BriefingERCOT

Texas Resumes Environmental Permit Reviews for Data Centers

The state restarted permit reviews in November. ERCOT targeted December 10 for its separate eligibility and community-impact reports.

Texas resumed environmental permit reviews for data centers in mid-November. The governor’s office notified the Texas Commission on Environmental Quality (TCEQ) on November 13 that ERCOT had finished gathering information on community impacts. TCEQ said in a written statement reported on November 17 that it had returned to its normal permit review process. The restart followed a September 21 directive that paused environmental permitting for data center projects.

What Texas reopened#

Texas’s environmental regulator handles applications such as air permits and stormwater authorizations for construction. In its October 19 response to the governor, TCEQ said it had paused issuance of permits for data center construction and directly supporting infrastructure and was screening other claimed authorizations. With normal review restored, TCEQ can consider applications under the usual state and federal requirements.

Agency records show how that works at individual sites. On November 17, TCEQ acknowledged an air permit-by-rule registration covering certified emissions for BT Gateway’s Royse City Data Center in Hunt County. On November 20, it issued a standard air permit covering emissions from specified generating units at Prime Data Centers’ AUS02 facility in Caldwell County. Each record covers a defined environmental authorization.

ERCOT still has a separate grid approval process#

ERCOT’s September board briefing tied its pause on first energization for new data centers and crypto mines of 75 MW or more to completion of both its eligibility audit and its community-impact review. The public PUCT docket, checked November 27, showed no order lifting that pause. ERCOT’s current instructions still require its approval before a covered large load can energize.

ERCOT’s broader interconnection queue includes data centers and other large electricity users at different stages. Its November 5 community-impact update describes a specific survey population. ERCOT reported responses from 433 of 465 loads. Those responses informed the community-impact review. A separate eligibility process assesses whether large loads qualify for Batch Zero, ERCOT’s coordinated reliability study.

ERCOT targeted December 10 to file its separate Batch Zero eligibility report and community-impact report with the Public Utility Commission of Texas. The eligibility filing is the next step toward final Batch Zero classifications.

For the history of the interconnection pause, see our August briefing on the state’s data center audit.

Daytime exterior of the Equinix Infomart Dallas data center beside Interstate 35E, with the Dallas skyline behind it.
Equinix's Infomart Dallas, an operating data center inside the ERCOT footprint. Photo: Andrew nyr / Wikimedia Commons, CC BY-SA 4.0.