Natural Gas Fired Combined CycleNYISO · Onondaga Countyplant:plant-10621

CH Resources Syracuse

Lakeside Syracuse LLC - Onondaga County - NYISO

CH Resources Syracuse is an operating 102.7 MW natural-gas-fired combined-cycle facility located at 300 Belle Island Road, Solvay, Onondaga County, New York. The facility is equipped with a Siemens V64.3 stationary gas turbine, SCR emissions control, and emergency diesel backup equipment. The plant originally operated as a cogeneration facility selling electricity to Niagara Mohawk Power Corporation and steam to the New York State Fairgrounds; both contracts terminated by mid-1998, after which the facility sold electricity wholesale into the NYISO market. The facility is currently owned by Lakeside Syracuse LLC (100% subsidiary of Vistra Corp.) and connected to the Niagara Mohawk transmission system at 115 kV in NYISO Zone C. It generated 16.1 GWh annually as of 2024.

Overview

Key fields

Nameplate capacity
102.7 MW

Canonical EIA plant baseline.

Registry anchor
Plant 10621

plant-10621

Structured profile

Technology
Natural Gas Fired Combined Cycle
Operator
Lakeside Syracuse LLC

Units and generators

Operating generator records and technology attributes reported through EIA-860.

GeneratorCapacityTechnologyOperationStatus
GEN165.5 MW
57.4 MW summer
Natural Gas Fired Combined Cycle
Natural Gas · CT
Jan 1994Operating
GEN237.2 MW
28.8 MW summer
Natural Gas Fired Combined Cycle
Natural Gas · CA
Jan 1994Operating

Performance

Monthly EIA generation history and recent market-resource behavior where linked telemetry is available.

Peer context

Technology capacity
102.7 MW
Natural Gas Fired Combined Cycle
National rank
#455
of 538 operating peers
NY rank
#21
of 39 operating peers

Monthly generation

Download CSV
Latest 12 months
16.1 GWh
Reported net generation
Latest report
Dec 2024
EIA-923 monthly filing
2024 capacity factor
1.8%
Using current reported nameplate capacity
Jan 2022: 714 MWh2022-01Feb 2022: 0 MWhMar 2022: 637 MWhApr 2022: 0 MWhMay 2022: 0 MWhJun 2022: 621 MWhJul 2022: 0 MWh2022-07Aug 2022: 22 MWhSep 2022: 743 MWhOct 2022: 0 MWhNov 2022: 0 MWhDec 2022: 0 MWhJan 2023: 0 MWh2023-01Feb 2023: 1.3 GWhMar 2023: 74 MWhApr 2023: 0 MWhMay 2023: 0 MWhJun 2023: 4 MWhJul 2023: 4.5 GWh2023-07Aug 2023: 0 MWhSep 2023: 5 GWhOct 2023: 0 MWhNov 2023: 0 MWhDec 2023: 0 MWhJan 2024: 0 MWh2024-01Feb 2024: 488 MWhMar 2024: 0 MWhApr 2024: 0 MWhMay 2024: 0 MWhJun 2024: 6.5 GWhJul 2024: 5 GWh2024-07Aug 2024: 3.6 GWhSep 2024: 74 MWhOct 2024: 0 MWhNov 2024: 0 MWhDec 2024: 437 MWh2024-12

Monthly generation is reported through EIA-923. Capacity factor uses the current EIA nameplate capacity and is shown only for complete calendar years.

Grid and market context

Deterministic links to ERCOT market resources, price records, outage disclosures, queue records, and nearby infrastructure. Candidate joins remain labeled until corroborated.

Nearby substations

HIFLD infrastructure inventory
IN SERVICE · 115 kV
0.1 km
IN SERVICE · 115 kV
0.3 km
IN SERVICE · 115 kV
0.4 km
IN SERVICE · 115 kV
0.5 km
IN SERVICE · 115 kV
0.6 km

Commercial, land, and environmental record

Source-backed project transactions, agreements, land records, permits, and environmental disclosures. Portfolio and adjacent-project facts remain explicitly scoped.

Transactions and agreements

Construction Commenced
1991
EPA records state that according to CH Resources, Syracuse Unit 1 commenced construction in 1991 or 1992.
CH Resources, Inc.
epa.gov
Contract Termination
Jul 1997
The power purchase agreement with Niagara Mohawk Power Corporation was terminated. From July 1997, all electrical output was sold to wholesale customers under short-term contracts.
CH Resources, Inc. · Niagara Mohawk Power Corporation
epa.gov
Contract Termination
Jun 1998
The steam purchase contract with the New York State Fairgrounds was terminated. EPA states that CH Resources purchased the unit before 1998.
CH Resources, Inc. · New York State Fairgrounds
epa.gov

Related parties and identifiers

Parties, market resources, and identifiers tied to this asset, with owner, operator, developer, EPC, compliance provider, and interconnecting entity roles kept separate.

Relationship graph

Drag organizations to explore the network. Select a node to pin its details and available page link.

AssetEquipmentOwner / operatorOfftaker

Parties and identifiers

RelationshipEntityBasis
Parent companyVistra Corp.parent company
Equipment supplierSiemensOEM gas turbine supplier
Transmission owner / interconnecting utilityNiagara Mohawk Power Corp. (National Grid)transmission/distribution owner
Former owner / sponsorCH Resources, Inc.historical owner and project sponsor
Former ownerWPS Empire Statepredecessor owner
Portfolio owner / sellerLotus Infrastructure PartnersFinancing covers a portfolio that includes CH Resources Syracuse.
OfftakerNiagara Mohawk Power Corporationformer electricity purchaser
OfftakerNew York State Fairgroundsformer steam purchaser
Grid selectionplant:plant-10621Canonical asset page /nyiso/assets/plant/ch-resources-syracuse.

Reporting portfolio

EIA reporting entity
Lakeside Syracuse LLC
Entity 58337
Operating portfolio
1 plants
1 states
Reported capacity
102.7 MW
Natural Gas Fired Combined Cycle

Portfolio membership follows the latest EIA-860 reporting entity. It does not imply ultimate ownership.

Timeline and sources

Project milestones and public references behind the asset profile.

Project timeline

  1. Construction commenced (1991 or 1992)epa.gov

    EPA records state that according to CH Resources, Syracuse Unit 1 commenced construction in 1991 or 1992.

  2. Generators enter operationEIA-860

    EIA-860 lists generator GEN1, generator GEN2 with this operating date.

  3. Electricity purchase agreement with Niagara Mohawk terminatedepa.gov

    The power purchase agreement with Niagara Mohawk Power Corporation was terminated. From July 1997, all electrical output was sold to wholesale customers under short-term contracts.

  4. Steam purchase agreement with New York State Fairgrounds terminatedepa.gov

    The steam purchase contract with the New York State Fairgrounds was terminated. EPA states that CH Resources purchased the unit before 1998.

  5. Transfer from WPS Empire State to Lakeside New York LLCdocuments.d...

    Lakeside New York LLC acquired the New York facilities (Syracuse and Beaver Falls) from WPS Empire State through ownership of Lakeside Syracuse LLC and Lakeside Beaver Falls LLC.

Common questions about CH Resources Syracuse

Answered from the published record above. Questions whose inputs this profile does not carry are omitted rather than estimated.

How big is CH Resources Syracuse?

CH Resources Syracuse has a reported capacity of 102.7 MW. Source: EIA Form 860M.

What kind of plant is CH Resources Syracuse?

CH Resources Syracuse is a Natural Gas Fired Combined Cycle facility in Onondaga County, NY, participating in the NYISO market.

Where is CH Resources Syracuse located?

CH Resources Syracuse is in Onondaga County, NY, inside the NYISO balancing area.

Who operates CH Resources Syracuse?

CH Resources Syracuse is operated by Lakeside Syracuse LLC according to the EIA generator inventory. Reporting membership does not by itself establish ultimate ownership.

How much electricity does CH Resources Syracuse generate?

CH Resources Syracuse reported 16.1 GWh over the twelve months to 2024-12. Figures are net generation as filed to EIA-923.

How does CH Resources Syracuse compare to other plants?

By capacity, CH Resources Syracuse ranks #455 of 538 operating plants of the same technology nationally. It ranks #21 of 39 in NY.

Related assets

Similar plants ranked by technology, capacity, and distance.

Asset analyst
plant:plant-10621

Ask about CH Resources Syracuse

Investigate technology, capacity, output, price behavior, ownership, and related facilities using this profile plus current grid data.