ACS Hicks Field Data Center
Under Construction
The Hicks Field Data Center is a five-building data center campus on about 107 acres in far northern Fort Worth, Tarrant County, Texas. The owner states in an October 2026 filing that the project is under construction. A signed facility extension agreement with Oncor carries a load ramp with a maximum of 335 MW. The campus is in the ERCOT market as Batch Zero project BZ-129, and a privately owned substation is planned beside an existing Oncor substation.
Overview
Campus power
- Up to 335 MW
- Utility Service · Contracted
- Status
- Under Construction
- Under Construction
- IT floor area
- Not disclosed
- Campus
- Cooling design
- Reported
- Water loop system planned to decrease water used on the site
- Project scope
- Building-level square footage from the state accessibility registration
- Power and grid
Power and grid
| Capacity | Basis | Status | Scope | As of |
|---|---|---|---|---|
| Up to 335 MW | Utility Service | Contracted | Exact Asset | — |
| Maximum load ramp in the signed facility extension agreement for the Hicks Field campus, not energized demand | ||||
- ISO / RTO
- ERCOT
- Substation
- Privately owned substation planned for the development, close to an existing Oncor substation
- Queue identifiers
- ERCOT Batch Zero BZ-129 · ERCOT legacy large-load project LLI-1345
Facility and development
- Cooling systems
- Water loop system planned to decrease water used on the site
- Utility agreements
- Transmission/Substation Facility Extension Agreement with Oncor executed February 22, 2026
- Grid record
- ERCOT · Privately owned substation planned for the development, close to an existing Oncor substation
ERCOT Batch Zero BZ-129 · ERCOT legacy large-load project LLI-1345 · PUCT Control Number 60425
- Regulatory record