Hyundai Motor Group Metaplant America is a vehicle assembly plant at Ellabell in Bryan County, Georgia, that began production in October 2024. The plant buys grid electricity from Georgia Power and has a 15-year solar power purchase agreement with Matrix Renewables.
Loading map…
Overview
The plant broke ground in October 2022 and began production in October 2024. The Kia Sportage Hybrid joined the Hyundai IONIQ 5 and IONIQ 9 lineup in June 2026. The company describes a 2,900-acre megasite.
Profile
- Electricity and grid
- The Metaplant buys electricity from Georgia Power. Hyundai Motor Group signed a 15-year power purchase agreement with Matrix Renewables for the Metaplant and other U.S. plants.
- Permits and investment
- The plant operates under Georgia air permit 3711-029-0015-P-01-0. The Corps of Engineers decision document places the project site at Latitude 32.1584, Longitude -81.4533. The economic development agreement totals more than $7.5 billion.
Facility
- Activity
- Hyundai IONIQ 5 and IONIQ 9 and Kia Sportage Hybrid vehicles
- Industry
- Manufacturing
- Site type
- Campus
- Operating status
- Operating