D.R. Horton Arlington Data Center D.R. Horton · Facility profile · Arlington, TX Arlington, TX ERCOT
Operating
Not disclosed No exact-asset power figure · building
Dallas - Allen Data Center TierPoint, LLC · Facility profile · Allen, TX Allen, TX ERCOT
Operating
Not disclosed No exact-asset power figure · facility
Dallas Empire Central Data Center DataBank · Facility profile · Dallas, TX Dallas, TX ERCOT
Operating
4 MW Critical IT Load · Operating · facility · 2026-07-27
Danik Data Center Mahesh Patel · Facility profile · Dallas, TX Dallas, TX ERCOT
Operating
Not disclosed No exact-asset power figure · building
Data Center Building TX11 Vantage Data Centers · Facility profile · San Antonio, TX San Antonio, TX ERCOT
Under Construction
Not disclosed No exact-asset power figure · building
Data Foundry 00 Switch · Facility profile · Austin, TX Austin, TX ERCOT
Operating
400 MW Utility Service · Reported · facility
7 profiles
7
Development status
Approved 7
Closed 1
Expanding 9
Operating 102
Proposed 16
Under Construction 29
Unknown 10 Sources and coverage The inventory contains published facility, campus, building, and phase records. Power figures describe the exact asset, including a campus record's own campus capacity, and retain their basis, scope, status, and date. Records at different scopes are not additive, and a published project does not establish an operating load.
Geographic directories use the state and city recorded for each asset. Organization groups preserve published names and roles. Utility groups use the utility named in the facility record; individual profiles distinguish service agreements from service-territory matches. Each profile carries the sources and dates behind its facts.