Amazon Horizon Junction Data Center Campus
Proposed
Horizon Junction is an Amazon Data Services campus on about 485 acres in Floyd County, Texas, with a Floydada mailing address. Amazon bought the land in June 2026, and the county has considered a tax abatement for about 7 data center buildings with improvements over a billion dollars. State filings schedule three data center buildings for construction from August 2026 to April 2027, and Amazon filed air permit applications in August. No electrical load, utility or interconnection figure has been published for the site, and the county has said it wants any abatement tied to an air-cooled design and on-site electricity supply.