Project Forge, also called the Green Fig data center, is a campus under construction at 13 S. Bacton Hill Road in East Whiteland Township, Chester County, Pennsylvania. Sentinel Data Centers is the developer, and the approved plan has two data center buildings of 750,000 square feet each. The site is grid-served by PECO, with an initial 150 MW load planned for 2026 and a maximum peak draw of 290 MW. As of October 2026 the township had issued no further permits and construction had stopped twice over permit concerns.