Intel Ocotillo Campus
Large load · 4500 SOUTH DOBSON ROAD, Chandler, AZ
Intel's Ocotillo campus in Chandler, Maricopa County, Arizona is a semiconductor manufacturing site where Intel owns and operates Fabs 12, 22, 32 and 42, with two more fabs under construction. Salt River Project's High-Tech Interconnection Project provides approximately 630 MW of load serving capacity to the facility. Campus energy use was 2,111,443 MWh per year.
Overview
Intel owns and operates semiconductor fabs 12, 22, 32 and 42 at its 682-acre Ocotillo campus in Chandler, Maricopa County, Arizona. Panther Lake and Clearwater Forest products built on Intel 18A are being manufactured at Fab 52. Fab 62 is under construction, with operations expected to begin by the end of 2028.
Profile
- Electricity and grid
- SRP's High-Tech Interconnection Project will provide approximately 630 MW of load serving capacity to the facility, with a dedicated Parlett Substation and 230 kV lines. SRP is also building a 230kV substation on Intel's campus with lines connecting to the Schrader and Henshaw Substations. The campus reported energy use of 2,111,443 MWh per year.
- Renewable supply and onsite generation
- Intel purchases renewable electricity from SRP's 100 MW East Line Solar project in Coolidge, Arizona, which began supplying the facility in December 2020, and generates electricity from a 7.7 megawatt solar carport. SRP and Intel also reached a 15-year agreement for energy from a solar plant to support the Ocotillo campus.
Facility
- Activity
- Semiconductor fabrication buildings (fabs)
- Industry
- Manufacturing
- Site type
- Campus
- Operating status
- Operating
Reported Jul 8, 2024
Permits and agreements
- Agreement
- 15-year agreement with SRP to provide energy from a solar plant
Related records
Timeline
- Jul 8, 2024
- NIST environmental assessment describes Fabs 12, 22, 32, 42 and construction of Fabs 52 and 62
www.nist.gov