Overview
ERCOT's public large-generation interconnection queue, with project identity, developer, proposed point of interconnection, transmission owner, technology, requested MW, queue status, and proposed or actual completion dates. Each posting is a snapshot, so current project claims must use the latest snapshot rather than count every vintage. Queue inclusion and proposed dates do not establish available transmission headroom, study outcome, approval, construction probability, or an operating asset. The official source is ERCOT's GIS Report.
Use with MCP
This table is readable two ways, over the same guarded boundary. Over HTTP: POST /api/v1/datasets/ercot_interconnection_queue/query, described in the API reference. Or from an MCP client: connect a market below, then use search_data or describe_data to load its query contract before calling query_data.
Schema20
event_timeDateTime64(6, 'UTC')snapshot_timeDateTime64(6, 'UTC')queue_idLowCardinality(String)project_nameNullable(String)interconnecting_entityNullable(String)countyNullable(String)stateNullable(String)interconnection_locationNullable(String)transmission_ownerNullable(String)generation_typeNullable(String)capacity_mwNullable(Float64)summer_capacity_mwNullable(Float64)winter_capacity_mwNullable(Float64)queue_dateNullable(DateTime64(6, 'UTC'))statusNullable(String)proposed_completion_dateNullable(DateTime64(6, 'UTC'))withdrawn_dateNullable(DateTime64(6, 'UTC'))withdrawal_commentNullable(String)actual_completion_dateNullable(DateTime64(6, 'UTC'))ingested_atDateTime64(6, 'UTC')Sample rows
| event_time | snapshot_time | queue_id | project_name | interconnecting_entity | county | state | interconnection_location | transmission_owner | generation_type | capacity_mw | summer_capacity_mw | winter_capacity_mw | queue_date | status | proposed_completion_date | withdrawn_date | withdrawal_comment | actual_completion_date | ingested_at |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 2030-12-31 00:00:00.000000 | 2026-04-02 00:00:00.000000 | 29INR0158 | NRG Prairie Energy Center | NRG Prairie Energy Center LLC | Hill | Texas | Tap 345 kV 1907 Venus Switch - 3383 Bynum ckt 1. | ∅ | GAS/CC | 1253 | ∅ | ∅ | 2030-12-31 00:00:00.000000 | Active | 2030-12-31 00:00:00.000000 | ∅ | ∅ | ∅ | 2026-07-05 02:48:35.572710 |