Hyperscale Data Michigan AI Data Center Campus
Under Construction
The Hyperscale Data Michigan campus is an existing data center at 415 E Prairie Ronde Street in Dowagiac, Cass County, Michigan, being converted from Bitcoin mining to AI computing. Alliance Cloud Services, a Hyperscale Data subsidiary, operates it and Indiana Michigan Power serves it. About 30 MW has been reported online, and a customer agreement covers an initial 20 MW of critical AI compute with the first 10 MW expected to be energized in December 2026. The company describes about 340 MW of potential total capacity, which depends on utility agreements and financing.