Dominion’s October Demand Rose 12.2% as PJM Revisits Data-Center Growth
A new independent forecast tests how much future data-center demand the supply pipeline can support. Measured growth already varies sharply across PJM’s operating areas.
Dominion’s average electricity demand reached 15.21 GW in October, up 12.2 percent from the same month in 2025. AEP’s average rose 6.3 percent; the Mid-Atlantic’s was nearly unchanged. Ask the Grid’s comparison covers every hour of both months, showing how differently demand is growing across PJM’s operating areas.
Those differences give a physical backdrop to the independent data-center forecast Charles River Associates presented to PJM on November 2. Its softer supply-constraint scenario reaches 30 GW of data-center demand in 2030. The gap against its reliability-constrained deployment view reaches approximately 11.5 GW that year. Which projects receive power depends partly on which supply projects arrive.
Demand growth extends into the night#
Dominion’s demand rose at every clock hour
October 2025 and 2026 · preliminary load averaged at each Eastern clock hour
- October 2025
- 12.01 GW
- October 2026
- 13.58 GW
- Same-hour change
- +1.57 GW
Source: PJM preliminary hourly load; Ask the Grid calculation. Each curve averages all 31 October days. Total-area demand; not weather-normalized.
PJM preliminary hourly demand; Ask the Grid calculations. Complete 744-hour October months, 31 observations per clock-hour bucket and area. Profiles show means by clock hour, not a single operating day. Not weather-normalized and not a measure of data-center consumption.
Dominion’s increase appears throughout the average October day. At 3 a.m. Eastern, preliminary load averaged 13.58 GW, up 1.57 GW from October 2025. Its mean load was higher at every clock hour. The change therefore reaches beyond the evening’s highest-demand hours.
These are total operating-area loads. Weather, customer growth, industrial activity and data centers can all contribute; this comparison does not separate their effects. Selecting the other areas reveals why a single regional growth rate can conceal different local planning questions.
The supply pipeline has several stages#
The generation pipeline is much larger than the group under construction
AEP and Dominion transmission footprints · requested generation capacity · November 4, 2026 snapshot
65% of AEP’s under-construction requested MW comes from solar-only entries.
Source: PJM generation interconnection queue. Separate groups in one snapshot; requested MW carries no guarantee of peak contribution or delivery date.
PJM public generation interconnection queue, snapshot 2026-11-04T11:00:22.561486Z; Ask the Grid calculation. Bars group entries by their source development status and transmission owner. Capacity is requested MW, not accredited capacity, dedicated data-center supply or a construction schedule. Solar-only excludes mixed-technology projects.
PJM’s November 4 queue snapshot lists 21 generation entries totaling 3.37 GW under construction in AEP’s transmission footprint, and 24 totaling 4.92 GW in Dominion’s. Separate groups remain in engineering and procurement or are already partly in service while construction continues.
Technology changes what those figures mean for reliability. Solar-only projects account for 65 percent of AEP’s under-construction requested MW and 54 percent of Dominion’s. Requested capacity describes the interconnection proposal; dependable capacity during a particular peak depends on the resource, its operating conditions and PJM’s accreditation rules. These projects also serve the wider system rather than a designated set of data centers.
The forecast tests what can actually connect#
CRA screened utility submissions for agreements, permitting progress, timing and local restrictions, then combined the project view with national demand assumptions. It also changed supply assumptions: active Reliability Resource Initiative projects receive their full listed capacity, four expedited projects add about 2.6 GW of installed capacity in 2029, and Homer City is assumed to begin operating in late 2029.
That makes the 11.5 GW difference a scenario result about demand and available power in 2030. PJM’s July auction produced a separate 6.83 GW accredited-capacity shortfall for 2028/2029. The two figures use different horizons and methods; they cannot be added or treated as successive readings of one shortage.
For developers and planners, the next useful evidence is project delivery: signed load commitments, construction milestones, operating dates and accredited supply in the zones where demand is rising. PJM’s next long-term forecast, expected in January, will show how the new information enters the regional planning baseline.
Sources and method
Demand uses PJM’s preliminary hourly series, retaining its latest available restatement. Each October contains 744 hours; each clock-hour profile averages 31 observations in Eastern time. Comparisons are not weather-normalized. Queue groups use one November 4 snapshot and the transmission-owner field; entries and requested MW are separate measures. All proposed-completion dates in the displayed groups were unfilled, so the figure compares stages rather than promising delivery dates. Sources: PJM demand, generation queue, CRA’s November 2 presentation, and PJM’s July auction account. The January forecast timing is attributed to PJM’s statement to Utility Dive.