Google Jackson County Data Center
Operating
Google Jackson County Data Center is a Google campus at 48809 Alabama Hwy 277 in Bridgeport, Jackson County, Alabama, on 320 acres of the retired Widows Creek coal plant. Google announced the site in 2015 as a $600 million investment and opened the first data center in 2018, reusing the plant's electric transmission lines. The Tennessee Valley Authority is Google's electric utility here, and Google began building a solar farm in 2019 to supply the data center.
Loading map…
Overview
- Status
- Operating
- Operating campus
- Site
- 320 acres
- Campus
- Project cost
- $600.0M
- Estimated construction cost.
- Compute profile
- Hyperscale
- Project scope
- Built on the grounds of TVA's retired Widows Creek coal plant, reusing its electric transmission lines; Google broke ground and opened the first data center in 2018.
Power and grid
- Utility
- Tennessee Valley Authority
- Nearest substations
- Unnamed tap161 kV
- Unnamed substation161 kV
- Point of interconnection
- Not identified
Facility and development
- Site area (acres)
- 320
- Construction
- Built on the grounds of TVA's retired Widows Creek coal plant, reusing its electric transmission lines; Google broke ground and opened the first data center in 2018.
- Facility class
- Hyperscale
- Project cost (USD)
- 600,000,000
Organizations
Wiessner Enterprises LLCOwnerCampus