Google Henderson Data Center
Operating
Google's Henderson data center is at 560 W Warm Springs Rd in Henderson, Clark County, Nevada, on a 59.95-acre parcel held by Jasmine Development LLC. Google broke ground in 2019 and Nevada regulators say the facility became fully operational in February 2021. It has ten cooling towers using potable water, and NDEP drafted an NPDES permit to discharge their blowdown to the Las Vegas Wash. A 2020 expansion brought Google's investment in the project to $1.2 billion.
Loading map…
Overview
- Status
- Operating
- Operating facility
- Site
- 59.95 acres
- Facility
- Compute profile
- Hyperscale
- Cooling design
- Reported
- Ten cooling towers using potable water
- Project scope
- Groundbreaking in 2019 on two parcels on West Warm Springs Road; the parcel's original construction year is 2020.
- Compute role
Power and grid
- Utility
- Southern California Edison Co
The site also falls inside the Nevada Power Co service territory.
- Substation
- Not identified
- Point of interconnection
- Not identified
- Interconnection request
- Not identified
- Pricing node
- SUNSETNV_LNODEBK3$36.49/MWh 30-day average
Facility and development
- Site area (acres)
- 59.95
- Construction
- Groundbreaking in 2019 on two parcels on West Warm Springs Road; the parcel's original construction year is 2020.
- Facility class
- Hyperscale
- Cooling systems
- Ten cooling towers using potable water
- Water permits