LG Energy Solution Michigan-Lansing is a battery cell plant in Delta Township, Eaton County, Michigan, that began production on August 18, 2026. Lansing Board of Water & Light supports the plant with transmission construction and a special electric rate. In December 2021 BWL discussed serving a prospective manufacturer needing 100 megawatts at an 80 percent load factor.
Loading map…
Overview
- Requested connection
- 100 MW
- planned · Dec 14, 2021
LG Energy Solution announced the start of production at its 226-acre Lansing facility. The plant produces LFP cells for energy storage and plans NMC cells for Toyota electric vehicles. It aims to reach more than 35 GWh of annual capacity.
Profile
- Electricity and grid
- Lansing Board of Water & Light contractors performed transmission work to support the plant in Delta Township. BWL discussed a manufacturing customer requiring 100 megawatts at an 80 percent load factor on a 20-year contract. BWL commissioners passed a special electric rate for Ultium, and BWL is connected to MISO.
- Ownership and permits
- LG Energy Solution owns the plant outright and it is no longer a GM joint venture. EGLE issued air Permit to Install 139-22A at 7111 Davis Highway.
Facility
- Activity
- LFP battery cells for energy storage systems
- Industry
- Manufacturing
- Site type
- Facility
- Operating status
- Operating