Peregrine Solar
EIA and CPS Energy report commercial operation beginning in February 2025; RWE announced the completed project in May 2025. RWE acquired that business in March 2023, and CPS Energy consented to the ownership change.
EIA and CPS Energy report commercial operation beginning in February 2025; RWE announced the completed project in May 2025. RWE acquired that business in March 2023, and CPS Energy consented to the ownership change.
EIA, RWE, and CPS Energy
EIA and CPS Energy
CPS Energy
10-year commitment
PERE_SLR_UNIT1 · PERE_SLR_UNIT2
EIA and RWE
25-year PPA
EIA and CPS Energy
Similar plants ranked by technology, capacity, and distance.
Operating generator records and technology attributes reported through EIA-860.
| Generator | Capacity | Technology | Operation | Status |
|---|---|---|---|---|
| PSPV | 300 MW 300 MW summer | Solar Photovoltaic Solar · PV | Feb 2025 | Operating |
Monthly EIA generation history and recent market-resource behavior where linked telemetry is available.
Deterministic links to ERCOT market resources, price records, outage disclosures, queue records, and nearby infrastructure. Candidate joins remain labeled until corroborated.
Source-backed project transactions, agreements, land records, permits, and environmental disclosures. Portfolio and adjacent-project facts remain explicitly scoped.
Parties, market resources, and identifiers tied to this asset, with owner, operator, developer, EPC, compliance provider, and interconnecting entity roles kept separate.
Drag organizations to explore the network. Select a node to pin its details and available page link.
Project milestones and public references behind the asset profile.
EIA and CPS Energy report February 2025.
ERCOT SCED disclosure is delayed, so plant performance windows end at the latest disclosed interval.
Monthly generation is reported through EIA-923. Capacity factor uses the current EIA nameplate capacity and is shown only for complete calendar years.
2 ERCOT market resources · Solar
Capacity factor is average output vs. this plant's observed peak.
Observed ERCOT settlement prices at PERE_SLR_RN over 363 days (2025-09-11 to 2026-09-10).
The TB2 figure is a price benchmark, not revenue: it values one perfect-foresight cycle per day between the 2 cheapest and 2 dearest hours of each day, gross of round-trip losses, and excludes ancillary services and any physical dispatch constraint. It describes what this node’s price shape was worth over the window — it is not this asset’s realized capture, and no dispatch is assumed or modelled.
Matched to the latest available ERCOT generation-interconnection queue record. Queue status and completion dates describe the queue record; operating status is verified separately against plant and market registrations.
| Largest reported plants | Capacity | State | |
|---|---|---|---|
| Bright Arrow Solar, LLC | 403.6 MW | TX | |
| Cartwheel 1 - Storage, LLC | 300 MW | TX | |
| Peregrine SolarCurrent | 300 MW | TX | |
| Fifth Standard Solar PV, LLC (Hybrid) | 287 MW | CA | |
| Radfords Run Wind Farm | 278 MW | IL | |
| Emily Solar, LLC | 273.6 MW | IL | |
| Copper Mountain Solar 3 | 255 MW | NV | |
| Copper Mountain Solar 5, LLC | 252 MW | NV |
Portfolio membership follows the latest EIA-860 reporting entity. It does not imply ultimate ownership.
View full reporting portfolioAnswered from the published record above. Questions whose inputs this profile does not carry are omitted rather than estimated.
Peregrine Solar has a reported capacity of 300 MW. Source: RWE Peregrine completion.
Peregrine Solar is a Solar Photovoltaic facility in Goliad County, TX, participating in the ERCOT market.
Peregrine Solar is in Goliad County, TX, inside the ERCOT balancing area.
Peregrine Solar is operated by RWE Clean Energy according to the EIA generator inventory. Reporting membership does not by itself establish ultimate ownership.
Peregrine Solar reports a commercial operation date of 2023. Current status: operating. Source: RWE Peregrine completion.
Peregrine Solar reported 704.2 GWh over the twelve months to 2026-06. Figures are net generation as filed to EIA-923.
By capacity, Peregrine Solar ranks #38 of 7,234 operating plants of the same technology nationally. It ranks #22 of 231 in TX.